Construction Non Conformance Report

This construction non-conformance report documents very poor bricklaying workmanship at the Freshwater Laboratory Complex project in Pekan, Pahang, Malaysia. The report notes substandard brickwork at the level 1 quarters studio unit and assigns reference number NCR/TCHINI/P2/CASB/ARCH/003. It requires the contractor to propose corrective actions and a completion date to address the non-conforming work.

Uploaded by

Syafiq Ishak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
344 views1 page

Construction Non Conformance Report

This construction non-conformance report documents very poor bricklaying workmanship at the Freshwater Laboratory Complex project in Pekan, Pahang, Malaysia. The report notes substandard brickwork at the level 1 quarters studio unit and assigns reference number NCR/TCHINI/P2/CASB/ARCH/003. It requires the contractor to propose corrective actions and a completion date to address the non-conforming work.

Uploaded by

Syafiq Ishak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION NON CONFORMANCE REPORT

PROJECT / PACKAGE The proposed construction and completion of Freshwater Laboratory


TITLE Complex (Phase 2), Tasik Chini, Pekan, Pahang Darul Makmur for the East
Coast Economic Region Development Council (ECERDC)
Activity Laying Bricks
Details of Non Conformance :

Very poor workmanship of laying bricks.

Location : Quarters (Studio Unit – level 1)

Attached : Photo
NCR Reference NCR / TCHINI / P2 / CASB / ARCH / 003
Issued by Consultant Company Signature
/ LCCPSB Name Date
Issued to Contractor Company Signature
Name date
Roof Causes of Non-Conformance:

Attached :
Correction Corrective Action Proposed/Agreed Completion Date : ___________

(Use separate sheet if necessary)

Verification of Action Taken :

Complied By Name Signature Date


Contractor
Approved By Name Signature Date
Consultant
Accepted By Name signature date
KLCCPSB