NABARD FormatforSQM
NABARD FormatforSQM
Format 1- Part I
20
3. QUALITY CONTROL:
3.1. Location of Field Laboratory:
3.2. Quality Control Register Part-I is maintained by:
3.3. Quality Control Register Part-II is maintained by:
4. INSPECTIONS BY SQM or SENIOR OFFICERS AND ACTION
TAKEN:
Inspection by SQMs and senior (i.e. SE or CE) departmental officers and action taken
statement:
Date of Inspected Observations Action Taken by PIU with
Visit By Date
21
Format 1- Part II
Report of State Quality Monitor (SQM)
PART II– Observations of SQM for Ongoing/Completed Work
(To be filled-up by SQM, use additional sheets, if required.)
Stage of Work: I II III
1. SETTING OUT AND WORKING DRAWING: For all stages of work
Grading: Grade: S SRI U If this item is graded SRI/U, write clear reasons and
suggestions for improvement:
# Whether Clearing and Whether the material Name the reusable material
Grubbing being done available from obtainable from clearance or
as per DPR and scarifying existing work scarification and indicate
Material obtained is or clearing operations approximate quantity and its
being disposed off can be salvaged and re-use by the PIU.
properly (Y/N) reused (Y/N)
Grading: Grade: S SRI U If this item is graded SRI/U, write clear reasons and
suggestions for improvement:
22
3. QUALITY ARRANGEMENTS AND ATTENTION TO QUALITY - For all
stages of work
Observations about Field Laboratory:
Observations about Mandatory Tests - Detail out the quantities of various items of
works and list the tests required. (Refer to abstract of QC Register Part-I)
Grading: Grade: S SRI U If this item is graded SRI/U, write clear reasons and
suggestions for improvement:
23
4. GEOMETRICS: The SQM should take at-least two measurements in 1 Km length
and if it is found that the roadway and carriageway is inadequate SQM may take more
observations:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
24
Grade: S U If this item is graded U, write clear reasons and
suggestions for improvement:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
25
Observations - Earth work in Hilly/Rolling terrain or high Embankments:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
6. Sub-Base:
Observations - Quality of Material and Workmanship:
# Location Confirms Suitable Whether Observed Prescribed
(RD) to from compaction Thickness Thickness
Grading. plasticity is adequate. of Layer provided
(Y/N) angle. (Y/N) (in mm) (Y/N)
(Y/N)
26
Grade: S U If this item is graded U, write clear reasons and suggestions
for improvement:
7. Base Course:
Observations- Quality of Material and Workmanship of WBM:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
27
8. Bituminous Course: Premix Carpet/Surface Dressing/ BM/ MPM etc including
Seal Coat: Observations - Quality of Material and Workmanship of BT Layer (in
case of ongoing works):
Observations about Quality of Prime Coat and Tack Coat with respect
to quality of material and workmanship - Visual Observation - if work is
ongoing:
28
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
29
10. Cross Drainage Works: Observations - Quality of CDs:
# RD at which Type of CD Whether quality of the Whether quality of
CD is located material is acceptable. workmanship is
(Y/N) acceptable. (Y/N)
Grade: S SRI U If this item is graded SRI/U, write clear reasons and suggestions
for improvement:
Grade: S SRI U If this item is graded SRI/U, write clear reasons and
suggestions for improvement:
30
12. CC/ Semi-Rigid (SR) Pavements and Associated Pucca Side Drains:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
31
13. Road Furniture and Markings
Observations - Item No. 14 a: Quality Road Furniture and Markings:
Main Informatory Board Fixed: Yes No
Citizen Information Board Fixed: Yes No
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
Grade: S U If this item is graded U, write clear reasons and suggestions for
improvement:
14. General Observations of SQM, (including the observations made during the
interaction with PIU staff and Contractor’s/ Consultant’s Engineers):
32
14.2. Whether the work has been completed/is in progress as per work
programme or the delay has occurred. If delay has occurred, whether the
liquidated damages have been withhold or recovered:
14.3. Whether the work has been completed within the sanctioned cost, if not,
what is the action taken by the PIU (in case of complete works):
14.4. Observations about the action taken by the PIU on the observations of
inspecting officers including SQMs. (Clearly offer comments about the action
taken on the observations of Departmental Officers, State Quality Monitors .
33
15. Other observations, if any:
34
16. Quality Grading of items and sub-items of work: The grading of every sub-item
and item of work is given below.
Awardable Awarded
# Sub Item for Observation Stage of Work Grades Grades
1 2 3 4 5
Item 1 – Setting Out and Working Drawing
a Bench Mark and Centre Line All Stages S/SRI/U
Availability of Working
b All Stages S/SRI/U
Drawing
Item Grade S/SRI/U
Item 2 – Site Clearance and Grubbing
a Site Clearance and Grubbing Stage-I S/SRI/U
b Re-use of Salvageable Material Stage-I S/SRI/U
Item Grade S/SRI/U
Item 3 - Quality Arrangements
a Quality Arrangements All Stages S/SRI/U
Number of Mandatory Tests as
b All Stages S/SRI/U
per prescribed frequency
c Maintenance of QC Registers All Stages S/SRI/U
Item Grade S/SRI/U
Item 4 – Geometrics
2 per Km in every
a Road way width S/U
inspection
2 per Km in every
b Carriageway width S/U
inspection
c Camber 2 per km S/U
35
Item 5B - Earth Work in Cutting in Hilly/ Rolling Terrain
b Plasticity km S/U
In Stage- II or III, 1 per
c Compaction S/U
km
d Total Thickness of Layer 2 per Km S/U
36
Item 8 - Bituminous Layer – Premix Carpet (PMC)/ Surface Dressing (SD)
Level of cleanliness of WBM
a surface prior to application of 1 per Km S/U
bituminous layer
Quality of Prime Coat/ Tack
1 observation on the day
b Coat with respect to quality of S/U
of inspection
material and workmanship
37
Item 11 - Side Drain and Catch Water Drain
38
17. Overall Grading of Work: The overall grading calculated on the basis of item and
sub-item wise grading is given below:
Awarded
Item No. Sub Item for Observation
Grade
Item No 1 Setting Out and Working Drawing
Item No 2 Site Clearance and Grubbing
Item No 3 Quality Arrangements
Item No 4 Geometrics
Earth Work and Sub-grade in Embankment/
Item No 5 A
Cutting
Item No 5 B Earth Work in Cutting in Hilly/ Rolling Terrain
Item No 6 Sub-Base
Item No 7 Base Course – Water Bound Macadam
Bituminous Layer – Premix Carpet (PMC)/
Item No 8
Surface Dressing (SD)
Item No 9 Shoulders
Cross Drainage Works – Causeways of all
Item No 10
spans and Culverts upto 6 m. span.
Item No 11 Side Drain and Catch Water Drain
CC/ Semi Rigid Pavements and Associated
Item No 12
Pukka Drains
Item No 13 Road Furniture and Markings
Overall Grading
Signature:
Name:
Date: ..……….
39
Annexure 2
Statement Showing Sub-Item and Item wise Observations to be made, their Method, Frequency
and Awardable Quality Grade
Sub Item for
# Observation Method of Observation Frequency Grades
1 2 3 4 5
Item 1 – Setting Out and Working Drawing
Bench Mark and
a Centre Line Visual All Stages S/SRI/U
Availability of
b Working Drawing Visual All Stages S/SRI/U
Item Grade S/SRI/U
Item 2 – Site Clearance and Grubbing
Site Clearance and
a Grubbing Visual Stage-I S/SRI/U
Re-use of Salvageable
b Material Visual Stage-I S/SRI/U
Item Grade S/SRI/U
Item 3 - Quality Arrangements
a Quality Arrangements Visual All Stages S/SRI/U
Number of Mandatory
b Tests as per prescribed Examination of Record All Stages S/SRI/U
frequency
Maintenance of QC Verification of QC
c All Stages S/SRI/U
Registers Register I and II
Item Grade S/SRI/U
Item 4 – Geometrics
2 per Km in every
a Road way width Measurements inspection S/U
2 per Km in every
b Carriageway width Measurements inspection S/U
c Camber Measurement 2 per km S/U
Super-elevation &
d Extra Widening at Measurement 1 curve in each km S/U
Curves
Item Grade S/U
Item 5A - Earth Work and Sub-grade in Embankment/ Cutting
Quality of Material for
Visual Classification of In Stage-I, 1 per km/
a Embankment/ Sub- S/U
Soils In Stage- II or III, 1 per km
grade
Field Density Test by
In Stage-I, 2 per km/
b Compaction sand replacement/core- S/U
In Stage- II or III, 2 per km
cutter method.
40
Sub Item for Method of
# Frequency Grades
Observation Observation
1 2 3 4 5
Item 5B - Earth Work in Cutting in Hilly/ Rolling Terrain
Stage I and II, at 2 critical
Stability and
locations with maximum
a Workmanship of Cut Visual Observation S/U
height of cutting in each
Slopes
km
Adequacy of Slope
b Visual Observation All Stages - In general S/U
Protection
Upon completion of At Stage III, at 2 critical
formation cutting, locations with maximum
c dressing, traffic Visual Observation height of cutting in each S/U
worthiness km
Stage II/III - 1 critical and
fairly representative
d Longitudinal Gradient Measurements stretch of 200m in each S/U
Km
Item Grade S/U
Item 6 - Sub-Base
Quality of Material
a Grain Size Gradation Test S/U
Test of LL, PI / Hand- In Stage- II or III, 1 per
b Plasticity feel test of ball making km S/U
with moisture content
Field Density Test by
In Stage- II or III, 1 per
c Compaction sand replacement/ core S/U
km
cutter method.
Measurement by taking
Total Thickness of
d pit for full layer 2 per Km S/U
Layer thickness
Item Grade S/U
Item 7 - Base Course – Water Bound Macadam
Grain Size of Course
a Aggregate Gradation Test S/U
Test for Liquid Limit In Stage- II or III, 1 per
Test of LL, PI / Hand-
and Plasticity Index in km
b feel test of ball making S/U
case fine aggregates
with moisture content
are crushable type
Volumetric Analysis
Hand-feel test - In Stage- II or III, 1 per
c for assessment of S/U
volumetric analysis. km
compaction of WBM
Surface Evenness In completed WBM 2 tests
d using straight edge Straight Edge per km S/U
Thickness of every Actual Measurement by
e 2 per Km S/U
layer of WBM. taking pit
Item Grade S/U
41
Sub Item for Method of
# Frequency Grades
Observation Observation
1 2 3 4 5
Item 8 - Bituminous Layer – Premix Carpet (PMC)/ Surface Dressing (SD)
Visual Observation - if
Level of cleanliness of work is ongoing observe
a WBM surface prior to the surface. If BT layer 1 per Km S/U
application of
laid assess by carefully
bituminous layer
removing the BT layer
Quality of Prime Coat/
Tack Coat with
Visual Observation - if 1 observation on the day of
b respect to quality of S/U
material and work is ongoing. inspection
workmanship
Gradation Test for
Course Aggregate (if
the work in the item is
Grain Size Analysis 1 test on the day of
c ongoing)/visual S/U
observation in case of (Gradation Test). inspection
completed item of
work
Grade of bitumen and
temperature at the Measurement of
1 test on the day of
d time of mixing and temperature by S/U
laying (if the work in thermometer. inspection
the item is ongoing)
Bitumen Extraction
e Test if PMC is Bitumen Extraction Test 1 test per Km S/U
complete
Measurement by taking
f Thickness of layer pit 2 per Km S/U
Surface Evenness in
g case of completed BT By straight edge 2 per Km S/U
work
Item Grade S/U
Item 9 – Shoulders
Quality of material for In Stage- II or III, 1 test
a shoulders Visual Observation S/SRI/U
per Km
Field Density Test by
In Stage- II or III, 1 test
b Degree of compaction sand replacement/core- S/SRI/U
per Km
cutter method.
In Stage- II or III, 2 tests
c Thickness of layer Measurement per km S/SRI/U
Item Grade S/SRI/U
Item 10 - Cross Drainage Works – Causeways of all spans and Culverts upto 6 m. span.
Quality of Material –
Visual observation ( for
Concrete, Stone/ brick
a CC verify cube test All Stages S/SRI/U
masonry, Hume pipes
results from records)
including size etc.
42
Sub Item for
# Method of Observation Frequency Grades
Observation
1 2 3 4 5
Quality of
Workmanship such as
b positioning of pipes, Visual observation All Stages S/SRI/U
wing walls, cushion
over H Pipes etc.
Item Grade S/SRI/U
Item 11 - Side Drain and Catch Water Drain
General quality of
Side Drains/ Catch
Water Drains and their Visual observation All Stages S/SRI/U
integration with CDs.
Item Grade S/SRI/U
Item 12 - CC/ Semi Rigid Pavements and Associated Pukka Drains
Quality of Material –
In Stage- II or III, 1 per
Concrete, Stone/
a Visual Observation 100 m. Length of S/U
Concrete Block
Pavement
Pavement etc.
Strength using
Strength of CC in
appropriate rebound
Concrete Pavement/ In Stage- II or III,1 per 100
b hammers/ verification of S/U
Concrete Block m. Length of Pavement
cube test results from
Pavement
test records.
Quality of
Workmanship –
Wearing surface
c texture, Adequacy of Visual observation In Stage- II or III S/U
setting of concrete,
Joints, Edges etc.
In Stage- II or III, 1 per
d Thickness of Layer Measurements 100 m. Length of S/U
Pavement
Item Grade S/U
Item 13 - Road Furniture and Markings
Citizen Information
Board, Main
Informatory Board,
a Quality and whether Visual observation Stage-I S/U
fixed during
construction.
Logo boards, 200 m
stones and Km stones,
b quality and whether Visual observation Stage-III S/U
fixed after completion.
Whether the
information in boards
c is given in local Visual observation Stage-I and III S/U
language.
Item Grade S/U
43