Purpose : This procedure is used as work instruction for TG operator , Desk Engineer , Shift
Incharge.
Scope : This instruction sheet explains the interlock and protections for Turbine.
Procedure:
Page 1 of 2
Desk Engineer Deptt.Head Head – Operation & Maintenance
Prepared By Reviewed by Approved By
HINDALCO MAHAN, 6X150 MW
RECORDS : Nil