Unimas Crit Path

This document provides a Gantt chart schedule for the Sg. Maaw-Sibu 132 kV Transmission Line Project. The project has a total duration of 469 days from January 2019 through June 2020. It involves several key activities including design, material procurement, manufacturing, construction, and installation work. The schedule outlines the start and finish dates and duration of each activity on the critical path.

Uploaded by

Roberto Rizzo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views1 page

Unimas Crit Path

This document provides a Gantt chart schedule for the Sg. Maaw-Sibu 132 kV Transmission Line Project. The project has a total duration of 469 days from January 2019 through June 2020. It involves several key activities including design, material procurement, manufacturing, construction, and installation work. The schedule outlines the start and finish dates and duration of each activity on the critical path.

Uploaded by

Roberto Rizzo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Sg.

Maaw-Sibu 132 kV Transmission Line Project

Activity ID Activity Name Original Start Finish Total A M J J A S O N D J F M A M J J A S O N D J F M A M J J


Duration Float
00122012201120012201120012301220112001230122011201123012201120012301220112001220122011200122011200120012201120112301220
Total 469 01-Jan-19 30-Jun-20 0 30-Jun-20 05:00 PM
08:00 AM 05:00 PM
PRE1000 Project Kick-Off Meeting 0 01-Jan-19 08:00 AM 0 Project Kick-Off Meeting
MILE1000 ProjectAward 0 01-Jan-19 08:00 AM 0 ProjectAward
PRE1010 Project Team & Mobilization of Construction Team 4 04-Jan-19 08:0009-Jan-19
AM 05:00 PM 0 PRE1010
DES1000 Compilation Submission of Sag & Tension Calculation 30 25-Jan-19 08:0007-Mar-19
AM 05:00 PM 0 DES1000
DES1010 Approval of Sag & Tension Calculation 30 25-Jan-19 08:0007-Mar-19
AM 05:00 PM 0 DES1010
DES1050 Approval of NS Design & Drawings 30 01-Mar-19 08:0011-Apr-19
AM 05:00 PM 0 DES1050
DES1040 Compilation & Submission of NS Design & Drawings 25 08-Mar-19 08:0011-Apr-19
AM 05:00 PM 0 DES1040
DES1160 Compilation & Submission of AAAC Sycamore Conductor Drawings 30 13-Mar-19 08:0023-Apr-19
AM 05:00 PM 0 DES1160
DES1220 Compilation & Submission of OPGW & OPUG Drawings 30 29-Mar-19 08:0009-May-19
AM 05:00 PM 0 DES1220
DES1200 Compilation & Submission of Line Fittings Drawings 30 10-Apr-19 08:0021-May-19
AM 05:00 PM 0 DES1200
MAT1030 Procurement of Tower 10 12-Apr-19 08:0025-Apr-19
AM 05:00 PM 0 MAT1030
DES1180 Compilation & Submission of Insulators Drawings 30 15-Apr-19 08:0024-May-19
AM 05:00 PM 0 DES1180
DES1250 Approval of Tower Earthing Drawings 30 18-Apr-19 08:0029-May-19
AM 05:00 PM 0 DES1250
DES1240 Compilation & Submission of Tower Earthing Drawings 30 18-Apr-19 08:0029-May-19
AM 05:00 PM 0 DES1240
MAT1310 Procurement of Tower Earthing 10 30-May-19 08:00
12-Jun-19
AM 05:00 PM 0 MAT1310
MAT1320 Manufacturing of Tower Earthing 30 13-Jun-19 08:0024-Jul-19
AM 05:00 PM 0 MAT1320
MAT1330 Delivery of Tower Earthing to Store 30 25-Jul-19 08:00 04-Sep-19
AM 05:00 PM 0 MAT1330
MAT1040 Manufacturing of Tower 20 01-Aug-19 08:0028-Aug-19
AM 05:00 PM 0 MAT1040
MAT1050 Approval of Full Type Test Report & COA from CIDB 20 27-Aug-19 08:0018-Sep-19
AM 05:00 PM 0 MAT1050
CON1170 Installation of Normal Foundation for TensionTower 60 05-Sep-19 08:0027-Nov-19
AM 05:00 PM 0 CON1170
MAT1070 Delivery of Tower to Store 20 19-Sep-19 08:0016-Oct-19
AM 05:00 PM 0 MAT1070
EREC1000 Erection & Installation of Anti Theft Nuts for Suspension Towers 90 17-Oct-19 08:0019-Feb-20
AM 05:00 PM 0 EREC1000
EREC1010 Erection & Installation of Anti Theft Nuts for Tension Towers 90 17-Oct-19 08:0019-Feb-20
AM 05:00 PM 0 EREC1010
EREC1020 Stringing Conductor & OPGW 90 19-Dec-19 08:0022-Apr-20
AM 05:00 PM 0 EREC1020
EREC1030 Tensioning Conductor & OPGW 10 23-Apr-20 08:0006-May-20
AM 05:00 PM 0 EREC1030
EREC1040 Clamping Conductor & OPGW 10 07-May-20 08:00
20-May-20
AM 05:00 PM 0 EREC1040
EREC1070 Laying of OPUG At SubStation 10 21-May-20 08:00
03-Jun-20
AM 05:00 PM 0 EREC1070
EREC1080 Anti Climbing Device & Tower Plate Installation 15 21-May-20 08:00
10-Jun-20
AM 05:00 PM 0 EREC1080
TEST1000 OPGW End to End Test 4 11-Jun-20 08:0015-Jun-20
AM 05:00 PM 0 TEST1000
TEST1010 Line Continuity Test 4 16-Jun-20 08:0019-Jun-20
AM 05:00 PM 0 TEST1010
TEST1020 Insulation & Impedence Test 4 20-Jun-20 08:0024-Jun-20
AM 05:00 PM 0 TEST1020
TEST1030 Commissioning of Line 4 25-Jun-20 08:0029-Jun-20
AM 05:00 PM 0 TEST1030
DMOB1000 Demobilization & Site Handed Over to SEB 1 30-Jun-20 08:0030-Jun-20
AM 05:00 PM 0 DMOB1000
MILE1050 Project Completion 0 30-Jun-20 05:00 PM 0 Project Completion
MILE1080 Project Completion 0 30-Jun-20 05:00 PM 0 Project Completion

Page 1 of 1
Actual Work Critical Remaining Work Summary
Remaining Work Milestone UNIMAS CONSTRUCTION SDN BHD