The Prospects of Non Conventional Source of Energy in India
The Prospects of Non Conventional Source of Energy in India
India’s estimated potential for electricity generation from renewables is 900 GW. The target set by
the Government of India for capacity addition from RE-based electricity generation is 175 GW by
2022. This comprises 100 GW from solar (60 GW from ground-mounted and 40 GW from rooftop),
60 GW from wind, 10 GW from biomass and 5 GW from small hydro. If this target is realized, the
327 billion units (BU) of electricity thus generated will cover 20% of total demand by 2022.
ELECTRICITY GENERATION
Cumulative
installed
capacity
by 2014-15 3 24 4.1 4.4 35.5
If the target of 175 GW by 2022 is achieved, it would contribute to achieving 19.44% of the total RE potential of 900 GW and
about 20.3% of electricity in the total demand. This would mean generation of around 327 BU of electricity (162 BU from solar,
112 BU from wind, 38 BU from biomass, 15 BU from SHP).[3]
Southern, western, and northern regions of India are expected to install more than 91% of the total target while remaining is
expected to be contributed by north-eastern and eastern regions. Maharashtra has the highest target of 22 GW followed by Tamil
Nadu with 21.5 GW (Fig 1.3).
Despite being the first to set up utility-scale solar power projects, neither Gujarat nor
Rajasthan is the leader in terms of installed capacity. Southern states — Tamil Nadu,
Telangana, and Andhra Pradesh — aggressively implemented their ambitious solar
power policies. Tamil Nadu now leads all Indian states in terms of operational solar
power capacity.
Apart from the availability of surplus land and ample solar radiation resources,
another possible factor that led to the domination of south Indian states in solar power
sector is the lack of adequate fuel to power gas-based power plants in the region.
6
State-wise, Tamil Nadu topped the list with 10.6 GW (10,625 MW) RE installed
capacity, followed by Maharashtra with 7.6 GW (7,647.60 MW) and Karnataka 7.4 GW
(7,457.97 MW). List of state-wise/UT-wise installed capacity is provided in Table 1.5.
Table.1.5: State & U.T. Wise Targets and Installed Capacity
(As of 31 March 2017)
Installed Capacity by March 2017 (MW)
RE Target 2022
State Sector Private Sector Total
1 Delhi 2,762 - 56.27 56.3
Key Points -:
The growth in solar power installed capacity is expected to surpass the installed capacity of wind
power, reaching 100 GW by 2022 from its current levels of 17.05 GW as of January 2018.
Three new solar parks was approved in 2017-18 with a total capacity of 1,523 MW.
Rapidly falling costs has made Solar PV the largest market for new investment.
Further, the scaling up of the target of National Solar Mission to 100 GW from 20 GW of grid
connected solar power by 2022, creates a positive environment for investors those who are keen
to tap into India’s renewable energy potential.
In November 2017, Government of India signed a US$ 100 million agreement with the World
Bank for ‘Shared Infrastructure for Solar Parks Project’.
Due to its favourable location in the solar belt (400 S to 400 N), India is one of the best recipients
of solar energy with relatively abundant availability.
India has a vast potential for solar power generation with about 58 per cent of the total land area
(1.89 million km2 ) receiving above 5 kWh/m2/day annual average global insolation
This coupled with its highest global warming mitigation potential makes it a viable alternative for
power generation among the available clean energy sources.
Under Union Budget 2018-19, zero import duty on components used in making solar panel was
announced to give a boost to domestic solar panel manufacturers.
1.) How much land is required to set up a 1MW solar power generation unit?
= 4.5 acres for crystalline technology and around 6.5-7.5 acres for Thin-Film technology.
9
3.) Can solar power developers avail loan from loans for solar power plant setup? What is the
loan % and what criteria does a bank/lending institution look for?
= There are 2 kinds of Financing mechanisms that are usually discussed- Recourse financing and
Non-Recourse Financing.
Recourse financing requires collaterals and other extensive guarantees from the solar developer who
wishes to avail loan.
Non-Recourse Financing does not require any additional collaterals as the asset or power plant itself
is the collateral in this case.
Now let us look at top 5 states for solar energy investments, based on the above parameters among
others.
1.Karnataka
Karnataka has gained a lot of attention recently, mainly due to some of the attractive solar schemes
the government has come up with. As mentioned before, the Karnataka Land Owning Farmer’s
Scheme offers developers an opportunity to sell power at Rs 8.4/unit. There is also a rooftop scheme
under BESCOM in Karnataka where solar power can be sold at a lucrative rate of Rs 9.56/unit on a
net-metering basis. On top of all this, things are getting in action for a 2000 MW solar park at
Pavagada Taluk in Tumkur District. In fact, NTPC has already invited bids for construction of 750
MW in late Jan followed by a bid for 250 MW in early Feb.
2.Madhya Pradesh
Madhya Pradesh, being the 2nd largest state and having large tracts of unused, undeveloped land, has
seen growing interest in the solar sector. The Welspun Solar MP Project of 151 MW is one of the
largest solar projects in the country. Recently, they even inked an agreement with IFC to build a 750
MW solar plant in Rewa. While MP has not exactly been hitting the headlines as much as states such
11
as Karnataka or AP, it has been making steady progress, and investors are more comfortable with the
overall transparency of this state government, much more than they have been with state
governments such as TN.
3.Andhra Pradesh
Under the JNNSM, NTPC has successfully allocated hundreds of megawatts of projects in several
large solar parks. SunEdison was allocated 500 MW under a historic low tariff of Rs 4.63/unit. This
was followed by SB Energy (a JV between SoftBank, Foxconn and Bharthi Enterprises), surprisingly
securing a tender for 350 MW for the same Rs 4.63/unit. Since the new government (TDP) took over
about 2 years back, things have been happening faster in this state. Most of the happenings so far
have been through NTPC tenders for large scale power plants (and this is the state in which we heard
about the hair raising Rs 4.63/kWh not once, but twice)
4.Gujarat
Without doubt, as in many other areas, Gujarat is a pioneer for solar energy in India. Their solar
model is what other states look up to. Gujarat is to India what Germany is to the world. Not only does
Gujarat have the first and largest solar park in India, the Charanka Solar Park, but they have also set
examples with innovative endeavors like solar canal projects. With regard to installed capacity, they
are slightly behind Rajasthan with close to 1 GW of installations. Gujarat were the pioneers in solar,
having a head start in 2011. But since then, they have lagged. They have a recent (2015) ambitious
solar policy, but little really is happening on the ground. Being a power surplus state does not help
much either in this context.
5. Rajasthan
Being the largest state in the country, there is a huge availability of unused land with the added appeal
of irradiation levels. This was a key factor in the state receiving the maximum share of the JNNSM
Phase-1 allocations with 873 MW out of 1100 MW. And under the second phase of JNNSM, 355
MW was allotted to Rajasthan out of 750 MW. In 2015, it was the first state to cross 1 GW solar
capacity surpassing Gujarat as the new leader in solar power with approximately 1.2 GW capacity.
One of their highlights is the Bhadla solar park at Jodhpur being developed by Rajasthan Renewable
Energy Corporation Limited (RREC). Big players like Adani Enterprises, Essel Infra Projects Ltd,
Azure Power and Reliance Power have already committed to commissioning solar parks in the state.
Rajasthan has many things going for it, but it gets the fifth place in the ranking owing to the policy
uncertainty. I have not seen effective, consistence and transparent policies in the state. Sure, central
government (NTpC and SECI) allotments have happened and will continue to happen, but most of
these allotments do not benefit the small-scale business investors. The state government keeps
making announcements that are big and bold, but so far I have not seen much of these state
government announcements actually convert into action on the field.
A state with good solar potential, but needs a better policy and implementation ecosystem.
Although, currently the above states seem to be attractive in general for solar in India, there are states
like Punjab, Telangana and Maharashtra which are not far behind. In fact, these dynamics will keep
changing over the next couple of years and will depend mostly on solar policies implemented by state
governments.
12
In the case of solar, capital costs in India were 25% lower than those in the U.S. However, most of
this cost advantage was eliminated by the lower expected output per MW, which was likely the result
of lower insolation and higher levels of dust in Rajasthan, where the Indian plant was built, or,
possibly the use of less expensive, but less reliable, equipment. With these two factors offsetting each
other, the Indian solar PV facility was nevertheless 26% more expensive due entirely to the higher
return requirements for investors in India, that is, the more expensive cost of financing the project.
The two wind projects depict a similar story, although the wind project in India is still cheaper,
despite the higher financing costs. While these projects do not rep-resent all U.S. or Indian renewable
projects, and rapid changes to cost and performance lead to constantly changing figures, the
comparison itself is indicative of the substantial impact of financing costs on renewable energy in
India.
The key takeaway is that the renewable projects could be much less expensive if not for the higher
financing costs.
13
14
Solar tariff has declined to lowest level of Rs 2.44 /kWh. The chronology of down ward trend in Solar tariff during
recent times is as given below:
Lowest
S. No Period Capacity Scheme State
Tariff (Rs./KWh)
1 February2017 750 MW 3.30 State Scheme Madhya Pradesh (REWA Solar park)
Rajasthan
2 May2017 250 MW 2.62 VGF Scheme
(Bhadla IV Solar park)
17
Rajasthan
3 May2017 500 MW 2.44 VGF Scheme
(Bhadla III Solar park)
Gujarat (NonSolar
4 Aug17 500 MW 2.65 State Scheme
Park)
As on 30.11.2017 over41.80 lakh Solar Lighting Systems, 1.42 lakh Solar Pumps, and power packs of
181.52 MWeq have been installed in the country. Major achievements of 18.47 lakh Solar Lighting Systems,
1.31 lakh. Solar Pumps, Power Packs of 96.39 MWeq have been reported during last three and half years.
Several schemes namely (i) Defence scheme (ii) Central Public Sector Undertakings (CPSUs) scheme (iii)
Bundling scheme (iv) Canal Bank/ Canal Top scheme (v) VGF Scheme (vi) Solar Park scheme (vii) Solar
rooftops, have been initiated/launched by the Ministry under National Solar Mission which are under
implementation.
Under Defence scheme against a target of 300 MW, 357.50 MW has been sanctioned; under Central Public
Sector Undertakings (CPSUs) scheme against a target of 1000 MW, entire capacity sanctioned; under 3000 MW
Bundling scheme, TranchI: 3000 MW has been tendered; under 100 MW Canal Bank/ Canal Top scheme, all
capacity sanctioned; under 2000 MW & 5000 MW VGF Scheme; and under 20,000 MW Solar Park
scheme, 35 Solar parks have been approved in 21 States with aggregate capacity of 20,514 MW.
Solar Rooftop
Ministry is implementing Grid Connected Rooftop and Small Solar Power Plants Programme which provides for
installation of 2100 MW capacity through CFA/ incentive in the residential, social, Government/PSU and
Institutional sectors.
Under the programme, central financial assistance upto 30% of bench mark is being provided for such projects in
Residential, Institutional and Social sectors in General Category States and upto 70% of the benchmark cost in
Special Category States. For Government sector, achievement linked incentives are being provided. Subsidy/CFA
is not applicable for commercial and industrial establishments in private sector.
So far sanctions for 1767 MWp capacity solar rooftop projects has been issued and around 863.92 MWp
capacity has been installed.
All the 36 State / UT ERCs have now notified net/gross metering regulations and/or tariff orders for rooftop
solar projects
Concessional loans of around 1375 million US dollarsfrom World Bank (WB), Asian Development Bank (ADB)
18
and New Development Bank (NDB) have been made available to State Bank of India (SBI), Punjab National Bank (PNB)
and Canara Bank for solar rooftop projects.
Suryamitra programmehas been launched for creation of a qualified technical workforce and over11 thousand persons
have been trained under the programme.
An online platform for expediting project, approval, report submission, and monitoring of RTS projects has
been created.
Initiated geotagging of RTS projects, in coordination with ISRO, for traceability and transparency.
Launched mobile app ARUN (Atal Rooftop Solar User Navigator) for ease of access of beneficiaries for request
submission and awareness.
MNRE has allocated Ministry wise expert PSUs for implementation of RTS projects in various
Ministries/Departments.
Published best practices guide and compendium of policies, regulations, technical standards and financing
norms for solar power projects.
19