LABOUR PRODUCTIVITY CHART UAE

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


CARPENTRY WORKS

Item No. CREW SIZE Hourly Production


Production Rate Per 10 hrs.
(Sqm)
FW FORMWORK
FW01 Formwork to footings 2 CARPENTERS, 1 HELPER 1.2 12
FW02 Formwork to isolated footings 2 CARPENTERS, 1 HELPER 1.6 16
FW03 Formwork to rafts 2 CARPENTERS, 1 HELPER 1.4 14
FW04 Formwork to rafts D>0.75m 2 CARPENTERS, 1 HELPER 1.8 18
FW05 Formwork to tie beams 2 CARPENTERS, 1 HELPER 1.0 10
FW06 Formwork to high level tie beams D>0.45M 2 CARPENTERS, 1 HELPER 1.2 12
FW07 Formwork to Neck Columns 2 CARPENTERS, 1 HELPER 4
FW08 Formwork to U/G Water tank 2 CARPENTERS, 1 HELPER 6
FW09 Formwork to basement retaining walls 2 CARPENTERS, 1 HELPER 9
FW10 Formwork to columns (small size) 2 CARPENTERS, 1 HELPER 7
FW11 Formwork to Columns (large size) 2 CARPENTERS, 1 HELPER 9
FW12 Formwork to D/S beam internal (shallow) 2 CARPENTERS, 1 HELPER 6
FW13 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 7
FW14 Formwork to D/S beam external (Shallow) 2 CARPENTERS, 1 HELPER 4
FW15 Formwork to D/S beam external (Deep) 2 CARPENTERS, 1 HELPER 6
FW16 Formwork to lift walls single core 2 CARPENTERS, 1 HELPER 6
FW17 Formwork to lift walls multi core 2 CARPENTERS, 1 HELPER 8
FW18 Formwork to slab decking (10ft) hourdi 2 CARPENTERS, 1 HELPER 1.6 16
FW19 Formwork to slab decking (>10ft) hourdi D/S beams 2 CARPENTERS, 1 HELPER 1.2 12
FW20 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.2 12
FW21 Formwork to slab decking (>10ft) hourdi 2 CARPENTERS, 1 HELPER 1.0 10
FW22 Formwork to staircase (non spiral) 2 CARPENTERS, 1 HELPER 4
FW23 Formwork to balcony parapets 2 CARPENTERS, 1 HELPER 6
FW24 Formwork to roof parapets 2 CARPENTERS, 1 HELPER 8

D = DEPTH Page 1 of 7
U. GR. = UNDERGROUND
D/S = DECK - SLAB
> = GREATER THAN
< = LESS THAN
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
CARPENTRY WORKS

Item No. CREW SIZE Hourly Production


Production Rate Per 10 hrs.
(sqm)
FW 25 shutter Manufacture for pile caps 1 CARPENTER + 1 HELPER 2.00 20
FW 26 shutter Fix for pile caps I CARPENTER + 1 HELPER 1.50 30
FW 27 Deshutter footings/pile caps 1 HELPER 6.00 60
FW 28 Shutter make column necks 1 CARPENTER + 1 HELPER 1.50 15
FW 29 Shutter fix column necks 1 CARPENTER + 1 HELPER 1.20 12
FW 30 Deshutter Column necks 1 HELPER 4.80 48
FW 31 Shutter make tie beams 1 CARPENTER + 1 HELPER 1.20 12
FW 32 shutter fix tie beams 1 CARPENTER + 1 HELPER 1.00 10
FW 33 Column shutter making 1 CARPENTER + 1 HELPER 1.20 12
FW 34 Column shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 35 Column deshuttering 1 HELPER 4.00 40
FW 36 Walls shutter making 1 CARPENTER + 1 HELPER 1.50 15
FW 37 Walls shutter fixing 1 CARPENTER + 1 HELPER 0.80 80
FW 38 De shutter Tie beam shutter 1 HELPER 4.00 40
FW 39 Wall formwork deshuttering 1 HELPER 3.20 32
FW 40 Staircase formwork making 1 CARPENTER + 1 HELPER 0.80 8
FW 41 staircase formwork fixing 1 CARPENTER + 1 HELPER 0.80 8
FW 42 Staircase formwork deshuttering 1 HELPER 1.60 16
FW 43 Drop beams formwork making 1 CARPENTER + 1 HELPER 1.00 10
FW 44 Drop beams formwork fixing 1 CARPENTER + 1 HELPER 0.80 8
FW 45 Drop beams formwork stipping 1 HELPER 3.20 32
FW 46 suspended slab formwork fixing 1 CARPENTER + 1 HELPER 1.20 12
FW 47 suspended slab formwork deshutter 1 HELPER 5.00 50
FW 48 Formwork fixing for sunshades 1 CARPENTER + 1 HELPER 0.70 7
FW 49 Parapet formwork making 1 CARPENTER + 1 HELPER 1.20 12
FW 50 Parapets formwork fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 51 Parapets formwork stripping 1 HELPER 4.00 40
FW 53 Fixing of lintle formwork 1 CARPENTER + 1 HELPER 0.50 5
FW 54 Deshutter lintle formwork 1 HELPER 2.00 20
FW 55 Deck formwork fixing 1 CARPENTER + 1 HELPER 1.50 15
FW 56 Deck Formwork deshuttering 1 HELPER 6.00 60
FW 57 Pipe scaffolding erection for slab 1 SCAFFOLDER 0.85 85
FW 58 inverted beam shutter fixing 1 CARPENTER + 1 HELPER 1.00 10
FW 59 De-Shuttering Manholes, square - circular (Timber) 1 CARPENTER + 1 HELPER 4.0 m2 40m2
FW 60 Manhole Shutter erection - square or circular(Timber) 1 CARPENTER + 1 HELPER 1.5 m2 15m2
2
FW 61 Metal Shutter for Manholes 1 CARPENTER + 1 HELPER 1.0 m 10m2
FW 62 Metal Shutter for Precast Beams 2 CARPENTERS + 2 HELPERS 3.0 m² 30m²
FW 63 Metal Shutter for Pile caps 2 CARPENTERS + 2 HELPERS 3.0 m² 27m²
FW 64 Metal Shutters for Pile cap Beams 2 CARPENTERS + 2 HELPERS 3.0 m² 30m²

Page 2 of 7
LABOUR PRODUCTIVITY CHART UAE

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


REINFORCEMENT

Item No. CREW SIZE Hourly


Production Rate

RF REINFORCEMENT
RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 25
RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 20
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 18
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER 20

RF 01 Fix Rebar to footings & tie beams 1 STEEL FIXER 78


RF 02 Fix Rebar to walls, columns, beams, solid slabs 1 STEEL FIXER 38
RF 03 Fix rebar to ribs of hourdi slab 1 STEEL FIXER 35
RF 04 Fix rebar to mesh reinforcement 1 STEEL FIXER 15
RF 05 Fix rebar to hidden beams 1 STEEL FIXER

RFC 01 Steel cutting and bending 18.25 mm 1 STEEL FIXER 50.00


RFC 02 Steel cutting and bending 8 - 16 mm 1 STEEL FIXER 40.00

EXCAVATION
EX 1 Manual Excavation 1 HELPER
EX 2 Backfill + levelling 1HELPER
EX 3 Shaping of sloped earth for blinding for bases including compaction 1 MASON + 2 HELPER
LABOUR PRODUCTIVITY CHART UAE

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


MASONRY WORKS
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR CERAMIC WORKS
MCR 13 Ceramic skirting by glue 1 MASON, 1 HELPER 2,5 M 25 Meter
MCR 14 Ceramic skirting by glue to halls, corridors 1 MASON, 1 HELPER 3M 30 Meter
MTW TILING WORKS
MTW 01 Mosiac / Terrazo tiles to roofs 1 MASON, 1 HELPER 1,6 16 sqm
MTW 02 Mosiac / Terrazo tiles to floors 1 MASON, 1 HELPER 1,4 14 sqm
MTW 03 Mosiac skirting to halls 1 MASON, 1 HELPER 2,5 25 Meter
MTW 04 Mosiac skirting flush / recessed 1 MASON, 1 HELPER 1,4 14 Meter
MTW 05 Grouting / sealing to roof / floor tiles 1 HELPER 2,5 25 Meter
MKP KERBING / BLOCK PAVING WORKS
MKP00 P.C.C. Curve kerb base (to curves) 1 MASON, 1 HELPER 2,5 25 Meter
MKP01 PCC to kerb base (Straight line) 1 MASON, 1 HELPER 3,0 30 Meter
MKP02 Haunching to kerb base (Dumpes) 1 MASON, 1 HELPER 4 40 Meter
MKP03 kerbstonse (Without PCC) 1 MASON, 1 HELPER 1,5 15 Meter
MKP04 Interlock paving on pre prepared sub - base 1 MASON, 1 HELPER 2 sqm
MKP05 Screed works including preparation 1 MASON, 1 HELPER 1,5 15 sqm
MKP06 Haunching ot Kerb Base (Mixing Truck) 1 MASON, 1 HELPER 10 M 100 Meter
DRW MANHOLE/ DRAINAGE CONSTRUCTION
DRW 01 Excavation for drains / manholes 1 HELPER 5 cu. meter
DRW 02 Backfill to drains / manholes 1 HELPER 10 cu. meter
DRW 03 Blockwork to manholes 1 MASON, 1 HELPER 2 Nos
DRW 04 Plaster to manholes 1 MASON, 1 HELPER 2 Nos
DRW 05 Benching to manholes 1 MASON, 1 HELPER 4 Nos
DRW 06 Fix covers to manholes 1 MASON, 1 HELPER 2 Nos
DRW 07 Fix gulley traps 1 MASON, 1 HELPER 1 Nos
DRW 08 Laying of P.V.C. sleeves 4" - 12" 4 HELPER 24M 240 Meter
MLW MISCELLANEOUS LABOUR WORKS
MLW01 Bitumen paint to concrete blockwork surfaces 1 HELPER 4 40 sqm
MLW02 Bitumin painting Bases / piles 1 HELPER 7.00 70
MLW03 Hacking of concrete surfaces 1 HELPER 5 50 sqm
MLW04 fixing of flexcell sheets 1 HELPER 6 sqm
MLW05 pile cutting/dressing 1 HELPER 1 Nos
MLW06 pile cutting/dressing (small diameter) 1 HELPER 2 Nos
MLW07 Vertical sealant (12 mm) 1 HELPER 2,5 25 Meter
MLW08 Horizontal sealant (12 mm) 1 HELPER 5 50 Meter
MLW09 Roof preparation for lw concrete 1 MASON, 1 HELPER 5 50 sqm
MLW10 Angle fillet fixing 1 MASON, 1 HELPER 4 40 Meter
MLW11 Hourdi block shifting and fixing to slab 2 HELPER 20 200 Nos
MLW12 Polythene sheet fixing 1 HELPER 3m 30
MLW13 Shaping of Soil Blinding 1 MASON + 1 HELPER 1M 10 Meter
MLW14 Protection Board installation 1 CARPENTER + 1 HELPER 8M2 80M2
MCW MISCELLANEOUS CARPENTARY WORKS
MCW 01 A/C subframe manufacture / fixing 1 CARPENTER 5 Nos
MCW 02 Door subframe manufacture / fixing 1 CARPENTER 4 Nos
MCW 03 Water bar fixing 1 CARPENTER 2M 20 Meter

Page 4 0f 7
LABOUR PRODUCTIVITY CHART UAE

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


BLOCKWORK PLASTERING WORKS
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
M MASONARY WORKS
MBW 01 Hollow Blockwork (100, 150 & 200 mm) 1 MASON, 1 HELPER 12 Nos 120 Nos
MBW 02 Hollow Blockwork (large panels) 1 MASON, 1 HELPER 14 Nos. 140 Nos
MBW 03 Solid blockwork 1 MASON, 1 HELPER 9,5 95 Nos
MBW 04 Solid Blockwork as Raft forms 1 MASON, 1 HELPER 11 110 Nos
MPL PLASTERWORK 1.2
MPL 01 Plaster (internal), walls final coat 1 MASON, 1 HELPER 1.6 16 sqm
MPL 02 Plaster (internal), walls rush coat 2 HELPER 1.4 150 sqm
MPL 03 Plaster (internal), walls mesh 1 HELPER 1.8 100 sqm
MPL 04 Plaster (internal), walls hacking 1 HELPER 1 100 sqm
MPL 05 Plaster (internal), walls guide point 1 MASON, 1 HELPER 1.2 100 sqm
MPL 06 Plaster (internal), walls corner beads 1 MASON, 1 HELPER 10 SM 100 sqm
MPL 07 Plaster (external), walls with grooves 1 MASON, 1 HELPER 10 SM 10 sqm
MPL 08 Plaster (external), walls without grooves 1 MASON, 1 HELPER 1,2 12 sqm
MPL 09 Plaster (external), walls rush coat 2 HELPER 15 SM 150 sqm
MPL 10 Plaster (external), walls mesh 1 HELPER 10 SM 100 sqm
MPL 11 Plaster (external), walls hacking 1 HELPER 10 SM 100 sqm
MPL 12 Plaster (external), walls guide points 1 MASON, 1 HELPER 10 SM 100 sqm
MPL 13 Plaster (external), walls corner beads 1 MASON, 1 HELPER 10 SM 100 sqm
MPL 14 Plastering of Arches/Mullians 1 MASON, 1 HELPER 0.8 80
MPL 15 Floor screed 50mm thick 1 MASON, 1 HELPER 2 20
MPL 16 Roof screed 100 mm thick 1 MASON, 1 HELPER 1.5 15
MPL 17 Mosiac floor Tiles fixing 1 MASON, 1 HELPER 1.6 1.5
MPL 18 Floor Screed 25mm thick 1 Mason + 1 Helper 0,6 6
MCR CERAMIC WORKS
MCR 01 Ceramic tiles to walls by mortar 1 MASON, 1 HELPER 1.2 8 sqm
MCR 02 Ceramic tiles to walls, mortar to corridors 1 MASON, 1 HELPER 1 9 sqm
MCR 03 Ceramic tiles to walls, cut pieces 1 MASON 2 20 sqm
MCR 04 Ceramic tiles to walls grouting 1 HELPER 5 50 sqm
MCR 05 Ceramic tiles to walls, by glue 1 MASON, 1 HELPER 1,2 12 sqm
MCR 06 Ceramic tiles to walls, corridors, by glue 1 MASON, 1 HELPER 1,3 13 sqm
MCR 07 Ceramic tiles to walls, by glue, cut pieces 1 MASON 2 20 sqm
MCR 08 Ceramic tiles to walls, by glue, grouting 1HELPER 5 50 sqm
MCR 09 Ceramic tiles to floors 1 MASON, 1 HELPER 1 10 sqm
MCR 10 Ceramic tiles to floors in halls 1 MASON, 1 HELPER 1,2 12 sqm
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 sqm
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 sqm
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60
PRODUCTIVITY RATES FOR ALL PROJECT WORKS:
BLOCKWORK PLASTERING WORKS
Item No. CREW SIZE Hourly Production
Production Rate Per 10 hrs.
Per Unit
MCR 11 Ceramic tiles to floors, cut pieces 1 MASON 2 20 sqm
MCR 12 Ceramic tiles to floors, grouting 1 HELPER 5 50 sqm
MCR 13 Marble flooring 1 MASON + 1 HELPER 0.60 60

Page 3 of 7
LABOUR PRODUCTIVITY CHART UAE
PRODUCTIVITY RATES

TILING WORKS

Productivity Rates for Tilling

Size. (Cms) Location Area Manpower Production Rate Remarks


(Sqm. Per day)

30 X 30 Floor Kitchen 1 Mason, 1 Helper 14 Residential Area by Sub-Contractor

30 X 30 Floor with pattern Corridor 1 Helper, 2 Masons 10 Residential Area by Sub-Contractor

40 X 40 Floor Bed room 1 Mason, 1 Helper 22-25 Residential Area by Sub-Contractor

20 X 20 Floor Store (small area) 1 Mason, 1 Helper 10 Residential Area by Sub-Contractor

30 X 60 Floor Bathroom 2 Mason, 1 Helper 6 Residential Area by Sub-Contractor

30 X 30 Floor + Wall Bathroom 2 Mason, 1 Helper 5

10 X 10 Wall Kitchen 1 Mason, 1 Helper 8-9 Residential Area by Sub-Contractor

30 X 60 Wall Corridor 1 Mason, 1 Helper 14-15 Residential Area by Sub-Contractor

30 X 30 Wall Bathroom 2 Mason, 1 Helper 7 Residential Area by Sub-Contractor

Residential Area by Sub-Contractor

Notes:

1. 1 Day = 10 hrs.

2. Gang Size:

1 Mason + 1 Helper for Kitchen and Bedroom.

2 Mason + 1 Helper for Bathroom.