Abdisa
Abdisa
1 Introduction
In Amhara region farming has been simply a way of life and was not a business enterprise till recent
years. Farmers are supposed to produce everything that they need, if possible, for their family. This
recurrent phenomenon though time be come an inherent responsibility of the farmers.
On the other hand frequent drought, land degradation and an increase of extra mouth per year pushes the
farmers to start irrigation agriculture. Farmers divert rivers and irrigate their plots of land. Even though
this traditional activity contributes a lot in Regional total food production, it faced numerous problems.
The major problem is yearly erosion of traditional diversion structures.
Hence to alleviate this problem the Amhara National Regional State Bureau of Water Resource (ANRS-
BoWRD) carried out the study design and construction of irrigation projects in the Region. This technical
study document presents the engineering study of Chacha-2 diversion irrigation project.
1.1 1.2 Objective
The objectives of this paper are:
Hydrology study of the project area
Weir design
Meteorological data
The base flow at the proposed diversion site (Chacha-2) has been estimated and measured to be
0.150m3/sec when the upstream irrigation structures of Chacha-1 existing modern irrigation project were
functioning on the existing situation.
It has been observed that the flow at Chacha-2 gets better recharges from springs and additional
tributaries. Observation and Consideration of the recharging capacity of the downstream river, there are
different additional tributaries for downstream users just after just the proposed irrigation project (chacha-
2) which are released and flow towards to down stream with the discharge of more than 0.035m3/sec of
water.
As to the downstream consideration, the river flows to Abay river basin and no existing irrigation practice
has been seen / not suitable / however for sustaining the existing down stream ecology more than 35lit/sec
of the flow has been released downstream. Chacha-2 was planned after detail analysis of above issues
Measured base flow of all above this project from previous studies can be shown in the table below.
Catchment characteristics
Elivation Max. Length El. Difference
3418-2880 12250 538
2880-2800 7000 80
2800-2739 31000 61
800.00
700.00
500.00 H6
H5
400.00
H4
300.00
H3
200.00 H2
100.00 H1
0.00
9.06
24.2
26.2
28.2
30.2
32.2
34.2
0
1
2
3
4
5
6
7
8
9
10
11.06
13.06
15.06
17.06
19.06
Time in hrs
2 Watershed Outputs
Watershed Size ,Km2 –539.6352
Average Stream Slope,% – 3.697814
3 Weir Body
Weir type – Ogee WES standard weir
To irrigate targeted command the off take level is made at = 2743.0m.
River bed level = 2740.3m
The water depth in the main canal =0.49m
Therefore the total crest level is 2743.6m
Total weir height = 2743.6-2740.3 = 3.3m
The total crest length available at 3.3m height is 46m.
Out of this total length 1.5m is provided for operation slab of offtake arrangement.
Hence the effective weir length is 44.5m
Hydraulic data of weir means fixing the dimension of vertical drop weir. The following is the procedure
of the design.
1. Determination of the crest level
Determination of the crest level of the weir is closely related to afflux, water way or intensity of
discharge and the pond level. It is determined by the permissible maximum value of afflux,
attained during the maximum flood. A crest level can be worked out as below.
Average level of the highest field =780m.
Water depth required=1.43m
Head loss at the turn out =0.1m
Head loss at the head regulator = 0.45m (given)
Slope from the highest field level to the weir =0.002
Distance from the highest field to the weir =400m
bed level of the weir =779.5m
The slope of the canal at 400m distance from the weir =0.002*400 = 0.8m
Crest level = 780 + 0.8 +0.45 +0.1 +1.43 = 782.70m
Pw = 4.75√𝑄
Q – The design discharge in m3/s
2.2.1
Adopt a = 1.5m
2) a = S + 1, where shutter height (No shutter provided).
B) Bottom width (B)
This should be fixed so that there is development of tension on the base of the weir.
𝐻+𝑑 3.2+2.04
i.For primary design 𝐵 = = = 4.88 ≈ 5𝑚
√𝐺−1 √2.24−1
However the actual width of the base should be determined as the maximum of the following
situation.
ii. No flow condition.
This occurs when the u/s water level at the pond level and there is no tail water on the
downstream.
The over turning moment (Mo) about toe the weir
𝛾𝐻𝑠3
𝑀𝑜 = , where Hs = H + s
6
3∗5.269
= [20.58 ] 2/3 = 2.12 MO = 120.21KN-m ………….. (3)
√2∗9.81
Structural analysis deals with checking the stability of the weir against.
i. - Over turning
ii. - Sliding
Force acting on the weir.
Static pressure
Friction force at the base (up lift pressure) to counter balance the sliding
Horizontal force
Weight of the weir
Silt-pressure
But it is observed that from the above three conditions the static conditions ( when there is no flow
downstream is considered the critical one , therefore analysis of the weir only for static condition is
carried out .
Table 3.1 Force and moment acting on the weir
Item Vertical force (KN) Horizontal force (KN) Lever arm Moment about
from the the toe
toe
Pw ½*9.81*3.22=50.23 h/3=3.2/3= -53.75
1.07
W1 3.2*1.5*22.4=107.52 3.5 +1.5/2 = +450.96
4.25
W2 ½*3.2*3.5*22.4=125.44 2/3*3.5 +296.27
=2.33
PS ½*8.19*0.33*0.82 0.8/2 =0.4 -0.35
=0.873
PW ½*9.81*3.2*5=78.48 2/3*5 =3.33 -261.34
Σ 311.44 51.103 ΣM+=749.23
ΣM-=315.44
𝛾𝑠 𝑡𝑜𝑡 = 18 KN / m3
𝛾𝑠𝑢𝑏 = 𝛾𝑠 𝑡𝑜𝑡 − 𝛾𝑤𝑎𝑡𝑒𝑟 = 18KN/m3 – 9.81KN/m3 = 8.19KN/m3
I) Check for over turning
∑ 𝑀+ 749.23
∑ 𝑀−
= = 3.37 > 1.5 … OK!
315.44
P1 = 70.50 KN/m2 P2 = 54.06 KN/m2 < 440 KN/m hence ok! Therefore the weir is safe
against over stress.
= 1.35
Ld = 5(1.35m – 0.65)
= 3.52m
From Bligh’s formula
𝐻
Ld = 2.21C√ 𝐵𝑆 - - - - - for weir shutter provided above the crest
= 2.21*12*√3.2/10
= 15.46 ≈ 16m
Thus the length of d/s impervious floor (Ld=16m)
Total creep length (L) = CHs from Bligh’s formula
Hs=seepage head
=pond level – bed level
=782.70-779.5 =3.2m
L = 12*3.2
= 38.4 adopt L=39
b) Length of u/s impervious floor (Lu)
Lu = L – (Ld+B+2d1+2d2)
=39 – (16+5+2*1+2*4.5)
=39−32
=7m
Correction
1. Due to the thickness of: the correction is positive downstream of the flow and negative
upstream of the flow of the relation to sheet pile.
(𝜙 D1−𝜙C1)t
For 𝜙C1 = where t - thickness of upstream floor.
d1
(88.12−83.08)1
= = 5.04 %
1
2. Due to mutual interference of the line: this correction is positive for the point in the rear or
back water; and subtractive for the point forward in the direction of flow.
𝐷 𝑑+𝐷
For 𝜙𝑐1 =19√𝑏1 ( ) Where D – depth off pile No 2
𝑏
4.5 1+4.5
For 𝜙𝑐1 = 19√ ( ) D = 779.5 – 775.08 = 4.5m
28 28
b) Downstream pile
1+√1+𝛼2 1+√1+6.222
𝜆 = 2
= 2
= 3.65
100 𝜆−2 100 3.65−2
𝜙𝐸 = COS −1 ( )= COS −1 ( ) = 35.06%
𝜋 𝜆 𝜋 3.65
100 𝜆−1 100 3.65−1
𝜙𝐷 = COS−1 ( )= COS −1 ( ) = 24.14%
𝜋 𝜆 𝜋 3.65
𝑑+𝐷
For 𝜙 𝐸 = - 19( ) * √𝐷⁄ ′
𝑏 𝑏
Where D = depth of pile no 1 =1m
d= depth of no 2 = 4.5 m
4.5+1
= - 19( 28
) * √1⁄28 b= total floor length =39m
The hydraulic gradient at the downstream end where water emerges out is called exit gradient. When
the pressure due to particular exit gradient is such that is equals submerged weight of soil particles the
exit gradient is called a critical exit gradient.
1
For safety exit gradient should always be less than this critical value. The critical gradient varies from
4
1
to 7 for different formations. [Sahasrabudhe, 1994)
1+√1+∝2 1+√1+6.222
λ= 2
= 2
= 3.65
𝐻 1 3.2 1
GE = 𝑑𝑆 × = 4.5 × 𝜋√3.65
2 𝜋√𝜆
1
GE = 0.12 < --------------- 0K!
7
=62.18%
62.18∗3.2
Residual head (h) = 100
=1.99m
ℎ 1.99
Thickness of floor at ‘A’ = 𝐺−1 = 2.24−1 = 1.61 < 2.21--------ok!
𝜙𝑐1 −𝜙𝐸
Percentage pressure at ‘B’ = 𝜙𝐸 + 𝑏
∗ 𝑙𝑏
(89.61−25.62)
= 25.62+ 28
∗11
=50.76%
50.76∗3.2
Residual head (h) = 100
=1.63m < 1.76m ----------------ok!
𝜙𝑐1 −𝜙𝐸
Percentage pressure at ‘C’ = 𝜙𝐸 + 𝑏
∗ 𝑙𝐶
(89.61−25.62)
= 25.62+ 28
*6
= 39.33%
39.33∗3.2
Residual head (h) = 100
= 1.26
ℎ 1.26
Thickness of the floor at ‘C’ = 𝐺−1 = 1.24 =1.02m < 1.32m
They are opening provided in the body of a weir or any cut at low levels. They are located in the
smaller compartment in front of still pond. These sluices are perfectly control by means of gates
which are operated from top.
Naturally the sluices should be located quite below the crest of the head regulator (Generally
1.8m below). Thus the scouring sluices maintenance the channel clear and defined in front of the
head regulator.
The sluices can also be used during the peak flood period to the lower discharge over the crest of
the weir.
Under sluices is used for quick lower of u/s high flood level because the discharge intensity over
the sluice portion is greater than that is the weir portion [Sahasrabudhe, 1994]
20.922 1
R = 1.35( )3 = 10m
1
H=0.55
H1=0.85
3
2
5.86 = 3 ∗ 0.577 ∗ √2 ∗ 9.81 ∗ 𝐵(0.55)2 + 0.8 ∗ 0.85√2 ∗ 9.81 ∗ 0.85 ∗ 𝐵
5.86 = 0.695B+2.78B
B= 1.68m adopt B= 1.7m
Provide 2 piers of 1.5m thickness each on the side (Garge 2003)
Overall waterway of the regulator = 1.5*2+2=4.5m
Figure 3.2 section of head regulator for the pond level flow condition
It is constructed at right angle to the weir axis. It divides the river channel in to compartment.
Thus in the smaller compartment, which is nearer to the head regulator, a still pond is created.
Divide wall have the following functions:
It separates the floor of the scouring sluice from that of the weir proper.
It provides comparatively still pocket in front of the canal head regulator so that
silt gets deposited in it and relatively clear water enters the canal.
It helps in the minimizing the effect of the main river current on the flow
condition in the head regulator.
Dimensions of divide wall
- Width of the head regulator, B= 1.7.0m
- The length of divide wall on the upstream = 0.58*B=0.58*1.7 = 0.99m
- D/S extends up to the end weir glacis(toe) = 6m
- Dived wall height = 4m
- The top width of the wall =1.5m (slope 0.5H:1V) [Arora 2002]
2.11 d) Silt Excluder
It is a structure which excludes the silt from irrigation water as the name implies. It separates the lower
silt laden portion of the water from the upper silt free portion. It consists of a series of parallel tunnels
of low height. The tunnels are constructed in the pocket parallel to the flow of water in the river. The
height of the tunnels depends upon the silt distribution in the flow of the water.
2.12 Design of silt Excluder
It is design that the bottom layer of water which is highly charged with silt and sediment will
pass down the tunnels and escape over the floor of the under-sluice way(s),since the gates of the
under sluice way(s) shall be kept open up to the top of the tunnels. The clearer water over the top
of the roof of the excluder tunnels will thus enter the canal through the head regulator.
Design procedure
- Full supply discharge of canal = 5.86𝑚3 /𝑠𝑒𝑐
- Crest level of the under sluice = 779.5m
- Crest level of the head regulator = 781.3m
- Usually, two or three bays of under sluice o f the weir are covered by the excluder.
However excluder covering only one bay has been designed [Garge 2003]
- Design discharge =15% to 20% of canal discharge [Garge 2003]
20
Q = 100 ∗ 5.86 = 1.17𝑚3 /𝑠𝑒𝑐
Height of tunnels generally varies from 0.5 to 0.6m for Sandy River and 0.8 to 1.2m for boulder Stage
River. [Garge 2003]
Assuming thickness of roof slab =0.2m
Height of tunnel (h) =781.3-0.2-779.5=1.6m
𝐴 0.58
Total clear width =ℎ = 1.6
= 0.36𝑚
P = B+2D (m 2 1) =B+ 5D , R=
A
P
2
0.2 D 0.5D 2
AR 3 (0.2 D 0.5D 2 ) ………………………..(2)
0.2 5D
Combining (1) and (2)
0.2D 0.5D
5
2 3
0.004773=
0.2D
2
5*D 3
FB
Fig 6.1
B
2 Watershed Outputs
Watershed Size ,Km2 –539.6352
Average Stream Slope,% – 3.697814
3 Weir Body
Weir type – Ogee WES standard weir
To irrigate targeted command the off take level is made at = 2743.0m.
River bed level = 2740.3m
The water depth in the main canal =0.49m
Therefore the total crest level is 2743.6m
Total weir height = 2743.6-2740.3 = 3.3m
The total crest length available at 3.3m height is 46m.
Out of this total length 1.5m is provided for operation slab of offtake arrangement.
Hence the effective weir length is 44.5m
Assume afflux=1m(Assumption)
Retrogression=0.5m(source .KRArora)
D/S HFL=2748.783-1
=2747.783m
D/S HFL before construction
=D/S HFL – Retrogression
=2747.783 – 0.5
=2747.283m
Design of Weir Wall
The weir wall is proposed to be trapezoidal cross-section with u/s face vertical and d/s face
with slope 1:1.
The top width of weir wall (B ' ) is given as
H
B'= where, B ' = Top width of weir wall and is
G 1
Generally 1.5 to 1.8m
H=Head of water over the weir wall at the
time of max. flood
G=Specific gravity of floor material
H=He-ha
=5.18-0.077
=5.1m
5.1
B'=
2.24 1
=4.58m
Note: Since B ' =4.58m is out of range (1.5-1.8m), take B ' =1.5m
Top width (B ' ) =1.5m
The bottom width (B) of the weir wall should not be less than
H Heightofweir
B=
G 1
5.1 3.3
B=
2.24 1
=7.5m
6.6 Design of weir wall
Depth of water over crest (Hd )=U/S HFL-crest level =1194.1-1192.02=2.1m
Top width(a)
Can be fixed as the largest of the following three equations
Bottom width(B)
1. No flow condition
This condition is when the water level on the U/S is at the pond level. The over turning movment is
due to
Hs=H+s=2.22+0=2.22m
Where Hs is seapage analysis head
=29.7m
Length of downstream impervious floor, l 2
Hs
L 2 =2.21*C
10
3.3
=2.21*9
10
=11.4m
Length of upstream impervious floor, L 1
L 1 =L- (L 2 +B+2d 1 +2d 2 )
=29.7-(11.4 +1.5+2*3.7+2*7.78)
=-ve
For the u/s impervious floor let us take nominal value of L 1 = 3m
Therefore, total length of impervious floor b, will be
b=L 1 +B+L 2
=3+7.5+11.4
=22m
Total creep length changed into=b+2d 1 +2d 2
=22+2*3.7+2*7.78
=45m
Protection Work
a) D/S protection work
The total length of d/s floor and d/s protection work is given by
=L 2 +L 3
Hsq
=18C
10q s
3.3 *18.1
=18*9
10 * 75
=45.7m
During the flood season, when high flood occurs over the weir crest water falls from the
maximum reservoir level of u/s to the d/s tail water and the difference b/n the u/s and d/s energy
grade line becomes very high. Therefore ,the energy must be dissipated before it reaches the
natural river source: other wise it causes damage to d/s of the apron. The energy tends to
dissipate through a hydraulic jump d/s of the weir .To control the location of the jump stilling
basin is designed.
Conventional Method
It is experimental formula to determine the length and depth of stilling basin.
L=3* hf
1
D= hf
2
Where :f/2 >=d>=f/3
L=Length of basin
D=depth of basin
h=over flow depth
f=u/s water level +velocity head –d/s water level.
f=2748.783+0.077-2747.783=1.077m
h=5.18m
f/2>=d>=f/3, 0.54<d<0.36
Correction for mutual interference
D d D
Correction=19* *
b' b
Where, D=Depth of pile whose effect is required on the another pile
(D=8-1.87=6.13)
'
b =Distance b/n two piles
=22m
b=Total floor length, b=22m
d=the depth of the pile on which the influence occur (d=2.9-0.8=2.1m)
6.26 2.1 6.26
Correction=19* *
21.5 21.5
=3.99% (+ve)
Therefore, corrected C 1 (67.72 2.75 3.99)
=74.46%
b) Downstream pile:
b=21.5m, d 2 8.0m , 2.69m, 1.93
100 2
E cos 1
=51.15%
100 1
D cos 1
=34%
Thickness correction for E
D
E E *1.74
d2
=3.73%(-ve)
Correction for mutual interference
D d D
Correction=-19* *
b' b
6.26 2.1 6.26
=-19* *
21.5 21.5
=-3.99%(-ve)
Corrected E 51.15 3.73 3.99
=43.43%
Percentage pressure at A
C1 ECorrected
= ECorrected * lengthofd / sfloor
b
=43.43+
74.46 44.43
*11.3
21.5
=59.21%
Residual head, h=0.59*3.15
=1.87m
h 1.87
Thickness of the floor = 1.5 2.2m………….Ok
G 1 1.24
Percentage pressure at B
=43.43+
74.46 44.43 * 5
21.5
Residual head, h=0.5*3.15
=1.59m
1.59
Thickness of the floor = 1.28 1.74m…………….Ok
1.24
Hence the floor is safe by Khosla ' s theory
2 Up lift pressure
a. Up stream pile
29.5
b=21.5m, d1=2.9m, 7.41 , 4.24
2 .9
t=0.8(assumed)
E1
C1
d1=2.9m d2=8m
D1
Fig 7.1 D2
100 2
E COS 1 , C1 100 E
=67.72%
=32.28%
100 1
D cos 1 D1 100 D
=22.32% = 77.68%
Thickness correction for c1
d C1
c1 1 * t =2.75%
d1
3.2 7.5 Stability analysis of weir
Dynamic case
Uplift pressure is considered for the weir wall.
Water wedge weight is considered for weir crest only
Unit weight of water and masonry is taken to be 9.81 and 22.4 KN/m 3 respectively.
Moment is taken about the toe per meter widt
HFL
PH1
PH1
H=3.3m
PH2 W1 W2
PH2 y1 PH3
PH3
w(H+Hd)= wHt
Pu
9m
P2 P1
Fig.7.2
He=5.26m
Ha=0.077m
Hd=He-Ha=5.18m and y1=1.54m,y2=5.8m(by trial and error)
Table 7.1
Static case
W1
PH1 PH W2
H H
wH
Pu
Fig. 7.3
V 197.67 H 48.67
M 600O M 1484.45
R
Safety factors
Overturning stability, S o
M R
1484.45
2.47 1.5 Safe
M O 600
Sliding stability, S s
H 48.67 0.25 0.75 OK!
V 197.67
Check for tension, x
M
884.62
4.48
V 197.67
B 7.3 B 7.3
e x 4.48 0.83, 1.22
2 2 6 6
B
e=0.83 1.22 OK! No tension.
6
3.3
Impervious floor
Hs
Min. length of d/s impervious floor, L2 3.87
10
Where H=Hs=3.15mC=9 (for boulder foundation Dr.K.A.Arora, 2002)
3.15
L2 3.87 * 9 =19.55m 20m.
10
Min. length of u/s impervious floor,
L1 L L2 B 2d1 2d 2 28.35 20 7.3 2 * 4.31 2 * 9.44 26.47m
Therefore, take nominal value of 2m for u/s length.
Protection work
Total length of d/s impervious floor and protection work
H q 3.15 25
L2 L3 27C s * 27 * 9 * * 78.74m
10 75 10 75
Length of the d/s protection work, L3 L2 L3 L2 78.74 20 58.74m. this length is both
inverted filter and launching apron.
L3 58.74
Length of the u/s protection work, L4 29.37m.
2 2
3
3 3
And Qw C d LH 2 1.7 *10 * 8.47 2 209.21m / sec Discharge through the proper weir with
3
length, L=10m.
Therefore, the total discharges,
Qs Qw Qs 209.21 84.06 293.27m 3 / sec Q 250m 3 / sec ok
7.7 Design of head regulator
It is provided at the head of the off taking canal and has the following objectives;
To regulate the supply of water in to the canal
To completely shutout the high flood from entering to the canal.
To control the entry of silt to the canal.
The regulation is provided by the gate which is fixed in such a way that, the discharge or
desired capacity of water can easily flow in to the intake canal. The intake canal is placed so
as the top level should be less than or equal to the crest level of the proper weir.
Crest levels
1) Under sluice=the crest level of under sluice is equal to the river bed level=1846.87m.
2) Head regulator=is kept 1.2 to 1.5m higher than the crest level of the under sluice (say
1.5m) =1846.87+1.5=1848.37m.
Bed level of canal=crest level of head regulator-canal flow depth
=1848.37-0.65=1847.72m.
7.8 Design of retaining wall (Guide wall)
To avoid out flanking of the river due to the control structure across the river a masonry guide
wall is provided. Considerations;
Analysis per meter span and moment heel
Earth pressure at rest was considered
m 22.4 KN / m , w 10 KN / m , soil 18KN / m
3 3 3
The d/s wing walls are kept straight for a length of 5 to 8 times the square root of the product of
head of water over the crest and difference between U/S HFL and D/S HFL.
Therefore, d/swing;
L 5 H e H a * U / SHFL D / SHFL 5 5.53 0.41 * 1854.93 1853.93 11m.
Upstream retaining wall
Data available
River bed level=1846.87m
U/S HFL=1854.93m
w 10 KN / m , m 22.4 KN / m , soil 18KN / m
3 3 3
Angle of repose 30 0
Top width=1.0m (source soil mechanics Arora)
Free board(FB)=0.5m(assumed)
Anchored depth below river bed =0.5m (source soil mechanics Arora)
Therefore, height of wing wall
H=Anchored depth+ (U/S HFL- river bed level) +FB
H=0.5+ (1854.93-1846.87) +0.5=9m.
Bottom width, B=50% TO70% Of H, Say 70%
B=0.7*9=6.3m
Ws1
Ww1 8.5m
Fig. 7.4 Ws2
H=9m WW3 Ps1
5.3m
1m
Table 7.3 Forces and moments acting on u/s retaining wall
No Item Forces Lever Moments(KN-
(KN) arm(m) m)
Vertical horizontal Overturning restoring
1 Ws1 siol * A1 328.95 3.86 1271.94
2 Ws 2 siol * A2 153 5.8 887.4
3 Wm1 m * Am1 190.4 0.5 95.2
4 Wm 2 m * Am 2 409.36 2.43 996.1093
5 Wm3 m * Am3 70.56 3.15 222.264
6 Ps 0.5 * K o * soil * H 2 243 3 729
Overturning stability, S o
M o
3472.913
4.764 1.5, OK !
M R 729
B/6=6.3/6=1.05m
B
Since e=0.77m 1.05m no tensión.
6
Downstream retaining wall
D/S HFL=1853.93m
Free board (FB) =0.4m (assumed)
Top width=1.0m (source soil mechanics Arora)
Anchored depth below river bed=0.6m (source soil mechanics Arora)
Therefore, H=0.6+ (1853.93-1846.87) +0.4=8m.
Bottom width, B=0.7*8=5.6
1m
WW1 WW2
Wm1
7.4m
W M2
PS
W M3 0.6m
4.6m
Overturning stability, S O
M O
2444.5332
4.77 1.5, OK !
M R 512
H 192 0.21 0.65, OK!
Sliding stability, S S
V 912.352
Check for tension, x
M 1932.5332 2.12m, e B x 5.6 2.12 0.682m
V 912.352 2 2
B/6=5.6/6=0.93m