PROJECT STANDARDS and SPECIFICATIONS Heat Tracing and Winterizing Systems Rev01
PROJECT STANDARDS and SPECIFICATIONS Heat Tracing and Winterizing Systems Rev01
PROJECT STANDARDS and SPECIFICATIONS Heat Tracing and Winterizing Systems Rev01
KLM Technology
Group Rev: 01
Project Engineering
Standard
April 2011
www.klmtechgroup.com
TABLE OF CONTENT
UNITS 3
APPLICATION AND METHODS 3
General Considerations 3
Methods of Winterization 3
CONDITIONS REQUIRING WINTERIZATION 4
REQUIREMENTS 5
General 5
Piping 6
Instruments 7
Valves 11
Equipment 11
Miscellaneous Items 13
DESIGN 14
Internal Steam Tracing 14
External Steam Tracing 14
Insulation 25
Steam Jacketing 25
Identification 26
Inspection and Testing 26
Electrical Tracing 26
Use of Heat Transfer Cement 28
APPENDIX A 29
APPENDIX B 30
APPENDIX C 31
APPENDIX D 32
Page 2 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
SCOPE
This Project Standards and Specifications covers the minimum requirements for
protection of process and utilities and all associated equipment and flow lines
and instruments against the temperature which would cause congealing or
freezing of contents, interfere with operation or cause damage to equipment or
pipe lines and for heat conservation requirement as would be determined by
process conditions. The heat conservation system shall be designed for
continuous operations while, winterizing shall be for seasonal operation. The two
systems shall be separate from each other.
REFERENCES
Throughout this Standard the following dated and undated standards/codes are
referred to. These referenced documents shall, to the extent specified herein,
form a part of this standard. For dated references, the edition cited applies. The
applicability of changes in dated references that occur after the cited date shall
be mutually agreed upon by the Company and the Vendor. For undated
references, the latest edition of the referenced documents (including any
supplements and amendments) applies.
SYMBOL/ABBREVIATION DESCRIPTION
CM Collection Manifold
DM Distribution Manifold
DN Diameter Nominal (Pipe Size), in (mm)
ET Electric Traced and Insulation
ETT Electric Traced with Heat Transfer Cement
H Heat Conservation
ID Inside Diameter
MI Mineral Insulation
PD Meters Positive Displacement Meters
P & IDS Piping and Instrumentation Diagrams
Ref. Reference
OD Outside Diameter
Page 3 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
UNITS
General Considerations
To avoid operating difficulties in process and utility Units in colder climates and
the hazard of freezing which may cause damage to equipment or blockage of
lines, different methods to the extent of protection required, will be used. The
extent of protection may vary considerably between one location and another.
However, the requirements for other ambient temperature conditions is also
covered herein.
Methods of Winterization
during start up or shut down, or when a line is blocked off in error, and as a
result, freezing of the system may take place.
2. Heating
Winterizing with heating should not be used where other methods can be
used. Any of the following heating system may be used:
- Internal heat tracing
- External heat tracing
- Jacketing
- Electrical tracing
- Routing along and/or insulating together with a hot line.
Heating medium for non-electric tracing and jacketing can be steam, hot oil
and hot water.
3. Vent / Drain on lines and equipment
Winterizing by draining require particular attention which must be given to
vents and drains on utility lines and equipment for eliminating low spots or
dead ends in which water and other liquids can collect and freeze. During
shut-down and non-operating period these lines may completely be drained.
4. Bypasses around equipment to provide continuous flow
Bypass line connection in appropriate points as specified herein, and in
accordance to project specification should be provided for use in maintaining
flow.
5. Hot air circulation
Hot air circulation may be used in aerial exchangers, instrument and
equipment housing, flushing connections to displace viscous-material.
Process, utilities, equipment and pipe lines and other equipment/pipe lines shall
be winterized when any of the following conditions apply to fluids contained:
a. Pour point or freezing point is above the lowest ambient temperature.
b. Undesirable phase separation, deposition of crystals or hydrate formation will
occur at any ambient temperature.
Page 5 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
REQUIREMENTS
General
1. The requirements for protection shall be based on the winterizing temperature
specified in project specification, and shall consist of two parts:
a. Lines and equipment which appear on P & I Diagrams. The extent and
degree of protection shall be specified by the project engineer and shown
on the P & I Diagrams.
Note:
Protection described by standard nomenclature on P & I Diagrams may be
inadequate for projects involving low winterizing temperatures in
combination with unusual process fluid properties. On such projects
consideration shall be given to the use of high thermal conduction cement
bonding of tracers, steam jacketing, electric heating, shelters and other
special design.
b. Lines and equipment not shown on the P & I Diagrams. Protection shall be
provided by the design Contractor/ Consultant to the extent and in the
manner provided herein.
2. Layout, design and details which are to be followed by the design Contractor
in winterizing all equipment shall be as specified herein.
3. Protective heating of piping and instruments shall be indicated on the process
engineering flow schemes and on the piping data sheets.
4. The extreme case of the lowest minimum temperature should not be selected,
but in general, equipment should be designed for protection against the
minimum temperature prevailing after rejection of the lowest 1% of the hourly
temperature readings in the coldest month, or in 1% of the daily minimum
temperatures for the year; the readings should as far as possible be based on
Page 6 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
the average of records obtained over a period of years and not those of a
single year.
5. The amount of winterizing protection shall be based on minimum atmospheric
temperature as shown on site data sheet. For heat conservation during
operation, fluids with a pour point of 10°C and higher shall be traced to
maintain a temperature at least 22°C above their pour point. Molten sulfur
lines shall be maintained between 118°C (245°F) and 158°C (316°F).
Piping
1. A list of all piping requiring tracing should be prepared for each Unit in project
specification.
2. Sections of gas systems in which ice or condensate would otherwise be
produced, due to atmospheric cooling or auto refrigeration, should be traced.
Protection will also be required where there is hydrate formation at
temperatures above 0°C.
3. Careful consideration should be given to the design and protection of lines
which are dry during normal operations but which may contain sufficient
moisture to be troublesome during an operational upset, e.g., flare lines, etc.
4. Process piping
a. Compressor suction lines between the knockout drum and the compressor
shall be heat traced and insulated if ambient temperature is below the dew
point of the gas at compressor suction or if handling hydrocarbon gas
components heavier than ethane.
b. Intermittently used process piping containing liquids such as tars or
chemicals, which will congeal during nonflowing conditions, shall be
provided with valves for venting and draining, blowing out with air or
flushing with light stock in preference to heat tracing.
c. Tank car and tank truck loading lines shall be heat traced and insulated
and provided with valved flushing or blow out connections.
Note:
Blowing out piping with air shall be confined to lines containing stocks of
low volatility which are well below their flash points. Where piping to be
blown discharges into tankage. Venting capacity shall be provided to
prevent pressurizing the tankage.
Page 7 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
Instruments
1. Winterization of instrumentation systems should be in accordance with
Section 8.5 of API RP 550. However, when electronic instruments are heat
traced the type of heat tracing should be to the instrument manufacturer’s
recommendation. Consideration should be given to the use of electrical heat
tracing and also to thermostatic control to ensure the manufacturer’s specified
operating temperatures are not exceeded.
2. Proposals for winterization are to be discussed and agreed with the
Company.
3. Where practical, instruments shall be installed in heated buildings to simplify
protection requirements and facilitate maintenance.
Page 8 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
furnished in the door on houses for indicating transmitters and meters. The
housings for analyzer transmitters are furnished as part of the instrument
assembly.
13. Level instruments
a. Protective provisions for differential type level instruments conform to that,
described for differential type flow instruments.
b. External float instruments are heat-traced for the following services:
- Steam
- Water
- Caustic
- Viscous hydrocarbon with a pour-point -12°C and above
- Light hydrocarbon where hydrate formation is possible.
14. Flow instruments
Differential pressure instruments having factory-filled bellows or diaphragm
assemblies are specified with a fill material that does not require winterizing.
Care should be taken not to overheat diaphragms above their design
temperature.
15. Control valves
a. Control valves are not traced with the associated process piping, except
that valves are steam traced on gas or vapor services with high pressure
drops, where hydrates may be formed, or where freezing or congealing
may occur.
b. When control valves used as direct connected regulators require
winterizing, the pressure control line and valve diaphragm chamber
containing the process fluid shall be heat traced and insulated. When the
diaphragm chamber is sealed, the pressure control line shall be heat
traced and insulated from the point of seal to the process line connection.
c. In light hydrocarbon-vapor services, where hydrate formation or frosting
due to low temperature is likely, only the control valves body shall be heat-
traced.
d. Steam atomizing control valves with diaphragm and in contact with heavy
process fluid shall be protected with seal pot filled with glycerin.
Page 10 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)
Valves
1. Where necessary, relief valves and adjoining piping should be suitably
protected.
2. The vent line relief valves discharging to atmosphere should have a suitable
drain hole at the lowest point.
3. Flanged shut off valves and check valves in vertical lines shall have bodies
trapped and valved above the disk or seat if commodity will freeze or congeal
during shutdown.
4. Water seals and traps should be steam traced.
5. Low points of flare lines should drain into vessels which are suitably protected
against freezing.
Equipment
1. Drum, vessel, storage tanks
a. A drum or vessel containing hydrocarbon and water which operate
normally at 52°C or above, shall be protected by insulating the nozzles,
block valves and drain piping in contact with water.
b. A drum or vessel containing hydrocarbon and water which operates
normally below 52°C shall be protected by steam tracing and insulating
the nozzles, block valves and drain piping in contact with water.
c. All other process vessels containing fluids which may congeal during
dormant periods shall be insulated and if necessary shall be heat traced.
d. Bottoms of fuel gas drums and low points in above ground gas lines shall
be insulated and steam traced.
e. Tanks containing liquids difficult to pump or flow when cold, shall be
equipped with heaters.
f. Steam coils in tanks should consist of a number of sections arranged in
parallel flow, thus avoiding the total loss of tank heating in the event of a
coil section leaking.
g. Roofed or open water tanks (except for potable water tanks) shall have
steam connections to heat and agitate water at intervals to prevent
freezing.
h. Storage tanks shall be equipped with freeze proof type water draw valves.
Page 12 of 32
KLM Technology
Group PROCESS DESIGN OF HEAT Rev: 01
TRACING AND WINTERIZING
Project Engineering Standard
April 2011
(PROJECT STANDARDS AND
SPECIFICATIONS)