Commissioning Procedure C&I Comments
Commissioning Procedure C&I Comments
1. PLC System
A) 1.5. Reference Document missing PLC control panel Schematic Drawing & PLC Network
configuration Drawing &PLC Vendor I/O list & Instrument data sheet & OPC interface DCS to PLC
Ethernet I/O list. So need to update existing page.
B) Attachment Not included such kind of redundancy test for (PLC Panel UPS power & Network
Communication) .also HMI NTP time sync test With GPS Clock.
2. Loop Test
A) Refer Attachment No 2 MOV loop test report Torque setting value & Seating Method Not Included.
So Need to Update Standard Format.
B) Refer Attachment No 2 analogue & On/Off pneumatic valve Loop Test Report Not Included
Manufacture Name, Type/Model & Valve Action, Travelling Time. So Need to update standard
Format.
A) Instrument data sheet & O&M manual are not included in this document. Please clarify and update
the Reference Document. (At least need to write Drawing Ref No)
A) Interlock test sheet Pump (selection & Auto change over) are not included in this document. Please
clarify and update.
C) Instrument Operating Set Points Missing for example (Vibration HH 168um & Tank level low 1m
…etc.)