Dredging Project Specifications
Dredging Project Specifications
Dredging Project Specifications
RFP # __________
12-01
SECTION 1
SUMMARY OF WORK
1.1 BACKGROUND
The South Fork Rivanna Reservoir (Reservoir) is a water supply reservoir on the South Fork
Rivanna River, Albemarle County, Virginia. The Reservoir extends from its dam upstream to the
Reas Ford Road (Route 660) Bridge, and includes portions of Ivy Creek, a major tributary to the
Reservoir (see Exhibit 1). The Reservoir is owned by the City of Charlottesville, and provides
potable water to the RWSA and its customers.
In 2009, HDR Engineering, Inc. (HDR) was tasked by RWSA to evaluate the feasibility of
dredging the Reservoir. HDR’s study evaluated dredging accumulated sediments both within the
area of the available water supply volume (Reservoir areas above the water supply intake
elevation) as well as areas below the water supply intake. As part of this study, HDR produced a
series of task reports as follows:
During Phase I of the study, HDR determined that most of the sediment in the Reservoir is
located in the upper reaches of the mainstream Reservoir and in Ivy Creek. Sampling and analysis
did not identify environmental contamination in the sediment. The sediment is primarily
composed of sand, silt, and clay-sized particles, with sand predominant in the uppermost reaches
of the mainstream Reservoir. Some sediment deposits have become vegetated wetlands.
Phase II of the study evaluated dredging alternatives, dewatering and processing site alternatives,
and the possibilities of re-using the sediment. HDR’s study included identifying suitable sites for
various dredging activities. As part of the site search, HDR contacted various landowners and
other stakeholders. Only sites with “willing landowners” are discussed within HDR’s reports. A
“willing landowner” is one that has given HDR permission to publicly evaluate and discuss the
potential feasibility of using their site or sites for a dredging project – however, this does not
represent a commitment on the part of the landowner for such use to occur. Any such
commitment of private property would be subject to future agreement between the property
owner and the Dredging Contractor.
HDR separated the Reservoir into seventeen (17) segments in three sections for study purposes
[see Exhibit 2]. Reas Ford Road Bridge was used as the uppermost limit of the main stem of the
Reservoir. The Upper Main Stem of the Reservoir extends from Reas Ford Road Bridge to the
Earlysville Road Bridge, a distance of approximately 4.1 miles. The Lower Main Stem of the
1
South Fork Rivanna Reservoir
Dredging Project Specifications
Reservoir extends from the Earlysville Road Bridge to the Dam, a distance of approximately 1.6
miles. The Ivy Creek portion of the Reservoir extends from the Woodlands Road Bridge
upstream approximately 0.7 miles. Sediment volume was estimated for each segment based on
2009 bathymetric data showing top of sediment compared to estimated original contours.
As shown in Table 1, restoring the Reservoir to its original contours and shoreline configuration
would require removal of approximately 1,742,567 cy of material. HDR recommended no-
dredge buffer areas be established along the shoreline to protect wetland areas and alongside the
bridges that cross the Reservoir. Removing these recommended no-dredge areas from
consideration reduces the estimated maximum potential removable volume of sediment to
1,541,000 cy for the entire Reservoir.
HDR also recommended that dredging be focused on the Upper Main Stem (Reas Ford Road
Bridge to Earlysville Road Bridge) and Ivy Creek. Based on that recommendation, HDR
proposed a minimum dredging target of 748,000 cy to restore as much useable volume as
practical given respective no-dredge buffers. A maximum dredging target restoring as much total
volume as practical would be 1,422,000 cy, based on the approximately 1,192,000 cy of sediment
to be removed from the Upper Main Stem Reservoir plus 230,000 cy of sediment to be removed
from Ivy Creek.
HDR developed a two-part conceptual dredging approach to maximize the dredging volume: Part
I would hydraulically dredge Reservoir segments 1 – 3 (the uppermost portion of the Upper Main
Stem beginning at the Reas Ford Road Bridge), dewater the sediment using mechanical
dewatering equipment, and sell or reuse the recovered sediment materials (largely sand) to off-set
the cost of dredging. HDR estimated that approximately 290,324 cubic yards of sediment could
reasonably be removed from the upper three segments comprising Part I.
2
South Fork Rivanna Reservoir
Dredging Project Specifications
Part II would dredge Reservoir segments 4 – 9 (the remainder of the Upper Main Stem down to
the Earlysville Road Bridge) and/or Ivy Creek and dewater the sediment using three confined
dike facilities. HDR assumed dredged sediments removed in Part II would remain in the confined
dike facilities and there would be no recovery of material based on conditions imposed by the
willing landowners. The two part dredging approach could be conducted independently,
simultaneously or in sequence, depending on available resources. HDR estimated that
approximately 835,686 cubic yards of material could reasonably be removed and dewatered
within the space available for confined dike facilities.
The HDR reports and other reference materials cited above are incorporated by reference, and are
available at:
www.rivanna.org/southfork/index.htm
The HDR reports, other reference materials cited above and other information or data supplied by
RWSA or HDR is presented for informational purposes only. RWSA and HDR do not guarantee
the accuracy or validity of the information or data, nor do they assume any responsibility for the
Dredging Contractor’s interpretation of the data.
3
South Fork Rivanna Reservoir
Dredging Project Specifications
4
South Fork Rivanna Reservoir
Dredging Project Specifications
E. The Dredging Contractor shall submit an Environmental Protection Plan for Owner’s
review prior to contract award. The contents of the Environmental Protection Plan are
described in Section 3.
F. The Dredging Contractor is responsible to perform all work in accordance with all
applicable federal, state, and local rules and regulations, including, but not limited
to, all permit conditions for the project.
G. The Dredging Contractor is responsible for all labor, supervision, equipment, and
materials required for dredging, staging, and dewatering, transport, delivery,
processing and disposal or final placement of all dredged material.
H. During all project activities, the Dredging Contractor is responsible to use Best
Management Practices (BMPs) to minimize the re-suspension of sediments to the
water column during dredging, to minimize the turbidity of any effluent
discharged from sediment dewatering, and to minimize erosion of disturbed land
areas.
I. The Dredging Contractor shall not stockpile any dredged material in wetland or
upland areas outside of the designated area(s) as specified by project plans. All
dredged material removed from the Reservoir is to be transported directly to the
staging area and/or dewatering area, and from the staging or dewatering area directly
to the placement site, or otherwise placed in accordance with project plans.
B. The Contactor shall be responsible for meeting all permit conditions for the project as
required by federal, state, and local governments. For any additional permit
requirements, the Contactor will be responsible for providing all surveys, engineering
and other assessments, and design services necessary for modifying existing permits
or obtaining new permits for dredging, dewatering, and effluent discharge, transport
and placement of the dredged material at their own cost.
5
South Fork Rivanna Reservoir
Dredging Project Specifications
work for the consideration set forth in is/her Bid. The submission of a Proposal shall
constitute and imply full knowledge of such conditions and regulations and acceptance
of the risks therein contained.
B. Where data on Reservoir conditions, sediment depths and characterizations have been
made available, it is understood that the data was developed in the usual manner and
with reasonable care, and such data, including location, depths and the character of
the sediment material have been recorded in good faith. There is no expressed or
implied agreement that the depths or the character of the material have been
correctly indicated, and Dredging Contractors should take into account the
possibility that conditions affecting the work to be done may differ from those
indicated. The Reservoir exists primarily to provide potable water to users in
Albemarle County and City of Charlottesville. RWSA manages the water level within
the Reservoir to maintain an adequate water supply volume in accordance with
available water flow, water demand, and federal, state and local permit requirements,
including mandatory minimum discharge flows. Water levels in the Reservoir may
fluctuate based on RWSA’s management of the Reservoir. Withdrawal of water from
the Reservoir for potable water supply by RWSA will take precedence over all other
uses of the Reservoir, including dredging. RWSA’s management of the Reservoir shall
not be a basis for an adjustment in the Contract Price or a claim for damages by the
Dredging Contractor. If RWSA’s management of the Reservoir restricts planned
dredging activity, the Dredging Contractor may request an extension of the project
schedule for an equivalent period or as agreed to by Owner.
C. The South Fork Rivanna River and its tributaries feeding the Reservoir occasionally
experience periods of low flow; extended periods of low flow can cause the level of
the Reservoir to drop. Periods of low flow can occur, but are not limited to, July
through October. The effects of periods of low flow, including reduced levels in the
Reservoir, may be more pronounced in the upper reaches of the Reservoir.
D. The Reservoir is frequently used by recreational boaters, the University of Virginia
Men’s and Women’s Rowing Teams and the Rivanna Rowing Club, and is the site of
rowing development camps and/or competitive meets or other events.
E. The South Fork Rivanna River and its tributaries, including the Reservoir, are subject
to periodic and potentially sudden rises in water surface elevations due to storm
events. Storm events can cause the River and its tributaries, including the Reservoir,
to overflow their banks and floodplain.
F. The Dredging Contractor shall be responsible for monitoring weather conditions and
identifying hazards likely to arise from weather conditions during the project. The
Dredging Contractor is responsible for taking all necessary and reasonable
corrective actions, including the use of safety devices, to address hazards likely
to arise from weather conditions during the project.
6
South Fork Rivanna Reservoir
Dredging Project Specifications
C. The HDR reports and other reference materials cited above in Section 1.1 are
incorporated by reference, and are available at:www.rivanna.org/southfork/index.htm
The HDR reports and other data supplied to Dredging Contractors are presented for
informational purposes only. The Owner does not guarantee the accuracy or validity
of the information within these reference materials, nor do they assume any
responsibility for the Dredging Contractor's interpretation of the data.
7
South Fork Rivanna Reservoir
Dredging Project Specifications
END OF SECTION
8
South Fork Rivanna Reservoir
Dredging Project Specifications
SECTION 2
DETAILS OF WORK
2.1 GENERAL SCOPE
The work consists of furnishing all labor, supervision, bonds, insurance, materials,
plant and equipment, for performing all operations necessary in connection with the
dredging of South Fork Rivanna Reservoir, complete, in strict accordance with the
Comprehensive Agreements and all federal, state, and local regulations and permit
conditions. The project consists of removing accumulated sediment within segments 1
– 3 of the Upper Main Stem Reservoir. As an optional item, Dredging Contractor may
propose to remove additional sediment from the remainder of the Upper Main Stem
and/or Ivy Creek sections of the Reservoir. The project does not involve dredging
beyond the original contours or expanding the Reservoir beyond its original shoreline
configuration.
B. Pre-Dredging Survey: The Owner shall provide a bathymetric survey showing top of
sediment prior to the start of dredging to determine the existing sediment quantity in
the area(s) to be dredged. The Dredging Contractor shall verify all existing
conditions and notify Owner of any differences, including sediment quantity and
characteristics, prior to the Dredging Contractor beginning to dredge.
D. Datum and Bench Mark: The Horizontal Datum to be used for all dredging
operations is to be referenced to the North American Horizontal Datum of 1983
(NAD 83). The Vertical Datum is based on the North American Vertical Datum of
1988 (NAVD 88).
9
South Fork Rivanna Reservoir
Dredging Project Specifications
B. Trees and brush within the proposed dredging limits that are snagged along the shore
and/or in the Reservoir above the water line shall be left in situ, and that area within
the proposed dredging limits occupied by the snagged tree(s) should not be disturbed.
B. The Dredging Contractor shall not damage any structure or vegetation outside of the
Limits of Dredging (horizontal and vertical limits) as shown on the plans. The
Dredging Contractor will be responsible for repairing or replacing damaged
structures or vegetation outside of the Limits of Dredging at its own cost.
B. Hydrilla, a nuisance aquatic plant, is present in the Reservoir and is known to occur
within some of the areas to be dredged. The Dredging Contractor may be required by
federal, state, and local agencies to take extra precautions with equipment and
operations to control the spread of hydrilla. No additional compensation for any such
precautions or requirements will be allowed.
10
South Fork Rivanna Reservoir
Dredging Project Specifications
11
South Fork Rivanna Reservoir
Dredging Project Specifications
3. The plan shall include a project schedule showing anticipated start and
completion dates, key milestones, anticipated dredging progress/volume per
month or other operational period, and accommodations for permit requirements
(including time of year restrictions).
4. The plan shall include provisions for coordinating dredging activities on the
Reservoir with other users of the Reservoir, including water supply withdrawals,
recreational fishing and boating, and rowing.
B. Dredging Contractor shall submit three (3) copies of a Draft Plan within thirty (30)
days of the Award of this Contract. The Draft Plan shall be reviewed by the Owner
or Owner’s Representative for coordination of work and comments regarding
sequencing. After obtaining all project permits and incorporating permit conditions
and Owner or Owner’s Representative's comments, Dredging Contractor will
transmit three (3) copies of the Final Plan to the Owner and one (1) to the Owner’s
Representative for their files. Any major deviation to the plan must be submitted by
the Dredging Contractor for the Owner or Owner's Representative's review prior to
implementation.
C. Dredging Contractor shall be responsible for construction means and methods.
D. Dredging Contractor is responsible for complying with all permit conditions and
notification requirements with applicable federal, state and local regulatory agencies.
If there is a finding of non-compliance with the permit conditions or other applicable
regulations, the Dredging Contractor shall identify and implement corrective
action(s) at their own expense. The Dredging Contractor shall be responsible for any
fine or fee associated with the finding of non-compliance.
12
South Fork Rivanna Reservoir
Dredging Project Specifications
C. All pipelines shall be kept in good condition at all times, and any leaks or breaks
along their length shall be promptly and properly repaired.
D. Auxiliary booster pump locations, if required shall be placed at approved locations.
E. The approximate location for the pipelines and pipeline details shall be included in
the Dredging Operations Plan prepared by the Dredging Contractor.
F. All pipelines shall be of sufficient strength to prevent bursting during pumping
operations. In the case that the pipe leaks or burst, the Dredging Contractor shall
cease pumping operations immediately and repair the pipeline. The Dredging
Contractor shall be responsible for cleaning up any spills, repairing or replacing
damaged structures and/or vegetation at its own cost.
13
South Fork Rivanna Reservoir
Dredging Project Specifications
B. The Dredging Contractor shall make all repairs, strengthening, extensions and
modifications to staging area facilities as are necessary for confining the dredged
material until acceptance of all work under the contract as specified herein. The
Dredging Contractor will be permitted to construct any other structures, such as
temporary holding tanks, containment berms, drying pads, floating baffles or
skimmers, or use any means necessary to control the dredge effluent as required to
meet federal, state and local requirements. The Dredging Contractor shall also be
responsible for the maintenance, stability and security of all structures used by him in
completion of the contract.
2.18 MOBILIZATION
A. The mobilization, staging and temporary equipment storage area shall be identified in
the Dredging Operation Plan. The Dredging Contractor is responsible for obtaining
all necessary permissions and permits for use of the mobilization, staging and
temporary equipment storage areas throughout the entire. Mobilization shall include
all work necessary to clear and grade the staging area, establish gravel and/or paved
work areas, set up all equipment (including any desired power and water
connections), piping and support activities as necessary to begin the dredging and/or
14
South Fork Rivanna Reservoir
Dredging Project Specifications
dewatering work.
B. As an incidental part of mobilization the Dredging Contractor shall respect and
adhere to all security measures in effect at the site.
C. Dredging Contractor's activities at mobilization site shall be coordinated with the
Owner’s Representative.
2.19 DEMOBILIZATION
A. At the completion of all dredging work the Dredging Contractor shall remove all
temporary components, piping, dredge, support equipment, and miscellaneous
material from the Owner’s site.
B. No equipment, materials, or temporary facilities (including gravel roadways,
equipment pads, and paved areas) shall remain on the Owner's property upon
completion of demobilization unless approved in writing by the Owner. Failure to
remove such items will result in the Owner withholding final contract payment until
items are appropriately removed.
C. The project staging area shall be restored to pre-mobilization conditions to the
Owner's satisfaction.
D. All disturbed areas shall be smoothed, layered with top soil, and planted to turf grass
or otherwise restored in accordance with permit requirements, including those areas
used for project staging.
END OF SECTION
15
South Fork Rivanna Reservoir
Dredging Project Specifications
SECTION 3
ENVIRONMENTAL PROTECTION
3.1 SCOPE
A. The work covered by this section consists of furnishing all labor, materials and
equipment, and performing all work required for the prevention of environmental
pollution during the dredging, dewatering and related project activities in and
adjacent to the South Fork Rivanna Reservoir except for those measures set forth in
other Technical Provisions of these specifications. For purpose of this specification,
environmental protection is defined as the retention of the environment in its natural
state to the greatest possible extent during project construction and to enhance the
natural appearance and function in its final condition. Environmental protection
requires consideration of air, water, and land, and involves management of noise and
solid waste, as well as other pollutants. In order to prevent, and to provide for
abatement and control of, any environmental pollution arising from the activities in
the performance of this contract, the Contractor and his subcontractors shall comply
with all applicable federal, state and local laws and regulations and project permits
concerning environmental disturbance and pollution control and abatement.
3.3 NOTIFICATION
A. The Owner or Owner’s Representative shall notify the Dredging Contractor in
writing of any observed non-compliance with the foregoing provisions and the action
to be taken by the Dredging Contractor to correct such non-compliance. The
Dredging Contractor shall, after receipt of such notice, immediately inform the
Owner or Owner’s Representative of proposed corrective action and takes such
action as may be approved. If the Dredging Contractor fails or refuses to comply
promptly, the Owner or Owner’s Representative may issue an order stopping all or
part of the work until satisfactory corrective action has been taken. No part of the
time lost due to any such stop orders shall be made the subject of a claim for
extension of time or for excess costs of damages by the Dredging Contractor.
B. Failure of the Owner or Owner’s Representative or other parties to observe and or
notify the Dredging Contractor of any non-compliance with the foregoing provisions
shall not relieve the Dredging Contractor of responsibility to prevent, and to provide
for abatement and control of, any environmental pollution arising from the
construction activities of the Dredging Contractor and his subcontractors in the
performance of this contract.
16
South Fork Rivanna Reservoir
Dredging Project Specifications
17
South Fork Rivanna Reservoir
Dredging Project Specifications
18
South Fork Rivanna Reservoir
Dredging Project Specifications
3.10 SANITATION
A. The dumping of sanitary sewage effluent and/or solids into waters surrounding the
job site will not be allowed. The Dredging Contractor must provide suitable
sanitation devices for the proper and sanitary storage of all sanitary sewage.
END OF SECTION
19
South Fork Rivanna Reservoir
Dredging Project Specifications
SECTION 4
HEALTH AND SAFETY
4.1 DESCRIPTION
The Dredging Contractor is responsible and liable for the health and safety of all on-site
personnel and the general public impacted by the dredging and associated project
work in South Fork Rivanna Reservoir.
The Dredging Contractor must comply with all applicable federal, state, and local
regulations and permit conditions protecting human health and the environment from the
hazards posed by activities during this dredging work.
4.2 BASIS
A. Federal, state, and local regulations addressing Occupational Safety and Health
Administration (OSHA) standards and regulations shall provide the basis for the
Dredging Contractor’s activities to provide for the health and safety of all on-site
personnel. The Dredging Contractor shall perform all work required by the
Comprehensive Agreements in compliance with federal, state, and local OSHA
standards and regulations.
B. Federal, state, and local regulations addressing dredging, material handling, storage
and transportation, including discharges of waste, water, or other materials or
emissions shall provide the basis for the Dredging Contractor’s activities to provide
for the health and safety of the general public. The Dredging Contractor shall perform
all work required by the Comprehensive Agreement in a safe and environmentally
acceptable manner. The Dredging Contractor shall provide for the safety of all project
personnel and the community for the duration of the Contract.
C. The safety and health of the public and project personnel and the protection of the
environment will take precedence over cost and schedule considerations for all project
work. When a situation affecting health and safety is identified, the Dredging
Contractor shall stop work that may be affected by the situation until the cause for
suspension of operations is addressed. Any additional costs will be considered only
after the cause for suspension of operations is addressed and work is resumed. The
Owner or Owner’s Representative will be kept appraised of conditions which may
adversely affect the health and safety of project personnel and the general public
D. The Owner or Owner’s Representative may stop work or any portion thereof due to
its reasonable judgments that the Dredging Contractor has or is violating the
Comprehensive Agreement or any requirement thereof, including but not limited to
violations of any law or regulation related to jobsite safety. If work or any portion
thereof is suspended for health and/or safety reasons, it will not resume until the cause
of the suspension is addressed and resolved by the Dredging Contractor. Provided,
however, if the Owner or Owner’s Representative suspends Work or any portion
thereof due to its reasonable judgment that the Dredging Contractor has or is violating
the Comprehensive Agreement or any requirement thereof, including but not limited
to violations of any law or regulation related to jobsite safety, then the Dredging
Contractor shall not receive an adjustment in the Contract Price or extension of the
Contract Times, even if it is determined that no violation actually existed.
20
South Fork Rivanna Reservoir
Dredging Project Specifications
4.3 RESPONSIBILITIES
A. The Dredging Contractor will be responsible for protecting project personnel and the
general public from hazards due to the exposure, handling, and transport of chemical
and hazardous materials associated with the dredging project. Barricades, shielding
lanterns, fenced and roped-off areas, filtration and proper signs will be furnished in
sufficient amounts and locations to safeguard project personnel and the public at all
times. The Dredging Contractor shall place a temporary safety fence consisting at a
minimum of portable chain link fence six feet in height around project staging areas.
The Dredging Contractor shall place warning and keep away signs surrounding the
staging areas and at the upstream and downstream end of the dredging foot print to
warn recreational boaters to stay away from dredging activities.
B. Ensure all applicable federal, state, and local OSHA health and safety requirements
are met.
C. The Dredging Contractor will be responsible for the following:
1. Performing on-site daily implementation, enforcement, and monitoring of
applicable federal, state, and local OSHA health and safety regulations.
2. Performing daily tailgate (“toolbox”) safety briefings prior to the start of work,
and maintaining records relating to these briefings.
3. Responsibility for the pre-construction training of all on-site personnel with
regard to the safety and other safety requirements to be observed during
construction, including:
i. Potential hazards
ii. Personal Protection equipment (PPE).
4. Emergency procedures dealing with fire and medical situations.
B. The Dredging Contractor shall schedule a site briefing with the local Fire Department
at the completion of mobilization to familiarize emergency response personnel with
his operations and site layout.
C. Master Telephone List: The attached master telephone list will be completed and
prominently posted at the Dredging Contractor’s field office and/or staging area. The
list will have telephone numbers of all project personnel and emergency services
including hospital, fire, police, and utilities. In addition, two copies with telephone
numbers are to be given to the Owner or Owner’s Representative for emergency
reference purposes.
21
South Fork Rivanna Reservoir
Dredging Project Specifications
END OF SECTION
22
South Fork Rivanna Reservoir
Dredging Project Specifications
SECTION 5
MEASUREMENT AND PAYMENT
5.1 GENERAL
A. The Dredging Contractor shall be paid for dredging and work items incidental to
dredging based on the accepted bid and/or the terms and conditions of the
Comprehensive Agreement between the Owner and the Dredging Contractor. Work
items incidental to dredging include all work activity related to dredging, dewatering,
transport, and placement of the dredged material.
B. The Dredging Contractor shall submit a Schedule of Values with the bid. The
Schedule of Values may include lump sum costs for Mobilization and
Demobilization, and a unit price per cubic yard of material removed (including all
dredging, dewatering, transportation, and placement at an approved placement site),
or other pricing as proposed by the Dredging Contractor.
B. The total amount of material removed will be measured by the cubic yards (cy) of
material removed by dredging, measured in-place by field verifying that the sediment
has been removed down to the lines and grades as specified. The Owner shall
insure that a final survey is completed in a timely manner to verify and insure that the
proposed volume of sediment has been removed. If a final survey is not completed
within a timely manner, the Owner and the Dredging Contractor shall agree on an
estimated amount of completion based upon plan quantities and surface area
completed. If target depths cannot be achieved due to in-place conditions or
restriction (i.e. hard, cemented sand and gravel or other obstructions), adjustments to
actual pay quantity may be included.
C. No additional payment shall be made for over depth dredging unless approved in
advance by the Owner and Owner’s Representative.
END OF SECTION
23
South Fork Rivanna Reservoir
Dredging Project Specifications
SECTION 6
SPECIAL PROVISIONS
6.1 GENERAL
The following special provisions apply to all work items and other project related
activities unless otherwise specified.
6.4 PERMITS
A. The Dredging Contractor shall be responsible for complying with all conditions of
federal, state, and local permits, as well as all applicable rules and regulations.
24
South Fork Rivanna Reservoir
Dredging Project Specifications
6.6 BLASTING
No blasting is required or permitted in this contract work.
6.7 ODORS
The Dredging Contractor shall be responsible for control of malodorous odors emanating
from the dredging operation and/or the sediment dewatering and placement,
beneficial reuse or stockpiling activities conducted by the Dredging Contractor and/or
it’s subcontractors. Specific activities to reduce odor include but are not limited to:
END OF SECTION
25
RD
P AN O R A MA RD
RI O M IL L S
SEM
INO L
E TR
L
BR A D
F OR
D LN
SEM IN
O LE
R EA
TR L
W
OO
DB
SF
DR UR
T ON N
OR
GH RD
RI
WA
D
B RW
LN
IC
K PL
EA
RL
YS
VI
LL
ER
D
DU N
E RD
US
B ERK M
HO
DE
E AK
BL
E
R
D
D
AR D
ORD R
LF
MI
R
R
ON D
UB
R
D
D
AU D
EA
H
OW D B R OO K D R
DR
WO O
A RR
OD
O
W
AN
RIV
N R I SE L N
RD
SU
WO O DLA
RE N C E
N DS RD
D
LA W
AT E R
C IR
EW
VI
R
WY N G
EA
CL
RE A
S FO
RD R
DW
D
RIO R
BE LA K E
DU N R O M
A F ORE
U ST D R
M
O
N MO N
T TE R EY
FA DR
RM R
IN
D
RD
Reservoir
0 0.1 0.2 Miles South Fork Rivanna Reservoir Property Adjacent to
City of Charlottesville Property Dredging Procurement Support Services S. Fork Rivanna Reservoir
Prepared by: Date: December 2011
Scale: 1" = 1,200'
3
+0
1 36
2
0
+4
56
Bridge
3 Upper Mainstem
76+2
6
4
17
90+
5
24
0+
11
5
0
6
130+
Dam
7
13
+ 48
156
267+
1 6
Woodlands
Hydraul RoadBridge
icRoad Bridge
8
12
14
0+00
172+28
7
+1
8
15 18
+4
30
12+3
IvyCreek
16 9
7
17
24
1
+7
5
11
36+32
Lower Mainstem
191+73
Earl
ysvil
le Road Bridge
10
215
6+3
Legend
0 1,000 2,000
D a te : J a n u a ry 2010
4,000
Feet
RIVANNA WATER AND SEWER AUTHORITY
S e d im e n t C h a ra c te riz a tio n T ra n s e c ts
C ro s s -s e c tio n a l T ra n s e c ts
1 R e s e rv o irS e g m e n ts