The document is a report requesting approval for planned power outages from the OCC meeting. It includes 12 outage requests from various owners including Power Grid Corporation of India Limited, Uttar Pradesh Power Transmission Corporation Limited, NTPC Limited, and Rajasthan Rajya Vidyut Prasaran Nigam Limited. The requests are for maintenance, testing, commissioning and other work on transmission lines, transformers, reactors, and busbars at different voltage levels between May 3rd and May 18th 2018. The total outage times range from 6 to 274 hours.
The document is a report requesting approval for planned power outages from the OCC meeting. It includes 12 outage requests from various owners including Power Grid Corporation of India Limited, Uttar Pradesh Power Transmission Corporation Limited, NTPC Limited, and Rajasthan Rajya Vidyut Prasaran Nigam Limited. The requests are for maintenance, testing, commissioning and other work on transmission lines, transformers, reactors, and busbars at different voltage levels between May 3rd and May 18th 2018. The total outage times range from 6 to 274 hours.
The document is a report requesting approval for planned power outages from the OCC meeting. It includes 12 outage requests from various owners including Power Grid Corporation of India Limited, Uttar Pradesh Power Transmission Corporation Limited, NTPC Limited, and Rajasthan Rajya Vidyut Prasaran Nigam Limited. The requests are for maintenance, testing, commissioning and other work on transmission lines, transformers, reactors, and busbars at different voltage levels between May 3rd and May 18th 2018. The total outage times range from 6 to 274 hours.
The document is a report requesting approval for planned power outages from the OCC meeting. It includes 12 outage requests from various owners including Power Grid Corporation of India Limited, Uttar Pradesh Power Transmission Corporation Limited, NTPC Limited, and Rajasthan Rajya Vidyut Prasaran Nigam Limited. The requests are for maintenance, testing, commissioning and other work on transmission lines, transformers, reactors, and busbars at different voltage levels between May 3rd and May 18th 2018. The total outage times range from 6 to 274 hours.
Sr.No Request by Owner Element Name Mode Reason Outage Request Status Type Hours By OCC From From To To Date Time Date Time POWER GRID POWER GRID CORPORATION CORPORATION KURUKSHETRA-CHAMPA POLE- For OCT & OLT of Pole-3 at Kurukshetra end, 2018- 2018- 1 HVDC DAILY 09:00 17:30 32 -- PENDING OF INDIA OF INDIA 1(PGNRDCL800004)/800 shutdown of both Poles are required for two days. 05-07 05-08 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION KUREKSHETRA -CHAMPA POLE - For OCT & OLT of Pole-3 at Kurukshetra end, 2018- 2018- 2 HVDC DAILY 09:00 17:30 32 -- PENDING OF INDIA OF INDIA II(PGLIHVL800001)/800 shutdown of both Poles are required for two days. 05-07 05-08 LIMITED LIMITED POWER GRID POWER GRID For OCT & OLT of Pole-3 at Champa end, shutdown CORPORATION CORPORATION KURUKSHETRA-CHAMPA POLE- 2018- 2018- 3 HVDC DAILY of both Poles are required on continuous two 09:00 17:30 32 -- PENDING OF INDIA OF INDIA 1(PGNRDCL800004)/800 05-09 05-10 days. LIMITED LIMITED POWER GRID POWER GRID For OCT & OLT of Pole-3 at Champa end, shutdown CORPORATION CORPORATION KUREKSHETRA -CHAMPA POLE - 2018- 2018- 4 HVDC DAILY of both Poles are required on continuous two 09:00 17:30 32 -- PENDING OF INDIA OF INDIA II(PGLIHVL800001)/800 05-09 05-10 days. LIMITED LIMITED Uttar Pradesh Power On daily basis for testing of auto reclosing relay & SLDC Uttar ANPARA-C (765KV)(LAPLUP)- 2018- 2018- 5 Transmission LINE DAILY timing test of existing breakers related to line at 08:00 18:00 34 -- PENDING Pradesh UNNAO (765KV)(UPPTCL) 05-03 05-04 Corporation Unnao end Limited POWER GRID POWER GRID VARANASI (765KV) CORPORATION CORPORATION FOR ATTENDING THE STRENGTHENING WORK OF 2018- 2018- 6 LINE (POWERGRID)-FATEHPUR-PG DAILY 08:00 18:00 274 -- PENDING OF INDIA OF INDIA SUSPENSION TOWERS , at Allahabad 05-04 05-15 (765 KV)(POWERGRID) LIMITED LIMITED Uttar Pradesh Power On daily basis for remaining work & commissioning SLDC Uttar ICT03 UNNAO (765KV)(UPPTCL) 2018- 2018- 7 Transmission ICT DAILY of CSD Relay on both sides (H.V. & L.V.) in panel of 08:00 18:00 34 -- PENDING Pradesh (ICT7650020)/1000 05-07 05-08 Corporation 1000 MVA ICT-III (along with 765 KV Bus-I). Limited Uttar Pradesh Power SLDC Uttar For remaining work in Bay No.-7 & Bay No.-11 2018- 2018- 8 Transmission BUS Bus-I(Unnao)(ABS765005) DAILY 08:00 18:00 10 -- PENDING Pradesh (extension work 1000 MVA ICT-III & Mainpuri Line) 05-07 05-07 Corporation Limited Uttar Pradesh Power REACTOR SLDC Uttar For CSD commissioning covering of PRDs and 2018- 2018- 9 Transmission REACTOR FATEHBAD_AGRA(765KV) DAILY 08:00 18:00 82 -- PENDING Pradesh spare bus reactor commissioning. No supply loss 05-15 05-18 Corporation (PGBR765002)/330.00 Limited RAJASTHAN SLDC RAJYA VIDYUT MORAK (220KV)(RRVPN)-BAROD 2018- 2018- 10 LINE DAILY PREVENTIVE MAINTENANCE WORK at Kota end 09:30 16:00 6 -- PENDING Rajasthan PRASARAN (220KV)(RRVPN) 05-10 05-10 NIGAM LIMITED RIHAND NTPC (400KV)(NTPC)- Erection & Commissioning of 3 no. 400 KV CTs in 2018- 2018- 11 NTPC Limited NTPC Limited LINE ALLAHABAD (400KV) CONTINUOUS 08:30 18:30 34 -- PENDING Bay no. 19 for new IBT-3 05-01 05-02 (POWERGRID) I 400kv Singrauli Allahabad Line-1 Shutdown from 09/05/2018 to 10/05/2018 on continuous Basis SINGRAULI NTPC (400KV)(NTPC)- along with 400KV generator # 2 to be shifted to 2018- 2018- 12 NTPC Limited NTPC Limited LINE ALLAHABAD (400KV) CONTINUOUS Transfer Bus-1. This is required in view of old CVT 08:30 18:00 33 -- PENDING 05-09 05-10 (POWERGRID) I (more than 20Years) replacement practice of NTPC Ltd. Both bay & Bay#2 shutdown is required as BUS CVT placed in between both these bay 2. POWER GRID POWER GRID FATEHPUR-PG (765 KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 13 LINE (POWERGRID)-SASARAM-ER DAILY Missing Jumper Bolts, Spacer Damper,cottor Pin 08:00 18:00 274 -- PENDING OF INDIA OF INDIA 05-18 05-29 (765KV)(POWERGRID) etc) LIMITED LIMITED POWER GRID POWER GRID ICT01 MOGA( 765KV) CORPORATION CORPORATION 2018- 2018- 14 ICT (POWERGRID) DAILY For AMP Works. 09:00 17:00 8 -- PENDING OF INDIA OF INDIA 05-01 05-01 (PGICT7650021)/1500 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR I(S) MOGA( 765KV) 2018- 2018- 15 REACTOR DAILY For AMP Works. 09:00 17:00 8 -- PENDING OF INDIA OF INDIA (PGBR7650025)/240.00 05-03 05-03 LIMITED LIMITED POWER GRID POWER GRID ICT 02 MOGA( 765KV) CORPORATION CORPORATION 2018- 2018- 16 ICT (POWERGRID) DAILY For AMP Works. 09:00 17:00 8 -- PENDING OF INDIA OF INDIA 04-02 04-02 (PGICT7650026)/1500 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR II MOGA( 765KV) 2018- 2018- 17 REACTOR DAILY For AMP Works. 09:00 17:00 8 -- PENDING OF INDIA OF INDIA (PGBR7650026)/240.00 04-04 04-04 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION MEERUT (765KV)(POWERGRID)- 2018- 2018- 18 LINE DAILY Commissioning of Priority Auto-Reclose circuit. 10:00 17:00 7 -- PENDING OF INDIA OF INDIA MOGA( 765KV)(POWERGRID) 04-16 04-16 LIMITED LIMITED POWER GRID POWER GRID MOGA( 765KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 19 LINE BHIWANI-PG (765 KV) DAILY Commissioning of Priority Auto-Reclose circuit. 10:00 17:00 7 -- PENDING OF INDIA OF INDIA 04-14 04-14 (POWERGRID) LIMITED LIMITED RAJASTHAN SLDC RAJYA VIDYUT KOTA(220KV)(RRVPN)-BAROD 2018- 2018- 20 LINE DAILY QUARTERLY MAINTENANCE WORK 08:00 18:00 10 -- PENDING Rajasthan PRASARAN (220KV)(RRVPN) 05-17 05-17 NIGAM LIMITED RAJASTHAN PHAGI (765KV)(RRVPN)- SLDC RAJYA VIDYUT For the replacement of defective CVT (Y-Phase) 2018- 2018- 21 LINE GWALIOR-WR (765KV) DAILY 08:30 19:00 10 -- PENDING Rajasthan PRASARAN due to oil leakage. 05-09 05-09 (POWERGRID) 1 NIGAM LIMITED RAJASTHAN PHAGI (765KV)(RRVPN)- SLDC RAJYA VIDYUT For the replacement of B-Phase defective CVT as 2018- 2018- 22 LINE GWALIOR-WR (765KV) DAILY 09:00 19:00 10 -- PENDING Rajasthan PRASARAN the oil leakage has been observed. 05-16 05-16 (POWERGRID) 2 NIGAM LIMITED RAJASTHAN RANAPRATAP SAGAR- RPS SLDC RAJYA VIDYUT (132KV)(RRVUNL)-GANDHI For replacement of damaged earth wire having 2018- 2018- 23 LINE DAILY 08:00 18:00 106 -- PENDING Rajasthan PRASARAN SAGAR MPSEB-WR (132KV) total 14.00Kms in the line 05-07 05-11 NIGAM LIMITED (POWERGRID) 1 +MP RAJASTHAN RANAPRATAP SAGAR- RPS SLDC RAJYA VIDYUT (132KV)(RRVUNL)-GANDHI For replacement of damaged earth wire having 2018- 2018- 24 LINE DAILY 08:00 18:00 106 -- PENDING Rajasthan PRASARAN SAGAR MPSEB-WR (132KV) total 14.00Kms in the line 05-07 05-11 NIGAM LIMITED (POWERGRID) 2 +MP Uttar Pradesh Power SLDC Uttar GREATER NOIDA(765 KV) 2018- 2018- 25 Transmission LINE DAILY Tower Strengthening, Tree cutting 05:00 11:00 126 -- PENDING Pradesh (UPPTCL)-HAPUR(UPPTCL) 05-14 05-19 Corporation Limited Uttar Pradesh Power GREATER NOIDA(765 KV) SLDC Uttar 2018- 2018- 26 Transmission LINE (UPPTCL)-MAINPURI-UP (765KV) DAILY Tower Strengthening, Tree cutting 05:00 11:00 126 -- PENDING Pradesh 05-07 05-12 Corporation (UPPTCL) Limited RAJASTHAN SLDC RAJYA VIDYUT ICT01 ANTA(765KV)(RRVPN) 2018- 2018- 27 ICT DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (ICT765004)/1500 05-09 05-09 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT ICT02 ANTA(765KV)(RRVPN) 2018- 2018- 28 ICT DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (ICT765005)/1500 05-10 05-10 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT ICT03 ANTA(765KV)(RRVPN) 2018- 2018- 29 ICT DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (ICT765006)/1500 05-15 05-15 NIGAM LIMITED Uttar Pradesh Power SLDC Uttar 765 kV bus reactor Hapur 2018- 2018- 30 Transmission REACTOR DAILY Aircell commissioning 08:00 19:00 11 -- PENDING Pradesh (UPPTCL)(BR7650013)/80.00 05-07 05-07 Corporation Limited 2018- 2018- 31 NTPC Limited NTPC Limited BUS BUS-3(ABS220007) CONTINUOUS ISOLATORS SERVICING & TIGHNESS CHECKING. 08:30 18:30 34 -- PENDING 05-01 05-02 2018- 2018- 32 NTPC Limited NTPC Limited BUS BUS-4(ABS220008) CONTINUOUS ISOLATORS SERVICING & TIGHNESS CHECKING. 08:30 18:00 33 -- PENDING 05-03 05-04 RAJASTHAN SLDC RAJYA VIDYUT Reactor Bank 1 ANTA(765KV) 2018- 2018- 33 REACTOR DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (LR765007)/240.00 05-23 05-23 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT Reactor Bank 2 ANTA(765KV) 2018- 2018- 34 REACTOR DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (LR765008)/240.00 05-24 05-24 NIGAM LIMITED KANPUR (400KV)(POWERGRID)- 2018- 2018- 35 NTPC Limited NTPC Limited LINE CONTINUOUS BAY EQUIPMENT MAINTENANCE & TESTING. 08:30 18:00 57 -- PENDING AURAIYA GPS (400KV)(NTPC) I 05-01 05-03 KANPUR (400KV)(POWERGRID)- 2018- 2018- 36 NTPC Limited NTPC Limited LINE CONTINUOUS BAY EQUIPMENT MAINTENANCE & TESTING. 08:30 18:00 57 -- PENDING AURAIYA GPS (400KV)(NTPC) II 05-07 05-09 KOTESHWAR- KOTESHWAR- Koteshwar(GENCO00100)- 2018- 2018- 37 GENCO CONTINUOUS Annual Maintenance Of Unit # 4 10:00 18:30 704 -- PENDING THDC THDC U4/100 05-01 05-30 TANDA (220KV)(NTPC)-BASTI 2018- 2018- 38 NTPC Limited NTPC Limited LINE DAILY RELAY TESTING. 08:30 18:30 34 -- PENDING (220KV)(UPPTCL) 05-14 05-15 Uttar Pradesh Power SLDC Uttar ICT01 FATEHBAD_AGRA(765KV) For commissioning of RTCC for tap change control 2018- 2018- 39 Transmission ICT CONTINUOUS 08:00 18:00 82 -- PENDING Pradesh (UPPTCL)(ICT765007)/1500 and covering of PRDs. No supply loss 05-07 05-10 Corporation Limited Uttar Pradesh Power SLDC Uttar ICT02 FATEHBAD_AGRA(765KV) For commissioning of RTCC for tap change control 2018- 2018- 40 Transmission ICT CONTINUOUS 08:00 18:00 82 -- PENDING Pradesh (UPPTCL)(ICT765008)/1500 and covering of PRDs. No supply loss 05-11 05-14 Corporation Limited RAJASTHAN 705-52 T , Tie CB of ICT-II & SLDC RAJYA VIDYUT 2018- 2018- 41 BAY 765KV PHAGI-2 LINE AT 765KV DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN 05-17 05-17 GSS ANTA(BAY1090) NIGAM LIMITED RAJASTHAN 702-52T tie CB for ICT-2 & 1. Measurement of Tan-delta & IR of CTs. SLDC RAJYA VIDYUT 2018- 2018- 42 BAY PHAGI-BHIWANI-1 LINE AT 765KV DAILY 2.Mainenance of CB & CTs. 3. Tightening of clamps 09:30 19:00 33 -- PENDING Rajasthan PRASARAN 05-03 05-04 PHAGI(BAY1089) & connectors. NIGAM LIMITED RAJASTHAN 706-52T tie CB for 765kV ANTA- 1. Measurement of Tan-delta & IR of CTs. SLDC RAJYA VIDYUT 2018- 2018- 43 BAY 1 & GWALIOR-1 LINES AT 765KV DAILY 2.Mainenance of CB & CTs. 3. Tightening of clamps 09:00 19:00 34 -- PENDING Rajasthan PRASARAN 05-21 05-22 PHAGI(BAY1088) & connectors. NIGAM LIMITED RAJASTHAN 701-52A CB for 765kV PHAGI- 1. Measurement of Tan-delta & IR of CTs. SLDC RAJYA VIDYUT 2018- 2018- 44 BAY BHIWANI-2 LINE 765KV DAILY 2.Mainenance of CB & CTs. 3. Tightening of clamps 09:00 19:00 34 -- PENDING Rajasthan PRASARAN 05-24 05-25 PHAGI(BAY1091) & connectors. NIGAM LIMITED RAJASTHAN 705-52A CB for 3*80MVAR BUS 1. Measurement of Tan-delta & IR of CTs. SLDC RAJYA VIDYUT 2018- 2018- 45 BAY REACTOR AT 765KV GSS DAILY 2.Mainenance of CB & CTs. 3. Tightening of clamps 09:30 19:00 33 -- PENDING Rajasthan PRASARAN 05-29 05-30 PHAGI(BAY1092) & connectors. NIGAM LIMITED Uttar Pradesh LUCKNOW-Kursi Road (400KV) Power SLDC Uttar PG(POWERGRID)-LUCKNOW 2018- 2018- 46 Transmission LINE DAILY Checking & Tightening of Jumpers and Clamps 09:00 17:00 8 -- PENDING Pradesh (Sarojini Nagar) 400- 05-12 05-12 Corporation UP(UPPTCL) Limited Uttar Pradesh Power LUCKNOW (Sarojini Nagar) 400- SLDC Uttar 2018- 2018- 47 Transmission LINE UP(UPPTCL)-UNNAO (400KV) DAILY Checking & Tightening of Jumpers and Clamps 09:00 17:00 8 -- PENDING Pradesh 05-13 05-13 Corporation (UPPTCL) Limited Power BAREILY-PG (400KV) Transmission SLDC Uttar (POWERGRID)-LUCKNOW 2018- 2018- 48 Corporation of LINE DAILY FOR YEARLY ROUTINE TESTING (MOST URGENT). 09:00 16:00 7 -- PENDING Pradesh (Sarojini Nagar) 400- 05-11 05-11 Uttarkhand UP(UPPTCL) Limited POWER GRID POWER GRID AGRA-PG (765KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 49 LINE FATEHPUR-PG (765 KV) DAILY To attend the shut down nature defects 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-01 05-02 (POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID AGRA-PG (765KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 50 LINE FATEHPUR-PG (765 KV) DAILY To attend the shut down nature defects 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-03 05-05 (POWERGRID) II LIMITED LIMITED POWER GRID POWER GRID AGRA-PG (765KV)(POWERGRID)- To attend the shut down nature defects and CORPORATION CORPORATION 2018- 2018- 51 LINE GWALIOR-WR (765KV) DAILY insulator replacement on balance towers with 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-07 05-09 (POWERGRID) I polymer LIMITED LIMITED POWER GRID POWER GRID AGRA-PG (765KV)(POWERGRID)- To attend the shut down nature defects and CORPORATION CORPORATION 2018- 2018- 52 LINE GWALIOR-WR (765KV) DAILY insulator replacement on balance towers with 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-10 05-12 (POWERGRID) II polymer LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION AGRA-PG (765KV)(POWERGRID)- 2018- 2018- 53 LINE DAILY To attend the shut down nature defects 08:00 18:00 58 -- PENDING OF INDIA OF INDIA JHATIKALA(765 KV)(POWERGRID) 05-21 05-23 LIMITED LIMITED POWER GRID POWER GRID FOR ATTENDING THE STRENGTHENING WORK OF AGRA-PG (765KV)(POWERGRID)- CORPORATION CORPORATION SUSPENSION TOWERS. To attend the shut down 2018- 2018- 54 LINE ALIGARH-PG (765KV) DAILY 08:00 18:00 130 -- PENDING OF INDIA OF INDIA nature defects (Fixing of Missing Jumper Bolts, 05-08 05-13 (POWERGRID) S/C LIMITED LIMITED Spacer Damper,cottor Pin etc) POWER GRID POWER GRID FOR ATTENDING THE STRENGTHENING WORK OF ALIGARH-PG (765KV) CORPORATION CORPORATION SUSPENSION TOWERS. To attend the shut down 2018- 2018- 55 LINE (POWERGRID)-GREATER DAILY 08:00 18:00 58 -- PENDING OF INDIA OF INDIA nature defects (Fixing of Missing Jumper Bolts, 05-03 05-05 NOIDA(765 KV)(UPPTCL) S/C LIMITED LIMITED Spacer Damper,cottor Pin etc) POWER GRID POWER GRID To attend the shut down nature defects (Fixing of CORPORATION CORPORATION GAYA-ER (765KV)(POWERGRID)- 2018- 2018- 56 LINE DAILY Missing Jumper Bolts, Spacer Damper,cottor Pin 08:00 18:00 10 -- PENDING OF INDIA OF INDIA BALIA (765KV)(POWERGRID) 05-06 05-06 etc) LIMITED LIMITED POWER GRID POWER GRID FOR ATTENDING THE STRENGTHENING WORK OF GAYA-ER (765KV)(POWERGRID)- CORPORATION CORPORATION SUSPENSION TOWERS. To attend the shut down 2018- 2018- 57 LINE VARANASI (765KV)(POWERGRID) DAILY 08:00 18:00 130 -- PENDING OF INDIA OF INDIA nature defects (Fixing of Missing Jumper Bolts, 05-01 05-06 1 LIMITED LIMITED Spacer Damper,cottor Pin etc) POWER GRID POWER GRID VARANASI (765KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 58 LINE (POWERGRID)-BALIA (765KV) DAILY Missing Jumper Bolts, Spacer Damper,cottor Pin 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-07 05-08 (POWERGRID) etc) LIMITED LIMITED To attend the shut down nature defects (Fixing of POWER GRID POWER GRID LUCKNOW(765 KV)- Missing Jumper Bolts, Spacer Damper,cottor CORPORATION CORPORATION 2018- 2018- 59 LINE PG(POWERGRID)-BAREILY-PG DAILY Pin,Broken Insulator Replacement etc) and 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-08 05-10 (765 KV)(POWERGRID) switching of Spare phase as B-Phase to attend the LIMITED LIMITED Leakage from MOG in Line Reactor at Bareilly also. POWER GRID POWER GRID LUCKNOW(765 KV)- To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 60 LINE PG(POWERGRID)-BALIA (765KV) DAILY Missing Jumper Bolts, Spacer Damper,cottor 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-24 05-26 (POWERGRID) Pin,Broken Insulator Replacement etc) LIMITED LIMITED POWER GRID POWER GRID VARANASI (765KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 61 LINE (POWERGRID)-KANPUR GIS DAILY Missing Jumper Bolts, Spacer Damper,cottor 08:00 18:00 106 -- PENDING OF INDIA OF INDIA 05-20 05-24 (765KV)(POWERGRID) I Pin,Broken Insulator Replacement etc) LIMITED LIMITED POWER GRID POWER GRID KANPUR GIS (765KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 62 LINE (POWERGRID)-ALIGARH-PG DAILY Missing Jumper Bolts, Spacer Damper,cottor 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-11 05-12 (765KV)(POWERGRID) S/C Pin,Broken Insulator Replacement etc) LIMITED LIMITED POWER GRID POWER GRID ICT02 LUCKNOW(765 KV)- CORPORATION CORPORATION 2018- 2018- 63 ICT PG(POWERGRID) DAILY For AMP Work 09:00 18:00 9 -- PENDING OF INDIA OF INDIA 05-15 05-15 (PGICT7650012)/1500 LIMITED LIMITED POWER GRID POWER GRID ICT01 LUCKNOW(765 KV)- CORPORATION CORPORATION 2018- 2018- 64 ICT PG(POWERGRID) DAILY For AMP Work 09:00 18:00 9 -- PENDING OF INDIA OF INDIA 05-14 05-14 (PGICT7650011)/1500 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR BAREILY-PG (765 KV) 2018- 2018- 65 REACTOR DAILY AMP of 240MVAR Bus Reactor 09:30 18:30 9 -- PENDING OF INDIA OF INDIA (PGBR765006)/240.00 05-08 05-08 LIMITED LIMITED POWER GRID POWER GRID Switching of Spare phase as B ph to attend the CORPORATION CORPORATION REACTOR BAREILY-PG (765 KV) 2018- 2018- 66 REACTOR DAILY leakage from MOG (During the switching the S/D of 10:00 11:00 1 -- PENDING OF INDIA OF INDIA (PGLR765001)/240.00 05-10 05-10 765KV S/C Bareilly Lucknow line is required) LIMITED LIMITED POWER GRID POWER GRID 702 Bay ( Tie bay of 765 KV CORPORATION CORPORATION 2018- 2018- 67 BAY Fatehpur Varanasi Line), at DAILY AMP and Tightening work 09:30 18:00 8 -- PENDING OF INDIA OF INDIA 05-09 05-09 Fatehpur(702 BAY) LIMITED LIMITED POWER GRID POWER GRID 704 Bay ( Tie bay of 765 KV CORPORATION CORPORATION 2018- 2018- 68 BAY Fatehpur Sasaram Line), at DAILY AMP and Tightening work 09:30 18:00 8 -- PENDING OF INDIA OF INDIA 05-11 05-11 Fatehpur(704 BAY) LIMITED LIMITED POWER GRID POWER GRID 710 Bay ( Main bay of 765 KV CORPORATION CORPORATION 2018- 2018- 69 BAY Fatehpur Agra-2 Line), at DAILY AMP and Tightening work 09:30 18:00 8 -- PENDING OF INDIA OF INDIA 05-15 05-15 Fatehpur(710 BAY) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 704 Main Bay (VNS-II Main Bay), 2018- 2018- 70 BAY DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA at Kanpur (GIS)(704 MAIN BAY) 05-08 05-08 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 705 Tie Bay (VNS-II- ICT-II Tie) , 2018- 2018- 71 BAY DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA at Kanpur (GIS)(705 TIE BAY) 05-09 05-09 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 706 Main Bay (ICT-II Main bay) , 2018- 2018- 72 BAY DAILY AMP work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA at Kanpur (GIS)(706 MAIN BAY) 05-15 05-15 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 707 Main Bay (ICT-I Main bay) , 2018- 2018- 73 BAY DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA at Kanpur (GIS)(707 MAIN BAY) 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 703 Bay, (ICT-1 Main Bay), at 2018- 2018- 74 BAY DAILY AMP Work 09:00 18:00 33 -- PENDING OF INDIA OF INDIA Lucknow(703 BAY) 05-16 05-17 LIMITED LIMITED POWER GRID POWER GRID JALLANDHAR-PG (400KV) CORPORATION CORPORATION For rectification of B-Phase CB HMV Drive at GIS 2018- 2018- 75 LINE (POWERGRID)-CHAMBA POOL CONTINUOUS 09:00 18:00 57 -- PENDING OF INDIA OF INDIA Chamba. 05-03 05-05 (400KV)(POWERGRID) 1 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS- I at For Extension of GIS Bus-Bar for ICT-III under 2018- 2018- 76 BUS CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA Hamirpur(PGABS400008) construction. (Rescheduled from 144 OCC.) 05-02 05-07 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS- II at For Extension of GIS Bus-Bar for ICT-III under 2018- 2018- 77 BUS CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA Hamirpur(PGABS400009) construction. (Rescheduled from 144 OCC.) 05-08 05-13 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 220KV BUS- I at For Extension of GIS Bus-Bar for ICT-III under 2018- 2018- 78 BUS CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA Hamirpur(PGABS220004) construction. (Rescheduled from 144 OCC.) 05-14 05-19 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 220KV BUS- II at For Extension of GIS Bus-Bar for ICT-III under 2018- 2018- 79 BUS CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA Hamirpur(PGABS220005) construction. (Rescheduled from 144 OCC.) 05-20 05-25 LIMITED LIMITED For Extension of GIS Bus-Bar for ICT-III under POWER GRID POWER GRID construction. ICT-II shutdown is required as it is ICT02 HAMIRPUR-PG (400KV) CORPORATION CORPORATION adjacent to the upcoming Bus section & gas 2018- 2018- 80 ICT (POWERGRID) CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA pressure is to be reduced to 03. Bar. So it could 05-02 05-07 (PGICT40000135)/315 LIMITED LIMITED not be charged till Bus-I is out. (Rescheduled from 144 OCC.) For Extension of GIS Bus-Bar for ICT-III under POWER GRID POWER GRID construction. ICT-II shutdown is required as it is ICT02 HAMIRPUR-PG (400KV) CORPORATION CORPORATION adjacent to the upcoming Bus section & gas 2018- 2018- 81 ICT (POWERGRID) CONTINUOUS 09:00 17:00 128 -- PENDING OF INDIA OF INDIA pressure is to be reduced to 03. Bar. So it could 05-08 05-13 (PGICT40000135)/315 LIMITED LIMITED not be charged till Bus-II is out. (Rescheduled from 144 OCC.) POWER GRID POWER GRID AMRITSAR (400KV) CORPORATION CORPORATION Auto-Reclosure Non Auto mode for OPGW work. 2018- 2018- 82 LINE (POWERGRID)-ParbatiPooling- DAILY 09:00 17:00 728 -- PENDING OF INDIA OF INDIA (Non- Shutdown activity). 05-01 05-31 BANALA (400KV)(POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID HAMIRPUR-PG (400KV) CORPORATION CORPORATION Auto-Reclosure Non Auto mode for OPGW work. 2018- 2018- 83 LINE (POWERGRID)-ParbatiPooling- DAILY 09:00 17:00 728 -- PENDING OF INDIA OF INDIA (Non- Shutdown activity). 05-01 05-31 BANALA (400KV)(POWERGRID) LIMITED LIMITED POWER GRID POWER GRID ICT01 KAITHAL (400KV) CORPORATION CORPORATION Replacement of 220 KV Side R & Y Phase LA's due 2018- 2018- 84 ICT (POWERGRID) DAILY 09:00 16:00 7 -- PENDING OF INDIA OF INDIA to THRC violation. 05-02 05-02 (PGICT4000090)/315 LIMITED LIMITED POWER GRID POWER GRID ICT02 KAITHAL (400KV) CORPORATION CORPORATION 2018- 2018- 85 ICT (POWERGRID) DAILY For AMP Works. 09:00 17:00 8 -- PENDING OF INDIA OF INDIA 04-16 04-16 (PGICT4000091)/315 LIMITED LIMITED POWER GRID POWER GRID KAITHAL (400KV)(POWERGRID)- CORPORATION CORPORATION Replacement of Y Phase LA of Line due to THRC 2018- 2018- 86 LINE BAGHPAT (400KV)(POWERGRID) DAILY 10:00 14:00 4 -- PENDING OF INDIA OF INDIA violation. 04-03 04-03 II LIMITED LIMITED POWER GRID POWER GRID ICT01 LUDHIANA (400KV) CORPORATION CORPORATION Replacement of 220KV Y-Phase Bushing of ICT-1 2018- 2018- 87 ICT (POWERGRID) CONTINUOUS 09:00 18:00 129 -- PENDING OF INDIA OF INDIA due to Tan Delta Violation. 05-02 05-07 (PGICT40000109)/315 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV Bus-I at For Replacement of T Connectors related to Bus 2018- 2018- 88 BUS DAILY 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Patiala(PGABS4000060) Reactor. 05-15 05-15 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400kV Bus-II at 2018- 2018- 89 BUS DAILY For AMP Works/to Attend Hotspots. 09:30 17:00 7 -- PENDING OF INDIA OF INDIA Wagoora(PGABS400007) 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID For diversion of Existing T. No. 66 to new pile CORPORATION CORPORATION HIRANAGAR(220KV)(JKPDD)- foundation tower because existing foundation got 2018- 2018- 90 LINE CONTINUOUS 09:00 17:30 200 -- PENDING OF INDIA OF INDIA SARNA (220KV)(PSTCL) damaged due to change in path of river flow. 05-02 05-10 LIMITED LIMITED (Rescheduled from 144 OCC.) Uttar Pradesh "1.Stringing of balance earth wire/tree cutting Power SLDC Uttar UNNAO (400KV)(UPPTCL)- 2.General maintenance of feeder, FSC-I and 2018- 2018- 91 Transmission LINE DAILY 09:00 18:00 81 -- PENDING Pradesh BAREILY-UP (400KV)(UPPTCL) I maintence of 50 MVAR Line Reactor at 400 KV S/S 05-23 05-26 Corporation Unnao at first circuit." Limited Uttar Pradesh Power SLDC Uttar OBRA (400KV)(UPPTCL)- Replacement of disc insulator by Polymer insulator 2018- 2018- 92 Transmission LINE DAILY 08:00 18:00 34 -- PENDING Pradesh SULTANPUR (400KV)(UPPTCL) and other maintenance work. 05-16 05-17 Corporation Limited Uttar Pradesh Power SLDC Uttar SULTANPUR (400KV)(UPPTCL)- 2018- 2018- 93 Transmission LINE DAILY Maintenance works & tree cutting. 08:00 18:00 10 -- PENDING Pradesh AZAMGARH (400KV)(UPPTCL) 05-18 05-18 Corporation Limited Uttar Pradesh Power SLDC Uttar MAU (400KV)(UPPTCL)- Servicing & overhauling of pantograph isolator, 2018- 2018- 94 Transmission LINE DAILY 08:00 18:00 10 -- PENDING Pradesh AZAMGARH (400KV)(UPPTCL) replacement of contact blades at Mau end. 05-11 05-11 Corporation Limited Uttar Pradesh Power SLDC Uttar AZAMGARH (400KV)(UPPTCL)- For Erection of new line Reactor at 400 KV 2018- 2018- 95 Transmission LINE DAILY 08:00 18:00 106 -- PENDING Pradesh SARNATH (400KV)(UPPTCL) Azamgarh end 05-20 05-24 Corporation Limited Uttar Pradesh Connecting the 33 KV Tertiary bushing terminals by Power 4" IPS AI Pipe along with 33 KV Surge Capacitor , SLDC Uttar ICT02 UNNAO (400KV)(UPPTCL) 2018- 2018- 96 Transmission ICT DAILY 33 KV CT Lightening Arrestor and 33 KV CT to 08:00 18:00 10 -- PENDING Pradesh (ICT40000193)/315 05-02 05-02 Corporation charge the 31.5 MVAR Tertiary reactor of Limited 400/220/33 KV 315 MVA ICT-III at 400 KV S/S Unnao Uttar Pradesh Major Overhauling of Main Circuit Breaker of 400 KV Power SLDC Uttar AGRA-UP (400KV)(UPPTCL)- Agra Feeder at 400 KV S/S Unnao bay Main Circuit 2018- 2018- 97 Transmission LINE CONTINUOUS 08:00 18:00 154 -- PENDING Pradesh UNNAO (400KV)(UPPTCL) Breaker (during shutdown the line will remain 05-07 05-13 Corporation charged through 400 KV TBC ) Unnao Limited DELHI ICT01 BAMNAULI(DTL) TO CHECK THE BUCHHOLZ RELAY AND ITS 2018- 2018- 98 SLDC Delhi TRANSCO ICT DAILY 07:00 12:00 5 -- PENDING (ICT4000028)/315 ASSOCIATED CKTS. 05-02 05-02 LIMITED Uttar Pradesh Power ICT02 LUCKNOW (Sarojini Nagar) SLDC Uttar FOR ROUTINE TESTING AND BAY MAINTAINANCE 2018- 2018- 99 Transmission ICT 400-UP(UPPTCL) DAILY 09:00 16:00 7 -- PENDING Pradesh WORK. 05-07 05-07 Corporation (ICT40000170)/315 Limited DELHI DADRI-THERMAL (400KV)(NTPC)- 2018- 2018- 100 SLDC Delhi TRANSCO LINE LONI-HARSHVIHAR (400KV)(DTL) DAILY TAN DELTA TESTING. 08:00 11:00 3 -- PENDING 05-03 05-03 LIMITED 1 DELHI DADRI-THERMAL (400KV)(NTPC)- 2018- 2018- 101 SLDC Delhi TRANSCO LINE LONI-HARSHVIHAR (400KV)(DTL) DAILY TAN DELTA TESTING. 13:30 16:00 2 -- PENDING 05-03 05-03 LIMITED 2 Uttar Pradesh Power SLDC Uttar PANKI (400KV)(UPPTCL)-ALIGARH For tightening of jumper & other maintenance 2018- 2018- 102 Transmission LINE DAILY 08:00 18:00 106 -- PENDING Pradesh (400KV)(UPPTCL) work. No supply loss 05-11 05-15 Corporation Limited Uttar Pradesh Power SLDC Uttar ALIGARH (400KV)(UPPTCL)- To replace Disc Insulator by polymer string of 2018- 2018- 103 Transmission LINE DAILY 08:00 16:00 104 -- PENDING Pradesh MURADNAGAR (400KV)(UPPTCL) Tension tower. 05-07 05-11 Corporation Limited Uttar Pradesh Power GREATER NOIDA (400KV) SLDC Uttar 2018- 2018- 104 Transmission LINE (UPPTCL)-SIKANDRABAD (400KV) DAILY Tower Strengthening, Tree cutting 05:00 11:00 30 -- PENDING Pradesh 05-28 05-29 Corporation (UPPTCL) 1 Limited Uttar Pradesh Power GREATER NOIDA (400KV) SLDC Uttar 2018- 2018- 105 Transmission LINE (UPPTCL)-SIKANDRABAD (400KV) DAILY Tower Strengthening, Tree cutting 05:00 11:00 126 -- PENDING Pradesh 05-07 05-12 Corporation (UPPTCL) 2 Limited Haryana SLDC Vidyut ICT02 DAULTABAD (400KV) 2018- 2018- 106 ICT DAILY For Annual mtc. 08:30 16:00 7 -- PENDING Haryana Prasaran (HVPNL)(ICT400005)/315 05-02 05-02 Nigam LTD Uttar Pradesh Power SLDC Uttar ICT01 SIKANDRABAD (400KV) 2018- 2018- 107 Transmission ICT DAILY Annual Maintenance 09:00 18:00 9 -- PENDING Pradesh (UPPTCL)(ICT40000188)/500 05-03 05-03 Corporation Limited Haryana SLDC Vidyut ICT03 KIRORI (400KV)(HVPNL) 2018- 2018- 108 ICT DAILY For annual mtc. 10:00 16:00 6 -- PENDING Haryana Prasaran (ICT400003)/315 05-07 05-07 Nigam LTD Haryana FATEHABAD PG (400KV) SLDC Vidyut For M&P testing of CVT of B ph installed on line bay 2018- 2018- 109 LINE (POWERGRID)-KHEDAR (400KV) DAILY 11:00 14:00 3 -- PENDING Haryana Prasaran at F/Bad Mathana. 05-09 05-09 (HPGCL) Nigam LTD Haryana FATEHABAD PG (400KV) SLDC Vidyut 2018- 2018- 110 LINE (POWERGRID)-NUHIANWALI DAILY Gen mtc and tree trimming. 09:00 17:00 8 -- PENDING Haryana Prasaran 05-11 05-11 (400KV)(HVPNL) Nigam LTD Haryana SLDC Vidyut KHEDAR (400KV)(HPGCL)- 2018- 2018- 111 LINE DAILY Gen mtc and tree trimming 09:00 17:00 8 -- PENDING Haryana Prasaran NUHIANWALI (400KV)(HVPNL) 1 05-15 05-15 Nigam LTD Uttar Pradesh Power SLDC Uttar ICT02 SIKANDRABAD (400KV) 2018- 2018- 112 Transmission ICT DAILY Annual Maintenance 09:00 18:00 9 -- PENDING Pradesh (UPPTCL)(ICT40000189)/500 05-08 05-08 Corporation Limited Uttar Pradesh Power SLDC Uttar REACTOR SIKANDRABAD (400KV) 2018- 2018- 113 Transmission REACTOR DAILY Annual Maintenance 09:00 18:00 9 -- PENDING Pradesh (BR4000039)/125.00 05-15 05-15 Corporation Limited POWER GRID POWER GRID VARANASI (765KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 114 LINE (POWERGRID)-KANPUR GIS DAILY Missing Jumper Bolts, Spacer Damper,cottor 08:00 18:00 106 -- PENDING OF INDIA OF INDIA 05-20 05-24 (765KV)(POWERGRID) II Pin,Broken Insulator Replacement etc) LIMITED LIMITED Haryana SLDC Vidyut Tie Bay 408 at Dhanonda for Gen mtc. of bay equipments & alignment of bus 2018- 2018- 115 BAY DAILY 09:00 15:00 6 -- PENDING Haryana Prasaran Dhanonda-CLP line(408) isolators. 05-02 05-02 Nigam LTD Uttar Pradesh Power SINGRAULI NTPC (400KV)(NTPC)- SLDC Uttar 2018- 2018- 116 Transmission LINE LUCKNOW (Sarojini Nagar) 400- DAILY FOR YEARLY ROUTINE TESTING 09:00 16:00 7 -- PENDING Pradesh 05-09 05-09 Corporation UP(UPPTCL) Limited Uttar Pradesh Power SLDC Uttar ICT01 BAREILY-UP (400KV) 2018- 2018- 117 Transmission ICT CONTINUOUS For Replacement of TarantulLa Jack Bus. 07:00 18:00 59 -- PENDING Pradesh (UPPTCL)(ICT40000162)/315 05-14 05-16 Corporation Limited Uttar Pradesh Power SLDC Uttar ICT02 BAREILY-UP (400KV) 2018- 2018- 118 Transmission ICT CONTINUOUS For Replacement of Tarantulla Jack Bus. 07:00 18:00 59 -- PENDING Pradesh (UPPTCL)(ICT40000163)/315 05-16 05-18 Corporation Limited Uttar Pradesh Power Servicing & overhauling of pantograph isolator, SLDC Uttar BALIA(400KV)(POWERGRID)-MAU 2018- 2018- 119 Transmission LINE CONTINUOUS replacement of contact blades and relay testing at 08:00 18:00 10 -- PENDING Pradesh (400KV)(UPPTCL) I 05-09 05-09 Corporation Mau. Limited Uttar Pradesh Power Servicing & overhauling of pantograph isolator, SLDC Uttar BALIA(400KV)(POWERGRID)-MAU 2018- 2018- 120 Transmission LINE CONTINUOUS replacement of contact blades and relay testing at 08:00 18:00 10 -- PENDING Pradesh (400KV)(UPPTCL) II 05-10 05-10 Corporation Mau. Limited ANTA GPS( GT)(GENCO001)- 2018- 2018- 121 NTPC Limited NTPC Limited GENCO CONTINUOUS Minor Inspection (8000 EOH) 00:00 23:59 143 -- PENDING U1/88.71 05-05 05-10 AURAIYA GPS (GT)(GENCO005)- 2018- 2018- 122 NTPC Limited NTPC Limited GENCO DAILY Boiler License renewal 00:00 23:59 23 -- PENDING U1/111.19 05-09 05-09 Faridabad GPS (GT) 2018- 2018- 123 NTPC Limited NTPC Limited GENCO CONTINUOUS Minor inspection 00:00 23:59 119 -- PENDING (GENCO0021)-U1/137.75 05-15 05-19 BHAKRA BEAS BHAKRA BEAS BHIWANI BBMB (220KV)(BBMB)- Erection on new towers for railway crossing in 2018- 2018- 124 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 201 -- PENDING HISSAR BBMB (220KV)(BBMB) 1 between span no.2-3 & half yearly maintenance 05-23 05-31 BOARD BOARD BHAKRA BEAS BHAKRA BEAS Erection of new towers for railway line (RVNL) BHIWANI BBMB (220KV)(BBMB)- 2018- 2018- 125 MANAGEMENT MANAGEMENT LINE DAILY crossing in between span no.2-3 & half yearly 08:00 17:00 201 -- PENDING HISSAR BBMB (220KV)(BBMB) 2 05-23 05-31 BOARD BOARD maintenance. BHAKRA BEAS BHAKRA BEAS PANIPAT BBMB (220KV)(BBMB)- Erection of new towers for railway line (RVNL) 2018- 2018- 126 MANAGEMENT MANAGEMENT LINE CONTINUOUS 08:00 17:00 249 -- PENDING CHARKHI DADRI (220KV)(BBMB) crossing in between span no. 327-328. 05-05 05-15 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BALLABGARH BBMB (220KV) 1 No. Isolator & 1 No. CT to be replaced at 2018- 2018- 127 MANAGEMENT MANAGEMENT LINE (BBMB)-SAMAYPUR (220KV) CONTINUOUS Samaypur substation . 1 No. CT to be replaced at 08:00 17:00 57 -- PENDING 05-02 05-04 BOARD BOARD (BBMB) 2 Ballabgarh substation. BHAKRA BEAS BHAKRA BEAS BALLABGARH BBMB (220KV) 2018- 2018- 128 MANAGEMENT MANAGEMENT LINE (BBMB)-BADARPUR (220KV) DAILY Half Yearly Maintenance 08:00 17:00 9 -- PENDING 05-21 05-21 BOARD BOARD (NTPC) 1 BHAKRA BEAS BHAKRA BEAS JAGADHRI (220KV)(BBMB)- For replacement of conventional disc insulator with 2018- 2018- 129 MANAGEMENT MANAGEMENT LINE KURUKSHETRA BBMB (220KV) DAILY 08:00 17:00 9 -- PENDING Antifog disc insulator 05-02 05-02 BOARD BOARD (BBMB) BHAKRA BEAS BHAKRA BEAS Due to 4 laning of NH-73, the height of conductor GANGUWAL (220KV)(BBMB)- 2018- 2018- 130 MANAGEMENT MANAGEMENT LINE CONTINUOUS is to be raised by erecting new tower by NHAI. 08:00 17:00 105 -- PENDING JAGADHRI (220KV)(BBMB) 05-25 05-29 BOARD BOARD (under self execution scheme) DELHI DEEPALPUR (400KV)(KT JHAJJAR)- REPLACE DAMAGED DROPPER JUMPER 'R' PHASE OF 2018- 2018- 131 SLDC Delhi TRANSCO LINE DAILY 06:00 10:00 4 -- PENDING BAWANA-DTL (400KV)(DTL) LINE ISOLATOR AND TAN DELTA TESTING. 05-02 05-02 LIMITED BHAKRA BEAS BHAKRA BEAS BHIWANI-PG (400KV) 2018- 2018- 132 MANAGEMENT MANAGEMENT LINE (POWERGRID)-BHIWANI BBMB DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING 05-17 05-17 BOARD BOARD (400KV)(BBMB) DELHI ALONGWITH 400KV DEEPALPUR CKT. FOR REPLACING 400KV BUS-1 AT BAWANA-DTL 2018- 2018- 133 SLDC Delhi TRANSCO BUS DAILY DAMAGED DROPPER JUMPER 'R' PHASE OF LINE 06:00 10:00 4 -- PENDING (400KV)(ABS4000018) 05-02 05-02 LIMITED ISOLATOR AND TAN DELTA TESTING. BHAKRA BEAS BHAKRA BEAS BHIWANI-PG (400KV) 2018- 2018- 134 MANAGEMENT MANAGEMENT LINE (POWERGRID)-HISSAR-PG DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING 05-15 05-15 BOARD BOARD (400KV)(POWERGRID) II Haryana SLDC Vidyut 400kv BUS-1 For Erection 400 kV Bays equipments at 400 kV 2018- 2018- 135 BUS DAILY 09:00 18:00 9 -- PENDING Haryana Prasaran Kirori(ABS4000097) Kirori for 400 kv Kirori-jind line. 05-01 05-01 Nigam LTD BHAKRA BEAS BHAKRA BEAS DADRI-THERMAL (400KV)(NTPC)- 2018- 2018- 136 MANAGEMENT MANAGEMENT LINE PANIPAT-PG (400KV) DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING 05-21 05-21 BOARD BOARD (POWERGRID) I Haryana SLDC Vidyut 400kv BUS-2 For Erection 400 kV Bays equipments at 400 kV 2018- 2018- 137 BUS DAILY 09:00 18:00 9 -- PENDING Haryana Prasaran KIRORI(ABS4000098) Kirori for 400 kv Kirori-jind line. 05-02 05-02 Nigam LTD DELHI MEHRAULI (220KV)(DTL)- 2018- 2018- 138 SLDC Delhi TRANSCO LINE DAILY TREE TRIMMING. 05:00 09:00 28 -- PENDING BADARPUR (220KV)(NTPC) 1 05-04 05-05 LIMITED DELHI MEHRAULI (220KV)(DTL)- 2018- 2018- 139 SLDC Delhi TRANSCO LINE DAILY TREE TRIMMING. 05:00 09:00 4 -- PENDING BADARPUR (220KV)(NTPC) 2 05-03 05-03 LIMITED DELHI MEHRAULI (220KV)(DTL)- 2018- 2018- 140 SLDC Delhi TRANSCO LINE DAILY TREE TRIMMING. 05:00 09:00 4 -- PENDING BADARPUR (220KV)(NTPC) 2 05-06 05-06 LIMITED BHAKRA BEAS BHAKRA BEAS HISSAR-PG (220KV) 2018- 2018- 141 MANAGEMENT MANAGEMENT LINE (POWERGRID)-HISSAR IA (220KV) DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING 05-10 05-10 BOARD BOARD (HVPNL) BHAKRA BEAS BHAKRA BEAS HISSAR-PG (220KV) 2018- 2018- 142 MANAGEMENT MANAGEMENT LINE (POWERGRID)-HISSAR IA (220KV) DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING 05-11 05-11 BOARD BOARD (HVPNL) 2 BHAKRA BEAS BHAKRA BEAS HISSAR BBMB (220KV)(BBMB)- 2018- 2018- 143 MANAGEMENT MANAGEMENT LINE DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING CHIRAWA (220KV)(RRVPN) 05-14 05-14 BOARD BOARD DELHI OKHLA (220KV)(DTL)-BADARPUR 2018- 2018- 144 SLDC Delhi TRANSCO LINE DAILY DEAD END REPLACEMENT AT TOWER NO 25. 05:00 10:00 5 -- PENDING (220KV)(NTPC) 1 05-12 05-12 LIMITED Haryana SLDC Vidyut ICT03 DHANONDA (400KV) For gen mtc of bay equipment and alignment of 2018- 2018- 145 ICT DAILY 09:00 16:00 7 -- PENDING Haryana Prasaran (HVPNL)(ICT4000010)/315 isolator. 05-15 05-15 Nigam LTD Uttar Pradesh Power SLDC Uttar ANPARA-B (400KV)(UPRVUNL)- 2018- 2018- 146 Transmission LINE CONTINUOUS Diversion work for Obra C 08:00 18:00 226 -- PENDING Pradesh OBRA (400KV)(UPPTCL) 05-01 05-10 Corporation Limited Uttar Pradesh Power SLDC Uttar ANPARA-B (400KV)(UPRVUNL)- For replacement of disc insulator by polymer & 2018- 2018- 147 Transmission LINE DAILY 08:00 18:00 178 -- PENDING Pradesh SARNATH (400KV)(UPPTCL) 2 replacement of Earthwire. 05-11 05-18 Corporation Limited Uttar Pradesh Power SLDC Uttar ANPARA-B (400KV)(UPRVUNL)- For DFCC works & replacement of damaged 2018- 2018- 148 Transmission LINE CONTINUOUS 08:00 18:00 154 -- PENDING Pradesh SARNATH (400KV)(UPPTCL) 1 conductor 05-25 05-31 Corporation Limited Uttar Pradesh "1. For replacement of disc insulator by polymer & Power SLDC Uttar ANPARA-B (400KV)(UPRVUNL)- replacement of Earthwire. 2. Servicing & 2018- 2018- 149 Transmission LINE DAILY 08:00 18:00 154 -- PENDING Pradesh MAU (400KV)(UPPTCL) overhauling of pantograph isolator, replacement 05-18 05-24 Corporation of contact blades. " Limited BHAKRA BEAS BHAKRA BEAS CHARKHI DADRI (220KV)(BBMB)- 2018- 2018- 150 MANAGEMENT MANAGEMENT LINE MAHINDERGARH HVPNL (220KV) DAILY Half Yearly Maintenance 08:00 17:00 9 -- PENDING 05-11 05-11 BOARD BOARD (HVPNL) 2 RAJASTHAN SLDC RAJYA VIDYUT ANTA(400KV)(RRVPN)-KALISINDH 2018- 2018- 151 LINE DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (400KV)(RRVPN) 2 05-03 05-03 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS JALLANDHAR-PG (220KV) 2018- 2018- 152 MANAGEMENT MANAGEMENT LINE (POWERGRID)-DASUYA (220KV) DAILY Half yearly mtc. of the substation equipment 08:00 17:00 9 -- PENDING 05-17 05-17 BOARD BOARD (PSTCL) I BHAKRA BEAS BHAKRA BEAS JALLANDHAR BBMB (220KV) 2018- 2018- 153 MANAGEMENT MANAGEMENT LINE (BBMB)-JAMSHER (220KV) DAILY Half yearly mtc. of the substation equipment 08:00 17:00 9 -- PENDING 05-22 05-22 BOARD BOARD (PSTCL) 1 Uttar Pradesh Power TANDA (220KV)(NTPC)- SLDC Uttar For Replacement of Insulators with polymer 2018- 2018- 154 Transmission LINE GORAKHPUR (BARAUHA)-UP DAILY 08:00 18:00 226 -- PENDING Pradesh Insulators. 05-11 05-20 Corporation (220KV)(UPPTCL) Limited BHAKRA BEAS BHAKRA BEAS JALLANDHAR BBMB (220KV) 2018- 2018- 155 MANAGEMENT MANAGEMENT LINE (BBMB)-JAMSHER (220KV) DAILY Half yearly mtc. of the substation equipment 08:00 17:00 9 -- PENDING 05-23 05-23 BOARD BOARD (PSTCL) 2 BHAKRA BEAS BHAKRA BEAS BAIRASUIL (220KV)(NHPC)-PONG Yearly mtc of 220KV SF-6 Breaker A-1 controlling 2018- 2018- 156 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 9 -- PENDING (220KV)(BBMB) Ckt & its allied equipments at Pong. 05-04 05-04 BOARD BOARD RAJASTHAN SLDC RAJYA VIDYUT ANTA(400KV)(RRVPN)-CHHABRA 2018- 2018- 157 LINE DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (400KV)(RRVPN) 1 05-08 05-08 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT ANTA(400KV)(RRVPN)-KAWAI 2018- 2018- 158 LINE DAILY Replacement of 02 nos CVT at Line 09:00 18:30 9 -- PENDING Rajasthan PRASARAN (400KV)(RRVPN) 2 05-08 05-08 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS JASSURE(HIMACHAL PRADESH Yearly mtc of 220KV SF-6 Breaker A-2 controlling 2018- 2018- 159 MANAGEMENT MANAGEMENT LINE STATE ELECTRICITY BOARD DAILY 08:00 17:00 9 -- PENDING Ckt & its allied equipments at Pong. 05-05 05-05 BOARD BOARD LIMITED)-PONG (220KV)(BBMB) 2 RAJASTHAN SLDC RAJYA VIDYUT ANTA(400KV)(RRVPN)-KAWAI 2018- 2018- 160 LINE DAILY Replacement of 01 no CVT at Line 09:00 18:30 9 -- PENDING Rajasthan PRASARAN (400KV)(RRVPN) 1 05-10 05-10 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS PONG (220KV)(BBMB)- Yearly mtc of 220KV SF-6 Breaker A-10 controlling 2018- 2018- 161 MANAGEMENT MANAGEMENT LINE JALLANDHAR BBMB (220KV) DAILY 08:00 17:00 9 -- PENDING Ckt & its allied equipments at Pong. 05-10 05-10 BOARD BOARD (BBMB) I RAJASTHAN SLDC RAJYA VIDYUT CHHABRA (400KV)(RRVPN)- 2018- 2018- 162 LINE DAILY Replacement of 01 no CVT at Line 09:00 18:30 9 -- PENDING Rajasthan PRASARAN KAWAI SCTPS (400KV)(ADANIRJ) 05-11 05-11 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS PONG (220KV)(BBMB)- Yearly mtc of 220KV SF-6 Breaker A-11 controlling 2018- 2018- 163 MANAGEMENT MANAGEMENT LINE JALLANDHAR BBMB (220KV) DAILY 08:00 17:00 9 -- PENDING Ckt & its allied equipments at Pong. 05-11 05-11 BOARD BOARD (BBMB) II RAJASTHAN SLDC RAJYA VIDYUT HISSAR BBMB (220KV)(BBMB)- 2018- 2018- 164 LINE DAILY Half yearly maintenace work of bay and line 08:00 19:00 35 -- PENDING Rajasthan PRASARAN CHIRAWA (220KV)(RRVPN) 05-11 05-12 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS PONG (220KV)(BBMB)-DASUYA Yearly mtc of 220KV SF-6 Breaker A-14 controlling 2018- 2018- 165 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 9 -- PENDING (220KV)(PSTCL) 1 Ckt & its allied equipments at Pong. 05-15 05-15 BOARD BOARD BHAKRA BEAS BHAKRA BEAS DEHAR (220KV)(BBMB)- Half yearly mtc. of the substation equipment 2018- 2018- 166 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 33 -- PENDING GANGUWAL (220KV)(BBMB) 2 related with Ckt. at Slapper end. 05-08 05-09 BOARD BOARD RAJASTHAN SLDC RAJYA VIDYUT BARMER (400KV)(RRVPN)- 2018- 2018- 167 LINE DAILY Quarterly Maintenance 10:00 18:00 8 -- PENDING Rajasthan PRASARAN RAJWEST (400KV)(RRVPN) 05-10 05-10 NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS PONG (220KV)(BBMB)-DASUYA Yearly mtc of 220KV SF-6 Breaker A-15 controlling 2018- 2018- 168 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 9 -- PENDING (220KV)(PSTCL) 2 Ckt & its allied equipments at Pong. 05-16 05-16 BOARD BOARD RAJASTHAN AKAL JAISALMER (400KV) SLDC RAJYA VIDYUT Erection of Gentry Beam (G2 Type) in Dia-4 by M/s 2018- 2018- 169 LINE (RRVPN)-BARMER (400KV) CONTINUOUS 06:00 18:00 36 -- PENDING Rajasthan PRASARAN GE T&D India Limited AT BARMER 05-21 05-22 (RRVPN) NIGAM LIMITED BHAKRA BEAS BHAKRA BEAS DEHAR (220KV)(BBMB)- Half yearly mtc. of the substation equipment 2018- 2018- 170 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 33 -- PENDING GANGUWAL (220KV)(BBMB) 1 related with Ckt. at Slapper end. 05-15 05-16 BOARD BOARD RAJASTHAN AKAL JAISALMER (400KV) SLDC RAJYA VIDYUT Erection of Gentry Beam (G1 Type) in Dia-4 by M/s 2018- 2018- 171 LINE (RRVPN)-BARMER (400KV) CONTINUOUS 06:00 18:00 36 -- PENDING Rajasthan PRASARAN GE T&D India Limited AT BARMER 05-25 05-26 (RRVPN) NIGAM LIMITED RAJASTHAN AKAL JAISALMER (400KV) SLDC RAJYA VIDYUT Erection of Gentry Beam (G1 Type) in Dia-4 by M/s 2018- 2018- 172 LINE (RRVPN)-BARMER (400KV) CONTINUOUS 06:00 18:00 36 -- PENDING Rajasthan PRASARAN GE T&D India Limited AT BARMER 05-29 05-30 (RRVPN) NIGAM LIMITED DEHAR (220KV)(BBMB)-KANGOO BHAKRA BEAS BHAKRA BEAS (220KV)(HIMACHAL PRADESH Half yearly mtc. of the substation equipment 2018- 2018- 173 MANAGEMENT MANAGEMENT LINE DAILY 08:00 17:00 33 -- PENDING STATE ELECTRICITY BOARD related with Ckt. at Slapper end. 05-21 05-22 BOARD BOARD LIMITED) RAJASTHAN SLDC RAJYA VIDYUT BASSI (220KV)(POWERGRID)- 2018- 2018- 174 LINE DAILY Quarterly maintenance 09:30 15:30 6 -- PENDING Rajasthan PRASARAN DAUSA (220KV)(POWERGRID) 1 05-22 05-22 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT BASSI (220KV)(POWERGRID)- 2018- 2018- 175 LINE DAILY Quarterly maintenance 09:30 15:30 6 -- PENDING Rajasthan PRASARAN DAUSA (220KV)(POWERGRID) 2 05-23 05-23 NIGAM LIMITED RAJASTHAN SAWAI MADHOPUR (220KV) SLDC RAJYA VIDYUT 2018- 2018- 176 LINE (RRVPN)-DAUSA (220KV) DAILY Quarterly maintenance 09:30 15:30 6 -- PENDING Rajasthan PRASARAN 05-24 05-24 (POWERGRID) I( PG NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT LALSOT (220KV)(RRVPN)-DAUSA 2018- 2018- 177 LINE DAILY Quarterly maintenance 09:30 15:30 6 -- PENDING Rajasthan PRASARAN (220KV)(POWERGRID) PG 05-25 05-25 NIGAM LIMITED RAJASTHAN for maintenance & tree cutting of the 220 kV Agra- SLDC RAJYA VIDYUT BHARATPUR (220KV)(RRVPN)- 2018- 2018- 178 LINE DAILY Bharatpur Inerstate line & Bay work at 220 kV GSS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN SIKANDRA (220KV)(UPPTCL) 05-11 05-11 RVPN, Bharapur NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT BIKANER (400KV)(RRVPN)- 2018- 2018- 179 LINE DAILY Routine Bay Maintenance work 07:00 10:00 3 -- PENDING Rajasthan PRASARAN BHADLA (400KV)(RRVPN) 1 05-10 05-10 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT BIKANER (400KV)(RRVPN)- 2018- 2018- 180 LINE DAILY Routine Bay Maintenance work 07:00 10:00 3 -- PENDING Rajasthan PRASARAN BHADLA (400KV)(RRVPN) 2 05-11 05-11 NIGAM LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION General Maintenenace jumper tightening and tree 2018- 2018- 181 SLDC Punjab LINE (PSPCL)-MUKTSAR (400KV) DAILY 09:00 17:00 8 -- PENDING CORPORATION cutting 05-01 05-01 (PSTCL) 1 LIMITED RAJASTHAN SLDC RAJYA VIDYUT BIKANER (400KV)(RRVPN)- 2018- 2018- 182 LINE DAILY Routine Bay Maintenance work 10:00 17:00 7 -- PENDING Rajasthan PRASARAN MERTA (400KV)(RRVPN) 05-17 05-17 NIGAM LIMITED PUNJAB STATE TRANSMISSION KANGRA (132KV)(PSPCL)- Disc cleaning & jumper tightemimg and other mtc. 2018- 2018- 183 SLDC Punjab LINE DAILY 10:00 16:00 6 -- PENDING CORPORATION SHANAN (132KV)(PSPCL) to be done 05-03 05-03 LIMITED For annual maintenance Remark:- 1. Power evacuation will be through 400kV CTPP-Bhilwara, RAJASTHAN 400kV CTPP-Hindaun Line , 220kV CTPP-Jhalawar SLDC RAJYA VIDYUT CHHABRA (400KV)(RRVPN)- 2018- 2018- 184 LINE CONTINUOUS line and 220 kV CTPP-Kawai line. 2. Due to 08:00 18:00 34 -- PENDING Rajasthan PRASARAN KAWAI SCTPS (400KV)(ADANIRJ) 05-21 05-22 proximity of cooling towers the insulators gets NIGAM LIMITED scaled, therefore descaling is must and it requires minimum 2 days. BHAKRA BEAS BHAKRA BEAS ICT PANIPAT BBMB (400KV) 2018- 2018- 185 MANAGEMENT MANAGEMENT ICT DAILY Half Yearly Maintenance 08:00 17:00 9 -- PENDING (BBMB)(ICT4000047)/450 05-02 05-02 BOARD BOARD PUNJAB STATE TRANSMISSION RAJPURA TPS (400KV)(NPLPB)- Tigheting of nut bolts of jumper, dampers, 2018- 2018- 186 SLDC Punjab LINE DAILY 09:00 17:00 8 -- PENDING CORPORATION RAJPURA (400KV)(PSTCL) 1 suspension clamps and cleaning of disc insulators 05-03 05-03 LIMITED For annual maintenance, checking of auto reclosing scheme and Descaling of insulators RAJASTHAN Remark:-1. Power evacuation will be through SLDC RAJYA VIDYUT BHILWARA (400KV)(RRVPN)- 400kV CTPP-Adani, 400kV CTPP-Hindon Line , 2018- 2018- 187 LINE CONTINUOUS 08:00 18:00 34 -- PENDING Rajasthan PRASARAN CHHABRA (400KV)(RRVPN) 220kV CTPP-Jhalawar line and 220 kV CTPP-Kawai 05-04 05-05 NIGAM LIMITED line. 2. Due to proximity of cooling towers the insulators gets scaled, therefore descaling is must and it requires minimum 2 days. BHAKRA BEAS BHAKRA BEAS ICT02 PANIPAT-PG (400KV) 2018- 2018- 188 MANAGEMENT MANAGEMENT ICT (POWERGRID) DAILY Half Yearly Maintenance 08:00 17:00 9 -- PENDING 05-03 05-03 BOARD BOARD (PGICT40000103)/450 For incorporating auto reclosing and annual maintenance at CTPP end. Remarks:- 1. Power RAJASTHAN evacuation will be through 400kV CTPP-Adani, SLDC RAJYA VIDYUT HINDAUN (400KV)(RRVPN)- 400kV CTPP-Bhilwara Line , 220kV CTPP-Jhalawar 2018- 2018- 189 LINE CONTINUOUS 08:00 18:00 34 -- PENDING Rajasthan PRASARAN CHHABRA (400KV)(RRVPN) line and 220 kV CTPP-Kawai line. 2. Due to 05-01 05-02 NIGAM LIMITED proximity of cooling towers the insulators gets scaled, therefore descaling is must and it requires minimum 2 days. RAJASTHAN SLDC RAJYA VIDYUT JODHPUR (400KV)(RRVPN)-AKAL Quaterly Maintenance of BOTH ENDS OF BAYS AND 2018- 2018- 190 LINE DAILY 09:00 18:00 9 -- PENDING Rajasthan PRASARAN JAISALMER (400KV)(RRVPN) LINE 05-17 05-17 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT MERTA (400KV)(RRVPN)- 2018- 2018- 191 LINE DAILY IInd Quarterly maintenance work OF BAYS AND LINE 10:00 18:00 8 -- PENDING Rajasthan PRASARAN JODHPUR (400KV)(RRVPN) II 05-10 05-10 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT KANKROLI (400KV)(POWERGRID)- 2018- 2018- 192 LINE DAILY IInd Quarterly maintenance work OF BAYS AND LINE 10:00 18:00 8 -- PENDING Rajasthan PRASARAN JODHPUR (400KV)(RRVPN) 05-24 05-24 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT MERTA (400KV)(RRVPN)- IInd Quarterly maintenance work OF BAYS AND LINE 2018- 2018- 193 LINE DAILY 10:00 18:00 8 -- PENDING Rajasthan PRASARAN JODHPUR (400KV)(RRVPN) I at jodhpur 05-31 05-31 NIGAM LIMITED RAJASTHAN RAPS B (220KV)(NPCIL)- SLDC RAJYA VIDYUT 2018- 2018- 194 LINE SAKATPURA-KOTA (220KV) DAILY QUARTERLY MAINTENANCE WORK 08:00 18:00 10 -- PENDING Rajasthan PRASARAN 05-10 05-10 (RRVPN) NIGAM LIMITED PUNJAB STATE MAKHU (400KV)(PSTCL)- TRANSMISSION Tightening/checking of jumpers and cleaning of 2018- 2018- 195 SLDC Punjab LINE AMRITSAR (400KV)(POWERGRID) DAILY 09:30 18:30 9 -- PENDING CORPORATION disc insulators in polluted area 05-03 05-03 I LIMITED RAJASTHAN SLDC RAJYA VIDYUT CHARKHI DADRI (220KV)(BBMB)- REPLACEMENT OF DISC INSULATORS WITH 2018- 2018- 196 LINE CONTINUOUS 09:00 17:00 344 -- PENDING Rajasthan PRASARAN KHETRI (220KV)(RRVPN) 1 COMPOSITE DISC INSULATORS 05-02 05-16 NIGAM LIMITED PUNJAB STATE MAKHU (400KV)(PSTCL)- TRANSMISSION Tightening/checking of jumpers and cleaning of 2018- 2018- 197 SLDC Punjab LINE AMRITSAR (400KV)(POWERGRID) DAILY 10:00 17:00 7 -- PENDING CORPORATION disc insulators in polluted area 05-04 05-04 II LIMITED RAJASTHAN SLDC RAJYA VIDYUT CHARKHI DADRI (220KV)(BBMB)- REPLACEMENT OF DISC INSULATORS WITH 2018- 2018- 198 LINE CONTINUOUS 09:00 17:00 344 -- PENDING Rajasthan PRASARAN KHETRI (220KV)(RRVPN) 2 COMPOSITE DISC INSULATORS 05-17 05-31 NIGAM LIMITED PUNJAB STATE TRANSMISSION RAJPURA (400KV)(PSTCL)-DHURI 2018- 2018- 199 SLDC Punjab LINE DAILY Line jumper/ Nut Bolt tightening 09:00 17:00 32 -- PENDING CORPORATION (400KV)(PSTCL) 1 05-07 05-08 LIMITED RAJASTHAN SLDC RAJYA VIDYUT MERTA (400KV)(RRVPN)- 2018- 2018- 200 LINE DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN HEERAPURA (400KV)(RRVPN) 05-03 05-03 NIGAM LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION 2018- 2018- 201 SLDC Punjab LINE (PSPCL)-NAKODAR (400KV) DAILY General Maintenance 09:00 17:00 8 -- PENDING CORPORATION 05-07 05-07 (PSTCL) LIMITED RAJASTHAN SLDC RAJYA VIDYUT KOTA (400KV)(POWERGRID)- 2018- 2018- 202 LINE DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN MERTA (400KV)(RRVPN) I 05-04 05-04 NIGAM LIMITED PUNJAB STATE TRANSMISSION RAJPURA TPS (400KV)(NPLPB)- Tightening of nut bolts of jumpers, dampers , 2018- 2018- 203 SLDC Punjab LINE DAILY 09:00 17:00 8 -- PENDING CORPORATION RAJPURA (400KV)(PSTCL) 2 suspension clamps and cleaning of Disc insulators 05-09 05-09 LIMITED RAJASTHAN SHREE CEMENTS (400KV)(SH. SLDC RAJYA VIDYUT 2018- 2018- 204 LINE CEMENTS)-MERTA (400KV) DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-07 05-07 (RRVPN) NIGAM LIMITED PUNJAB STATE NALLAGARH (220KV) Tightening of nut bolts of jumpers, dampers , TRANSMISSION 2018- 2018- 205 SLDC Punjab LINE (POWERGRID)-MOHALI (220KV) DAILY suspension clamps and cleaning of Disc insulators 10:00 17:00 7 -- PENDING CORPORATION 05-09 05-09 (PSTCL) 1 of Tower No 40 to 50 LIMITED PUNJAB STATE TRANSMISSION RAJPURA TPS (400KV)(NPLPB)- Tightening of nut bolts of jumpers, dampers , 2018- 2018- 206 SLDC Punjab LINE DAILY 10:00 17:00 7 -- PENDING CORPORATION NAKODAR (400KV)(PSTCL) 1 suspension clamps and cleaning of Disc insulators 05-10 05-10 LIMITED PUNJAB STATE TRANSMISSION KANGRA (132KV)(PSPCL)- Disc cleaning & Jumper tightening and other mtc. 2018- 2018- 207 SLDC Punjab LINE DAILY 10:00 16:00 6 -- PENDING CORPORATION SHANAN (132KV)(PSPCL) to be done 05-10 05-10 LIMITED PUNJAB STATE TRANSMISSION MUKTSAR (400KV)(PSTCL)- tightening/checking of jumpers and cleaning of 2018- 2018- 208 SLDC Punjab LINE DAILY 10:00 17:00 7 -- PENDING CORPORATION MAKHU (400KV)(PSTCL) 1 disc insulators in polluted area 05-10 05-10 LIMITED PUNJAB STATE TRANSMISSION MUKTSAR (400KV)(PSTCL)- tightening/checking of jumpers and cleaning of 2018- 2018- 209 SLDC Punjab LINE DAILY 10:00 17:00 7 -- PENDING CORPORATION MAKHU (400KV)(PSTCL) 2 disc insulators in polluted area 05-11 05-11 LIMITED PUNJAB STATE TRANSMISSION RAJPURA (400KV)(PSTCL)-DHURI 2018- 2018- 210 SLDC Punjab LINE DAILY Line jumper/ Nut Bolt tightening 10:00 16:00 30 -- PENDING CORPORATION (400KV)(PSTCL) 2 05-14 05-15 LIMITED RAJASTHAN SLDC RAJYA VIDYUT ICT03 AKAL JAISALMER (400KV) 2018- 2018- 211 ICT DAILY QUARTERLY MAINTANANCE 09:00 16:00 7 -- PENDING Rajasthan PRASARAN (RRVPN)(ICT4000071)/315 05-15 05-15 NIGAM LIMITED PUNJAB STATE TRANSMISSION RAJPURA TPS (400KV)(NPLPB)- Tightening of nut bolts of jumpers, dampers , 2018- 2018- 212 SLDC Punjab LINE DAILY 09:00 17:00 8 -- PENDING CORPORATION NAKODAR (400KV)(PSTCL) 2 suspension clamps and cleaning of Disc insulators 05-16 05-16 LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION General maintenance, Jumper tightening and Tree 2018- 2018- 213 SLDC Punjab LINE (PSPCL)-MUKTSAR (400KV) DAILY 09:00 17:00 8 -- PENDING CORPORATION Cutting 05-16 05-16 (PSTCL) 2 LIMITED PUNJAB STATE TRANSMISSION MOGA (400KV)(POWERGRID)- General maintenance, Jumper tightening and Tree 2018- 2018- 214 SLDC Punjab LINE DAILY 10:00 16:00 6 -- PENDING CORPORATION NAKODAR (400KV)(PSTCL) Cutting 05-17 05-17 LIMITED RAJASTHAN SLDC RAJYA VIDYUT ICT01 BHILWARA (400KV) Quarterly Maintenane of 400KV ICT-I Bay , 315MVA 2018- 2018- 215 ICT DAILY 09:00 17:00 8 -- PENDING Rajasthan PRASARAN (RRVPN)(ICT40000207)/315 TR-I and associated Equipments 05-23 05-23 NIGAM LIMITED PUNJAB STATE HAMIRPUR HSEB (132KV) TRANSMISSION (HIMACHAL PRADESH STATE Tightening of Jumpers of Deadend Towers, Disc 2018- 2018- 216 SLDC Punjab LINE DAILY 09:00 17:00 8 -- PENDING CORPORATION ELECTRICITY BOARD LIMITED)- Cleaning & Tree Cutting 05-16 05-16 LIMITED CHOHAL (132KV)(PSTCL) RAJASTHAN SLDC RAJYA VIDYUT ICT02 BHILWARA (400KV) Quarterly Maintenane of 400KV ICT-2 Bay , 315MVA 2018- 2018- 217 ICT DAILY 09:00 17:00 8 -- PENDING Rajasthan PRASARAN (RRVPN)(ICT4000064)/315 TR-II and associated Equipments 05-24 05-24 NIGAM LIMITED PUNJAB STATE TRANSMISSION KANGRA (132KV)(PSPCL)- Disc cleaning & Jumper tightening and other mtc. 2018- 2018- 218 SLDC Punjab LINE DAILY 10:00 16:00 6 -- PENDING CORPORATION PATHANKOT (132KV)(PSTCL) to be done 05-17 05-17 LIMITED RAJASTHAN SLDC RAJYA VIDYUT SHUNT REACTOR-I BIKANER 2018- 2018- 219 REACTOR DAILY Routine Bay Maintenance 10:00 17:00 7 -- PENDING Rajasthan PRASARAN (400KV)(BR4000012)/50.00 05-18 05-18 NIGAM LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION 2018- 2018- 220 SLDC Punjab LINE (PSPCL)-NAKODAR (400KV) DAILY General Maintenance 10:00 16:00 6 -- PENDING CORPORATION 05-24 05-24 (PSTCL) LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION 2018- 2018- 221 SLDC Punjab LINE (PSPCL)-DHURI (400KV)(PSTCL) DAILY Line jumper/nut bolt tightening 09:00 17:00 32 -- PENDING CORPORATION 05-21 05-22 1 LIMITED RAJASTHAN SLDC RAJYA VIDYUT Shunt Reactor (line reactor for 2018- 2018- 222 REACTOR DAILY Routine Maintenance 09:00 18:00 9 -- PENDING Rajasthan PRASARAN Akal Bay)(LR400009)/50.00 05-17 05-17 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 50MVAR 2018- 2018- 223 REACTOR DAILY Routine Bay Maintenance 09:00 18:00 9 -- PENDING Rajasthan PRASARAN REACTOR(LR4000029)/50.00 05-17 05-17 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT REACTOR AKAL JAISALMER 2018- 2018- 224 REACTOR DAILY Routine Maintenance 09:00 16:00 7 -- PENDING Rajasthan PRASARAN (400KV)(BR4000015)/50.00 05-19 05-19 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT Shunt Reactor RATANGARH 2018- 2018- 225 REACTOR DAILY REPLACEMENT OF LBB RELAY 09:00 18:00 9 -- PENDING Rajasthan PRASARAN (400KV)(BR4000016)/50.00 05-03 05-03 NIGAM LIMITED RAJASTHAN QUARTERLY MAINTANANCE Remark:- AS THE SLDC RAJYA VIDYUT 400KV BUS-I AKAL JAISALMER 2018- 2018- 226 BUS DAILY MAINTENANCE INCLUDES 40 ISOLATORS SO 2 DAYS 09:00 16:00 31 -- PENDING Rajasthan PRASARAN (400KV)(ABS4000025) 05-22 05-23 ARE REQUIRED NIGAM LIMITED RAJASTHAN 404-52-D CB OF ANTA- SLDC RAJYA VIDYUT 2018- 2018- 227 BAY KALISINDH-I AT 765KV DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN 05-16 05-16 ANTA(BAY1017) NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV 752A CB OF 400KV KOTA 2018- 2018- 228 BAY DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN LINE AT 400KV MERTA(BAY1021) 05-22 05-22 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV 752B CB OF 400KV KOTA 2018- 2018- 229 BAY DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN LINE AT 400KV MERTA(BAY1022) 05-23 05-23 NIGAM LIMITED RAJASTHAN 400KV 852A CB OF 400KV SCL SLDC RAJYA VIDYUT 2018- 2018- 230 BAY BEAWAR LINE AT 400KV DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-24 05-24 MERTA(BAY1023) NIGAM LIMITED RAJASTHAN 400KV 852B CB OF 400KV SCL SLDC RAJYA VIDYUT 2018- 2018- 231 BAY BEAWAR LINE AT 400KV DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-25 05-25 MERTA(BAY1024) NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT spare bay for 400kV Anta-Kawai 2018- 2018- 232 BAY DAILY Half yearly maintenace work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN at 765kV GSS ANTA(BAY1093) 05-22 05-22 NIGAM LIMITED RAJASTHAN 552B CB of 400kV Ratangarh SLDC RAJYA VIDYUT 2018- 2018- 233 BAY line at 400kV GSS DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-08 05-08 MERTA(BAY1095) NIGAM LIMITED RAJASTHAN 552T tie CB for 400KV SLDC RAJYA VIDYUT 2018- 2018- 234 BAY Ratangarh line at 400KV GSS DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-09 05-09 MERTA(BAY1096) NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 552A CB for 315MVA ILT-II at 2018- 2018- 235 BAY DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 400KV GSS MERTA(BAY1097) 05-10 05-10 NIGAM LIMITED RAJASTHAN 652B CB for 400KV HEERAPURA SLDC RAJYA VIDYUT 2018- 2018- 236 BAY LINE AT 400KV GSS DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-15 05-15 MERTA(BAY1098) NIGAM LIMITED RAJASTHAN 652T tie CB for 400kV SLDC RAJYA VIDYUT 2018- 2018- 237 BAY HEERAPURA LINE AT 400KV GSS DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN 05-16 05-16 MERTA(BAY1099) NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 652A CB for 125MVAR Reactor-I 2018- 2018- 238 BAY DAILY Ist QUARTERLY MAINT.WORK OF BAY & EQUIPMENTS 09:00 17:00 8 -- PENDING Rajasthan PRASARAN at 400KV GSS MERTA(BAY1100) 05-17 05-17 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS 2018- 2018- 239 BUS DAILY II QUARTERLY MAINT.WORK 09:00 18:00 9 -- PENDING Rajasthan PRASARAN A(ABS4000099) 05-17 05-17 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 2018- 2018- 240 BUS MAIN BUS-B(ABS40000100) DAILY IInd Quarterly maintenance work 09:00 18:00 9 -- PENDING Rajasthan PRASARAN 05-22 05-22 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS- Erection of Gentry Beam (G1 Type) in Dia-4 by M/s 2018- 2018- 241 BUS CONTINUOUS 06:00 18:00 36 -- PENDING Rajasthan PRASARAN I(ABS40000101) GE T&D India Limited 05-25 05-26 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS- Erection of Gentry Beam (G2 Type) in Dia-4 by M/s 2018- 2018- 242 BUS CONTINUOUS 06:00 18:00 84 -- PENDING Rajasthan PRASARAN II(ABS40000102) GE T&D India Limited, 05-15 05-18 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS- 2018- 2018- 243 BUS DAILY Routine Bay Maintenance work 07:00 10:00 3 -- PENDING Rajasthan PRASARAN I(ABS40000103) 05-10 05-10 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS- 2018- 2018- 244 BUS DAILY Routine Bay Maintenance work 10:00 17:00 7 -- PENDING Rajasthan PRASARAN II(ABS40000104) 05-24 05-24 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400KV MAIN BUS- 2018- 2018- 245 BUS DAILY IInd Quarterly maintenance work 10:00 18:00 8 -- PENDING Rajasthan PRASARAN A(ABS40000105) 05-31 05-31 NIGAM LIMITED RAJASTHAN 4352T , tie CB FOR 400KV AKAL- SLDC RAJYA VIDYUT Erection of Gentry Beam (G2 Type) in Dia-4 by M/s 2018- 2018- 246 BAY BARMER LINE AT 400KV GSS CONTINUOUS 06:00 18:00 84 -- PENDING Rajasthan PRASARAN GE T&D India Limited, 05-15 05-18 BARMER(BAY1094) NIGAM LIMITED POWER GRID POWER GRID BALIA(400KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 247 LINE SOHAWAL (400KV)(POWERGRID) DAILY AMP work of Isolator, CVT, WT, LA and Relay Testing 09:30 17:30 8 -- PENDING OF INDIA OF INDIA 05-08 05-08 I LIMITED LIMITED POWER GRID POWER GRID BALIA(400KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 248 LINE SOHAWAL (400KV)(POWERGRID) DAILY AMP work of Isolator, CVT, WT, LA and Relay Testing 09:30 17:30 8 -- PENDING OF INDIA OF INDIA 05-09 05-09 2 LIMITED LIMITED "Retrofitting of existing 400kV Lines and Integration of SCADA with HVDC Control Room: It POWER GRID POWER GRID AGRA-PG (400KV)(POWERGRID)- will be total new commissioning as all control & CORPORATION CORPORATION 2018- 2018- 249 LINE JAIPUR South (400KV) CONTINUOUS Power cables are need to be laid and changed a. 08:00 18:00 130 -- PENDING OF INDIA OF INDIA 05-04 05-09 (POWERGRID) I Laying of new cables b. Termination of cables c. LIMITED LIMITED Green lining d. C&P testing and greenlining e. Commissioning & Charging "Retrofitting of existing 400kV Lines and Integration of SCADA with HVDC Control Room: It POWER GRID POWER GRID AGRA-PG (400KV)(POWERGRID)- will be total new commissioning as all control & CORPORATION CORPORATION 2018- 2018- 250 LINE JAIPUR South (400KV) CONTINUOUS Power cables are need to be laid and changed a. 08:00 18:00 130 -- PENDING OF INDIA OF INDIA 05-15 05-20 (POWERGRID) II Laying of new cables b. Termination of cables c. LIMITED LIMITED Green lining d. C&P testing and greenlining e. Commissioning & Charging "Retrofitting of existing 400kV Lines and Integration of SCADA with HVDC Control Room: It POWER GRID POWER GRID AGRA-PG (400KV)(POWERGRID)- will be total new commissioning as all control & CORPORATION CORPORATION 2018- 2018- 251 LINE BHIWADI-PG (400KV) CONTINUOUS Power cables are need to be laid and changed a. 08:00 18:00 106 -- PENDING OF INDIA OF INDIA 05-10 05-14 (POWERGRID) I Laying of new cables b. Termination of cables c. LIMITED LIMITED Green lining d. C&P testing and greenlining e. Commissioning & Charging "Retrofitting of existing 400kV Lines and Integration of SCADA with HVDC Control Room: It POWER GRID POWER GRID AGRA-PG (400KV)(POWERGRID)- will be total new commissioning as all control & CORPORATION CORPORATION 2018- 2018- 252 LINE BHIWADI-PG (400KV) CONTINUOUS Power cables are need to be laid and changed a. 08:00 18:00 130 -- PENDING OF INDIA OF INDIA 05-21 05-26 (POWERGRID) II Laying of new cables b. Termination of cables c. LIMITED LIMITED Green lining d. C&P testing and greenlining e. Commissioning & Charging POWER GRID POWER GRID KANPUR (400KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 253 LINE KANPUR GIS (765KV) DAILY AMP of Line Equipments and Main bay 09:00 17:00 8 -- PENDING OF INDIA OF INDIA 05-02 05-02 (POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID ALLAHABAD-PHULPUR (220KV) REPLACEMENT OF CONDUCTOR FROM POWERGRID CORPORATION CORPORATION 2018- 2018- 254 LINE (POWERGRID)-REWA ROAD DAILY S/S GANTRY TO TOWER NO. -01 and UPPTCL S/S 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-01 05-02 (220KV)(UPPTCL) 1 GANTRY TO TOWER NO.-1 LIMITED LIMITED POWER GRID POWER GRID ALLAHABAD-PHULPUR (220KV) REPLACEMENT OF CONDUCTOR FROM POWERGRID CORPORATION CORPORATION 2018- 2018- 255 LINE (POWERGRID)-REWA ROAD DAILY S/S GANTRY TO TOWER NO. -01 and UPPTCL S/S 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-03 05-04 (220KV)(UPPTCL) 2 GANTRY TO TOWER NO.-19 LIMITED LIMITED POWER GRID POWER GRID SITARGANJ (220KV) To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 256 LINE (POWERGRID)-BAREILY-CB GANJ DAILY Missing Jumper Bolts, Spacer Damper,cottor 09:00 18:00 33 -- PENDING OF INDIA OF INDIA 05-08 05-09 (220KV)(UPPTCL) Pin,Broken Insulator Replacement etc) LIMITED LIMITED POWER GRID POWER GRID TANAKPUR (220KV)(NHPC)- To attend the shut down nature defects (Fixing of CORPORATION CORPORATION 2018- 2018- 257 LINE BAREILY-CB GANJ (220KV) DAILY Missing Jumper Bolts, Spacer Damper,cottor 09:00 18:00 33 -- PENDING OF INDIA OF INDIA 05-10 05-11 (UPPTCL) Pin,Broken Insulator Replacement etc) LIMITED LIMITED BHAKRA BEAS BHAKRA BEAS ICT BHIWANI BBMB (400KV) 2018- 2018- 258 MANAGEMENT MANAGEMENT ICT DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING (BBMB)(ICT4000048)/500 05-09 05-09 BOARD BOARD BHAKRA BEAS BHAKRA BEAS REACTOR I PANIPAT BBMB 2018- 2018- 259 MANAGEMENT MANAGEMENT REACTOR DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING (400KV)(BR400007)/80.00 05-10 05-10 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus-1 at 2018- 2018- 260 MANAGEMENT MANAGEMENT BUS DAILY Half yearly maintenance. 08:00 17:00 9 -- PENDING Panipat(ABS220002) 05-24 05-24 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus-2 at 2018- 2018- 261 MANAGEMENT MANAGEMENT BUS DAILY Half yearly maintenance of LHS of Bus. 08:00 17:00 9 -- PENDING Panipat(ABS220003) 05-22 05-22 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus-2 at 2018- 2018- 262 MANAGEMENT MANAGEMENT BUS DAILY Half yearly maintenance of RHS of Bus. 08:00 17:00 9 -- PENDING Panipat(ABS220003) 05-25 05-25 BOARD BOARD POWER GRID POWER GRID SHAMSAHABAD ROAD (220KV) CORPORATION CORPORATION 2018- 2018- 263 LINE (UPPTCL)-AGRA-PG (400KV) DAILY AMP works of Line bay at POWERGRID end, 08:00 18:00 10 -- PENDING OF INDIA OF INDIA 05-07 05-07 (POWERGRID) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION FIROZABAD (220KV)(UPPTCL)- 2018- 2018- 264 LINE DAILY AMP works of Line bay at POWERGRID end, 08:00 18:00 10 -- PENDING OF INDIA OF INDIA AGRA-PG (220KV)(POWERGRID) 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SINGRAULI NTPC (400KV)(NTPC)- For replacment of Disc Insulaotrs with Polymer 2018- 2018- 265 LINE DAILY 08:00 18:00 58 -- PENDING OF INDIA OF INDIA ANPARA-B (400KV)(UPRVUNL) insulator. 05-02 05-04 LIMITED LIMITED BHAKRA BEAS BHAKRA BEAS 220 KV Bus- I at Half yearly maintenance of bus coupler bay and 2018- 2018- 266 MANAGEMENT MANAGEMENT BUS DAILY 08:00 17:00 9 -- PENDING Hisar(ABS2200013) Bus-I. 05-15 05-15 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus- II at Half yearly maintenance of Bus coupler bay and 2018- 2018- 267 MANAGEMENT MANAGEMENT BUS DAILY 08:00 17:00 9 -- PENDING Hissar(ABS2200014) Bus-II at Hisar 05-17 05-17 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BARNALA (220KV)(BBMB)-LEHRA Urgently required for Automation of s/stn. & half 2018- 2018- 268 MANAGEMENT MANAGEMENT LINE CONTINUOUS 08:00 17:00 225 -- PENDING MOHABAT (200KV)(PSTCL) yearly maintenance of s/stn. equipment/Lines. 04-22 05-01 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BARNALA (220KV)(BBMB)- Urgently required for Automation of S/Stn. & half 2018- 2018- 269 MANAGEMENT MANAGEMENT LINE CONTINUOUS 08:00 17:00 225 -- PENDING SANGRUR (220KV)(BBMB) yearly maintenance of equipment/ Lines 05-12 05-21 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BALLABGARH BBMB (220KV) To replace 1 no. Line isolator ,1 no. PT ,2 Nos. CT 2018- 2018- 270 MANAGEMENT MANAGEMENT LINE (BBMB)-SAMAYPUR (220KV) CONTINUOUS and carry out half yearly maintenance at 220 kV 08:00 20:00 60 -- PENDING 04-09 04-11 BOARD BOARD (BBMB) 1 Samaypur substation. BHAKRA BEAS BHAKRA BEAS to replace 1 No. Blue phase CT and to carry out 220 KV Bus- I at 2018- 2018- 271 MANAGEMENT MANAGEMENT BUS CONTINUOUS half yearly maintenance at 220 kV Ballabhgarh sub 08:00 20:00 60 -- PENDING Samaypur(ABS2200015) 04-09 04-11 BOARD BOARD station. BHAKRA BEAS BHAKRA BEAS 220 KV Bus- II at 2018- 2018- 272 MANAGEMENT MANAGEMENT BUS DAILY half yearly maintenance of substation equipment. 08:00 17:00 9 -- PENDING Barnala(ABS2200010) 05-04 05-04 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus- I at half yearly maintenance of bus coupler -I and bus-I 2018- 2018- 273 MANAGEMENT MANAGEMENT BUS DAILY 08:00 17:00 33 -- PENDING Jamalpur(ABS2200011) and other substation equipments. 05-07 05-08 BOARD BOARD BHAKRA BEAS BHAKRA BEAS 220 KV Bus- II at half yearly mtc. of bus -II and bus coupler-II 2018- 2018- 274 MANAGEMENT MANAGEMENT BUS DAILY 08:00 17:00 33 -- PENDING Jamalpur(ABS2200012) /sectionalizer and substation equipment. 05-09 05-10 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BALLABGARH BBMB (220KV) 2018- 2018- 275 MANAGEMENT MANAGEMENT LINE (BBMB)-SAMAYPUR (220KV) DAILY To replace 2 no. CTs at Samaypur. 08:00 17:00 9 -- PENDING 04-23 04-23 BOARD BOARD (BBMB) 3 BHAKRA BEAS BHAKRA BEAS BALLABGARH BBMB (220KV) 2018- 2018- 276 MANAGEMENT MANAGEMENT LINE (BBMB)-BADARPUR (220KV) DAILY for replacement of 1 no. P.T. at Ballabhgarh. 08:00 17:00 9 -- PENDING 04-09 04-09 BOARD BOARD (NTPC) 2 Uttar Pradesh Power SLDC Uttar 400 kV main bus 1 2018- 2018- 277 Transmission BUS DAILY For Maintenance of Bus. 07:00 18:00 11 -- PENDING Pradesh Bareilly(ABS40000107) 05-21 05-21 Corporation Limited POWER GRID POWER GRID BHIWANI-PG (765 KV) CORPORATION CORPORATION 2018- 2018- 278 LINE (POWERGRID)-PHAGI (765KV) DAILY AMP work 08:00 18:00 10 -- PENDING OF INDIA OF INDIA 05-09 05-09 (RRVPN) 1 LIMITED LIMITED POWER GRID POWER GRID PHAGI (765KV)(RRVPN)- CORPORATION CORPORATION 2018- 2018- 279 LINE GWALIOR-WR (765KV) DAILY AMP Work 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-03 05-04 (POWERGRID) 1 LIMITED LIMITED POWER GRID POWER GRID PHAGI (765KV)(RRVPN)- CORPORATION CORPORATION 2018- 2018- 280 LINE GWALIOR-WR (765KV) DAILY AMP work 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-05 05-06 (POWERGRID) 2 LIMITED LIMITED Uttar Pradesh Power SLDC Uttar 400 kV Bus Reactor 2018- 2018- 281 Transmission REACTOR DAILY For Routine Maintenance and Tan Delta Testing 07:00 18:00 11 -- PENDING Pradesh Bareilly(BR4000056)/80.00 05-22 05-22 Corporation Limited POWER GRID POWER GRID JHATIKALA(765 KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 282 LINE BHIWANI-PG (765 KV) DAILY A' type delta tower strenghtening work 08:00 18:00 154 -- PENDING OF INDIA OF INDIA 05-07 05-13 (POWERGRID) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION AGRA-PG (765KV)(POWERGRID)- 2018- 2018- 283 LINE DAILY A' type delta tower strenghtening work 08:00 18:00 154 -- PENDING OF INDIA OF INDIA JHATIKALA(765 KV)(POWERGRID) 05-01 05-07 LIMITED LIMITED For removal of sheet piles under CW duct R&M Singrauli STPS(GENCO0047)- 2018- 2018- 284 NTPC Limited NTPC Limited GENCO CONTINUOUS works (site located under 400 KV lines from 00:30 23:30 143 -- PENDING U1/200 04-26 05-01 Unit#1) For removal of sheet piles under CW duct R&M Singrauli STPS(GENCO0050)- 2018- 2018- 285 NTPC Limited NTPC Limited GENCO CONTINUOUS works (site located under 400 KV lines from 00:30 23:30 95 -- PENDING U4/200 05-05 05-08 Unit#4) Uttar Pradesh Power SLDC Uttar Servicing & overhauling of pantograph isolator, 2018- 2018- 286 Transmission ICT ICT III(ICT40000221)/200 DAILY 08:00 18:00 10 -- PENDING Pradesh replacement of contact blades. 05-14 05-14 Corporation Limited Uttar Pradesh Power 400 kV Main bus 2 at SLDC Uttar For erection work of 400KV Pantograph isolator for 2018- 2018- 287 Transmission BUS Gorakhpur (UPPTCL) CONTINUOUS 09:00 18:00 129 -- PENDING Pradesh reactor bay 05-20 05-25 Corporation (ABS40000108) Limited Rihand TPS(GENCO0041)- 2018- 2018- 288 NTPC Limited NTPC Limited GENCO CONTINUOUS Unit Overhauling (Boiler+APH Seal Leakages) 00:30 23:30 599 -- PENDING U1/500 05-07 05-31 Uttar Pradesh Power 315 MVA Transformer at SLDC Uttar For attending the oil leakage from OLTC, pump & 2018- 2018- 289 Transmission ICT Gorakhpur (UPPTCL) CONTINUOUS 09:00 17:00 32 -- PENDING Pradesh changing the defective WTi / OTi 05-28 05-29 Corporation (ICT40000222)/315 MVA Limited POWER GRID POWER GRID CORPORATION CORPORATION BUS I CHITTORGARH(765KV) For Alumiinium Tube Connection of 704 & 707 Bay 2018- 2018- 290 BUS DAILY 10:00 18:00 32 -- PENDING OF INDIA OF INDIA (PGABS765001) Bus side Isolator to CB of banaskanta Bay. 05-02 05-03 LIMITED LIMITED Maintenance work of Line 1- Complete tightening Uttar Pradesh of section tower jumpers 2- Replacement of Power Jumpers. 3- Checking of OPGW wire. 4- Realignment SLDC Uttar MAINPURI-UP (765KV)(UPPTCL)- 2018- 2018- 291 Transmission LINE DAILY of vibration damper CC ring, spacer. 5- Insulator 08:00 18:00 82 -- PENDING Pradesh PARICHA (400KV)(UPRVUNL) 05-14 05-17 Corporation checking, cleaning and replacement of defective Limited disc. 6- Cutting, looping chopping of tree below the corridor. Uttar Pradesh Power SLDC Uttar BANDA (400KV)(UPPTCL)-REWA Tightening of jumper on section Tower. Chopping 2018- 2018- 292 Transmission LINE DAILY 08:00 18:00 34 -- PENDING Pradesh ROAD (400KV)(UPPTCL) of tree in proximity of conductor. 05-10 05-11 Corporation Limited Uttar Pradesh Power SLDC Uttar BANDA (400KV)(UPPTCL)-REWA 2018- 2018- 293 Transmission LINE DAILY For Jumpering of 220KV Bus Extension. 08:00 18:00 34 -- PENDING Pradesh ROAD (400KV)(UPPTCL) 2 05-12 05-13 Corporation Limited POWER GRID POWER GRID BHIWANI-PG (400KV) CORPORATION CORPORATION For Rectification of Defects observed during Aerial 2018- 2018- 294 LINE (POWERGRID)-JIND (400KV) DAILY 08:00 18:00 34 -- PENDING OF INDIA OF INDIA patrolling and Misc line mtc. Works 05-25 05-26 (POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID BHIWANI-PG (400KV) CORPORATION CORPORATION For Rectification of Defects observed during Aerial 2018- 2018- 295 LINE (POWERGRID)-JIND (400KV) DAILY 08:00 18:00 34 -- PENDING OF INDIA OF INDIA patrolling and Misc line mtc. Works 05-28 05-29 (POWERGRID) II LIMITED LIMITED POWER GRID POWER GRID BHIWADI-PG (400KV) CORPORATION CORPORATION 2018- 2018- 296 LINE (POWERGRID)-HISSAR-PG DAILY AMP work 08:00 18:00 10 -- PENDING OF INDIA OF INDIA 05-12 05-12 (400KV)(POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION BASSI (400KV)(POWERGRID)- 2018- 2018- 297 LINE DAILY To attend Shut down defects & AMP work 08:00 18:00 34 -- PENDING OF INDIA OF INDIA SIKAR (400KV)(POWERGRID) I 05-01 05-02 LIMITED LIMITED Uttar Pradesh Power SLDC Uttar ICT01 PANKI (400KV)(UPPTCL) Replacement of gasket and centrifusing of 2018- 2018- 298 Transmission ICT CONTINUOUS 08:00 17:00 585 -- PENDING Pradesh (ICT40000135)/240 transformer oil etc. No supply loss 05-07 05-31 Corporation Limited POWER GRID POWER GRID CORPORATION CORPORATION BASSI (400KV)(POWERGRID)- 2018- 2018- 299 LINE DAILY To attend Shut down defects & AMP work 08:00 18:00 34 -- PENDING OF INDIA OF INDIA SIKAR (400KV)(POWERGRID) II 05-03 05-04 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SIKAR (400KV)(POWERGRID)- 2018- 2018- 300 LINE DAILY To attend Shut down defects & AMP 08:00 18:00 34 -- PENDING OF INDIA OF INDIA RATANGARH (400KV)(RRVPN) 2 05-07 05-08 LIMITED LIMITED POWER GRID POWER GRID NEEMRANA (400KV) CORPORATION CORPORATION 2018- 2018- 301 LINE (POWERGRID)-SIKAR (400KV) DAILY Insulator replacement works. 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-10 05-11 (POWERGRID) II LIMITED LIMITED POWER GRID POWER GRID KANPUR (400KV)(POWERGRID)- CORPORATION CORPORATION Line Diversion work under NHAI .s/d will be avail dt 2018- 2018- 302 LINE BALLABGARH-PG (400KV) CONTINUOUS 08:00 18:00 202 -- PENDING OF INDIA OF INDIA 20.4.18 to 29.4.18 05-01 05-09 (POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID BALLABGARH-PG (400KV) CORPORATION CORPORATION Line Diversion work under DFCC.S/D will be avail 2018- 2018- 303 LINE (POWERGRID)-MAHARANIBAGH CONTINUOUS 08:00 18:00 490 -- PENDING OF INDIA OF INDIA from 21.4.18 to 10.5.18 05-10 05-30 (400KV)(POWERGRID) LIMITED LIMITED POWER GRID POWER GRID NAWADA (400KV)(HVPNL)- CORPORATION CORPORATION Line Diversion work under DFCC.S/D will be avail 2018- 2018- 304 LINE GREATER NOIDA (400KV) CONTINUOUS 08:00 18:00 202 -- PENDING OF INDIA OF INDIA from 21.4.18 to 10.5.18 05-01 05-09 (UPPTCL) LIMITED LIMITED POWER GRID POWER GRID Line Diversion work due to tower falling in the CORPORATION CORPORATION FARIDABAD GPS(NTPC)- 2018- 2018- 305 LINE CONTINUOUS middle of road (HUDA).S/d will be avail from 08:30 18:30 202 -- PENDING OF INDIA OF INDIA PALLA(HVPNL) I 05-01 05-09 20.4.18.to 29 .4.18 LIMITED LIMITED POWER GRID POWER GRID Line Diversion work due to tower falling in the CORPORATION CORPORATION FARIDABAD GPS(NTPC)- 2018- 2018- 306 LINE CONTINUOUS middle of road (HUDA).S/d will be avail from 08:30 18:30 202 -- PENDING OF INDIA OF INDIA PALLA(HVPNL) II 05-01 05-09 20.4.18.to 29 .4.18 LIMITED LIMITED POWER GRID POWER GRID ROORKEE (400KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 307 LINE SAHARANPUR (400KV) DAILY For AMP 08:00 18:00 10 -- PENDING OF INDIA OF INDIA 05-07 05-07 (POWERGRID) 1 LIMITED LIMITED POWER GRID POWER GRID BAGHPAT (400KV)(POWERGRID)- CORPORATION CORPORATION 2018- 2018- 308 LINE SAHARANPUR (400KV) DAILY For AMP 08:00 18:00 10 -- PENDING OF INDIA OF INDIA 05-09 05-09 (POWERGRID) LIMITED LIMITED POWER GRID POWER GRID SAHARANPUR-UP (220KV) CORPORATION CORPORATION 2018- 2018- 309 LINE (UPPTCL)-SAHARANPUR-PG DAILY For AMP 11:00 19:30 8 -- PENDING OF INDIA OF INDIA 05-14 05-14 (220KV)(POWERGRID) LIMITED LIMITED POWER GRID POWER GRID NANAUTA (220KV)(UPPTCL)- CORPORATION CORPORATION 2018- 2018- 310 LINE SAHARANPUR-PG (220KV) DAILY For AMP 12:00 20:30 8 -- PENDING OF INDIA OF INDIA 05-16 05-16 (POWERGRID) LIMITED LIMITED POWER GRID POWER GRID BHIWADI-PG (400KV) CORPORATION CORPORATION Disconnector switch 403-89A modification & 2018- 2018- 311 LINE (POWERGRID)-GURGAON CONTINUOUS 09:00 18:00 57 -- PENDING OF INDIA OF INDIA associated bay 203 will be also in outage 05-03 05-05 (400KV)(POWERGRID) LIMITED LIMITED POWER GRID POWER GRID BALLABGARH-PG (400KV) CORPORATION CORPORATION Disconnector switch 402-89A modification & 2018- 2018- 312 LINE (POWERGRID)-GURGAON CONTINUOUS 09:00 18:00 129 -- PENDING OF INDIA OF INDIA associated bay 402 will be also in outage 05-10 05-15 (400KV)(POWERGRID) LIMITED LIMITED Uttar Pradesh Power SLDC Uttar 400 kV Bus - A PANKI (400KV) For replacement of A- Bus Pentograph Isolator of 2018- 2018- 313 Transmission BUS CONTINUOUS 08:00 17:00 105 -- PENDING Pradesh (ABS4000027) ICT-I. No supply loss 05-08 05-12 Corporation Limited Uttar Pradesh Power SLDC Uttar ICT02 AGRA-UP (400KV) For routine maintenance and testing. No supply 2018- 2018- 314 Transmission ICT DAILY 09:00 18:00 9 -- PENDING Pradesh (UPPTCL)(ICT40000209)/500 loss 05-10 05-10 Corporation Limited Uttar Pradesh Power AGRA-UP (400KV)(UPPTCL)- SLDC Uttar For attending PLCC link healthiness and wave trap 2018- 2018- 315 Transmission LINE FATEHBAD _AGRA(400KV) DAILY 08:00 18:00 34 -- PENDING Pradesh damaged net. No supply loss 05-21 05-22 Corporation (UPPTCL) Limited Uttar Pradesh Power SLDC Uttar AGRA-PG (400KV)(POWERGRID)- For routine maintenance and testing. No supply 2018- 2018- 316 Transmission LINE DAILY 09:00 18:00 9 -- PENDING Pradesh AGRA-UP (400KV)(UPPTCL) loss 05-12 05-12 Corporation Limited Uttar Pradesh Power SLDC Uttar For replacement of 400 KV B- Bus Pentoraph 2018- 2018- 317 Transmission BUS BUS B-PANKI(ABS4000055) CONTINUOUS 08:00 17:00 105 -- PENDING Pradesh Isolator of ICT-I. No supply loss 05-14 05-18 Corporation Limited Uttar Pradesh Power 400 kV Bus Reactor at 765 kV SLDC Uttar O-rings needs to be changed for attending oil 2018- 2018- 318 Transmission REACTOR Fatehabad (UPPTCL) CONTINUOUS 08:00 18:00 34 -- PENDING Pradesh leakages. No supply loss 05-19 05-20 Corporation (BR4000057)/80.00 Limited Uttar Pradesh Power SLDC Uttar ICT01 MURADNAGAR (400KV) 2018- 2018- 319 Transmission ICT CONTINUOUS Replacement of 400KV side Isolator 08:00 15:00 79 -- PENDING Pradesh (UPPTCL)(ICT40000172)/315 05-02 05-05 Corporation Limited Uttar Pradesh Power ROORKEE (400KV)(POWERGRID)- SLDC Uttar 2018- 2018- 320 Transmission LINE MUZZAFARNAGAR-UP (400KV) DAILY For routine testing & preventive maintenance 10:00 18:00 8 -- PENDING Pradesh 05-03 05-03 Corporation (UPPTCL) Limited Uttar Pradesh Power MUZZAFARNAGAR-UP (400KV) SLDC Uttar 2018- 2018- 321 Transmission LINE (UPPTCL)-MUZZAFARNAGAR PG DAILY For routine testing & preventive maintenance 10:00 18:00 8 -- PENDING Pradesh 05-04 05-04 Corporation (400KV)(POWERGRID) Limited Uttar Pradesh Power SLDC Uttar ICT01 GREATER NOIDA (400KV) For general maintenance of T/F and for attending 2018- 2018- 322 Transmission ICT DAILY 08:00 17:00 9 -- PENDING Pradesh (UPPTCL)(ICT40000140)/315 Bus A Isolator problem alongwith 400KV Bus A. 05-06 05-06 Corporation Limited Uttar Pradesh Power SLDC Uttar ICT02 GREATER NOIDA (400KV) For general maintenance of T/F and for attending 2018- 2018- 323 Transmission ICT DAILY 08:00 17:00 9 -- PENDING Pradesh (UPPTCL)(ICT40000141)/315 Bus B Isolator problem alongwith 400KV Bus B . 05-13 05-13 Corporation Limited Uttar Pradesh Power NARA (220KV)(UPPTCL)- SLDC Uttar For tree cutting, repairing of conductor, inspection 2018- 2018- 324 Transmission LINE ROORKEE PTCUL (220KV) DAILY 09:00 18:00 33 -- PENDING Pradesh of insulators & other maintenance work. 05-10 05-11 Corporation (PTCUL) +UPPT Limited Uttar Pradesh Power KHODRI (220KV)(PTCUL)- SLDC Uttar For lopping, Chopping of trees in line corridor and 2018- 2018- 325 Transmission LINE SAHARANPUR-UP (220KV) DAILY 08:00 18:00 34 -- PENDING Pradesh maintenance work of bay 05-14 05-15 Corporation (UPPTCL) 2 +UP Limited Uttar Pradesh Power NAWADA (400KV)(HVPNL)- SLDC Uttar 2018- 2018- 326 Transmission LINE GREATER NOIDA (400KV) DAILY For general maintenance of bay. 08:00 17:00 9 -- PENDING Pradesh 05-27 05-27 Corporation (UPPTCL) Limited Uttar Pradesh Power SLDC Uttar ICT03 SULTANPUR (400KV) For Routine Testing and M&R Work along with 2018- 2018- 327 Transmission ICT DAILY 08:00 18:00 10 -- PENDING Pradesh (UPPTCL)(ICT40000212)/315 220KV 'A' Bus 05-21 05-21 Corporation Limited Maintenance work of Line 1- Complete tightening Uttar Pradesh of section tower jumpers 2- Replacement of Power Jumpers. 3- Checking of OPGW wire. 4- Realignment SLDC Uttar MAINPURI-UP (765KV)(UPPTCL)- 2018- 2018- 328 Transmission LINE DAILY of vibration damper CC ring, spacer. 5- Insulator 08:00 18:00 82 -- PENDING Pradesh ORAI (400KV)(UPPTCL) 05-18 05-21 Corporation checking, cleaning and replacement of defective Limited disc. 6- Cutting, looping chopping of tree below the corridor. POWER GRID POWER GRID HISSAR-PG (220KV) CORPORATION CORPORATION Pre-Monsoon maintenance and defect removal of 2018- 2018- 329 LINE (POWERGRID)-HISSAR IA (220KV) DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA line. 04-28 04-28 (HVPNL) LIMITED LIMITED POWER GRID POWER GRID HISSAR-PG (220KV) CORPORATION CORPORATION Pre-Monsoon maintenance and defect removal of 2018- 2018- 330 LINE (POWERGRID)-HISSAR IA (220KV) DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA line. 04-27 04-27 (HVPNL) 2 LIMITED LIMITED POWER GRID POWER GRID 765KV PHAGI-1 M/BAY 716 CORPORATION CORPORATION 2018- 2018- 331 BAY BHIWANI(765KV PHAGI-1 M/BAY CONTINUOUS For Attending SF6 Gas leakage in R Phase CB 10:00 18:00 32 -- PENDING OF INDIA OF INDIA 05-15 05-16 716 BHIWANI) LIMITED LIMITED POWER GRID POWER GRID 765KV BHIWANI M/BAY 712 CORPORATION CORPORATION 2018- 2018- 332 BAY MEERUT(765KV BHIWANI M/BAY DAILY AMP WORK 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-01 05-02 712 MEERUT) LIMITED LIMITED POWER GRID POWER GRID 765KV AGRA T/BAY 714 CORPORATION CORPORATION 2018- 2018- 333 BAY MEERUT(765KV AGRA T/BAY 714 DAILY AMP Works 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-08 05-09 MEERUT) LIMITED LIMITED POWER GRID POWER GRID 765KV AGRA M/BAY 715 CORPORATION CORPORATION 2018- 2018- 334 BAY MEERUT(765KV AGRA M/BAY DAILY AMP Works 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-15 05-16 715 MEERUT) LIMITED LIMITED POWER GRID POWER GRID 765KV ICT-I T/BAY 705 Construction work of Banaskanta Bay REMARKS-For CORPORATION CORPORATION 2018- 2018- 335 BAY CHITOTGARH(765KV ICT-I T/BAY DAILY Alumiinium Tube Connection of 705 & 704 Bay Tie 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-07 05-09 705 CHITOTGARH) Bay & Main Bay of Banaskanta # 2 Bay LIMITED LIMITED POWER GRID POWER GRID 765KV ICT-II T/BAY 708 Construction work of Banaskanta Bay. REMARKS- CORPORATION CORPORATION 2018- 2018- 336 BAY CHITOTGARH(765KV ICT-II T/BAY DAILY For Alumiinium Tube Connection of 708 & 707 Bay 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-07 05-09 708 CHITOTGARH) Tie Bay & Main Bay of Banaskanta # 1 Bay LIMITED LIMITED 765KV AJMER -I & 240MVAR POWER GRID POWER GRID L/R(SW) BAY 713 CSD RELAY COMMISSIONING of Line Reactor CB,LR CORPORATION CORPORATION 2018- 2018- 337 BAY CHITORGARH(765KV AJMER -I & DAILY will be out of service during CSD relay 10:00 14:00 4 -- PENDING OF INDIA OF INDIA 05-10 05-10 240MVAR L/R(SW) BAY 713 commissioning & Line remain service with main CB LIMITED LIMITED CHITORGARH) POWER GRID POWER GRID 765KV AJMER -I T/ BAY 714 CORPORATION CORPORATION CSD RELAY COMMISSIONING of Tie CB, Line remain 2018- 2018- 338 BAY CHITORGARH(765KV AJMER -I T/ DAILY 10:00 14:00 4 -- PENDING OF INDIA OF INDIA service with main CB 05-10 05-10 BAY 714 CHITORGARH) LIMITED LIMITED 765KV AJMER -II & 240MVAR POWER GRID POWER GRID L/R(SW) BAY 710 CSD RELAY COMMISSIONING of Line Reactor CB,LR CORPORATION CORPORATION 2018- 2018- 339 BAY CHITORGARH(765KV AJMER -II & DAILY will be out of service during CSD relay 10:00 14:00 4 -- PENDING OF INDIA OF INDIA 05-04 05-04 240MVAR L/R(SW) BAY 710 commissioning & Line remain service with main CB LIMITED LIMITED CHITORGARH) POWER GRID POWER GRID 765KV ICT-I M/BAY 706 CSD RELAY COMMISSIONING of ICT # 1 main CB,ICT CORPORATION CORPORATION 2018- 2018- 340 BAY CHITOTGARH(765KV ICT-I M/BAY DAILY # 1 will be out of service during CSD relay 10:00 14:00 4 -- PENDING OF INDIA OF INDIA 05-14 05-14 706 CHITOTGARH) commissioning. LIMITED LIMITED POWER GRID POWER GRID 765KV ICT-II M/BAY 709 CSD RELAY COMMISSIONING of ICT # 2 main CB,ICT CORPORATION CORPORATION 2018- 2018- 341 BAY CHITORGARH(765KV ICT-II M/BAY DAILY # 2 will be out of service during CSD relay 15:00 19:00 4 -- PENDING OF INDIA OF INDIA 05-14 05-14 709 CHITORGARH) commissioning. LIMITED LIMITED POWER GRID POWER GRID 765 KV 240MVAR B/R-I M/BAY CB CSD RELAY COMMISSIONING of Bus Reactor- I,Main CORPORATION CORPORATION 712 CHITORGARH(765 KV 2018- 2018- 342 BAY DAILY CB,BR#1 remain service through Tie Bay ,during 10:00 14:00 4 -- PENDING OF INDIA OF INDIA 240MVAR B/R-I M/BAY CB 712 05-15 05-15 CSD relay commissioning LIMITED LIMITED CHITORGARH) POWER GRID POWER GRID 765 KV 240MVAR B/R-I T/BAY CB CSD RELAY COMMISSIONING of Bus Reactor- I,Main CORPORATION CORPORATION 711 CHITORGARH(765 KV 2018- 2018- 343 BAY DAILY CB,BR#1 remain service through Tie Bay ,during 15:00 19:00 4 -- PENDING OF INDIA OF INDIA 240MVAR B/R-I T/BAY CB 711 05-15 05-15 CSD relay commissioning LIMITED LIMITED CHITORGARH) POWER GRID POWER GRID ICT02 SOHAWAL (400KV) CORPORATION CORPORATION AMP of ICT-2 / Erection , Testing & Commissioning 2018- 2018- 344 ICT (POWERGRID) DAILY 09:30 17:30 56 -- PENDING OF INDIA OF INDIA of 72.5 Tertiary System 05-01 05-03 (PGICT4000071)/315 LIMITED LIMITED POWER GRID POWER GRID ICT01 SOHAWAL (400KV) CORPORATION CORPORATION Construction of remaining portion of Firewall 2018- 2018- 345 ICT (POWERGRID) DAILY 09:30 17:30 296 -- PENDING OF INDIA OF INDIA between Bus Reactor-2 & ICT-1 & AMP of ICT-1 05-05 05-17 (PGICT4000070)/315 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION PANKI-2 MAIN BAY, at 2018- 2018- 346 BAY CONTINUOUS For CT retrofitment work 09:00 17:00 152 -- PENDING OF INDIA OF INDIA Kanpur(BAY 4001080) 05-17 05-23 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION FATEHPUR-2 MAIN BAY, at 2018- 2018- 347 BAY CONTINUOUS For CT retrofitment work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Kanpur(BAY1081) 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID ICT01 BAGHPAT (400KV) CORPORATION CORPORATION AMP WORKS & its associated bays no 401 & 209 2018- 2018- 348 ICT (POWERGRID) DAILY 09:00 19:00 10 -- PENDING OF INDIA OF INDIA will be also in outage 05-07 05-07 (PGICT4000072)/500 LIMITED LIMITED POWER GRID POWER GRID ICT02 BAGHPAT (400KV) CORPORATION CORPORATION AMP WORKS & its associated bays no 410 & 211 2018- 2018- 349 ICT (POWERGRID) DAILY 09:00 19:00 10 -- PENDING OF INDIA OF INDIA will be also in outage 05-08 05-08 (PGICT4000075)/500 LIMITED LIMITED POWER GRID POWER GRID ICT01 MANESAR (400KV) CORPORATION CORPORATION 2018- 2018- 350 ICT (POWERGRID) DAILY AMP WORKS 09:00 19:00 10 -- PENDING OF INDIA OF INDIA 05-09 05-09 (PGICT4000055)/500 LIMITED LIMITED POWER GRID POWER GRID ICT02 MANESAR (400KV) CORPORATION CORPORATION 2018- 2018- 351 ICT (POWERGRID) DAILY AMP WORKS 09:00 19:00 10 -- PENDING OF INDIA OF INDIA 05-16 05-16 (PGICT4000056)/500 LIMITED LIMITED POWER GRID POWER GRID ICT04 BALLABGARH-PG (400KV) CORPORATION CORPORATION S/D required for replacement of Turret Gasket for 2018- 2018- 352 ICT (POWERGRID) CONTINUOUS 10:00 18:00 32 -- PENDING OF INDIA OF INDIA arresting Oil leakage 05-01 05-02 (PGICT4000024)/500 LIMITED LIMITED POWER GRID POWER GRID ICT03 BALLABGARH-PG (400KV) CORPORATION CORPORATION S/D required for replacement of Turret Gasket for 2018- 2018- 353 ICT (POWERGRID) DAILY 10:00 18:00 32 -- PENDING OF INDIA OF INDIA arresting Oil leakage 05-03 05-04 (PGICT4000021)/500 LIMITED LIMITED POWER GRID POWER GRID ICT02 BALLABGARH-PG (400KV) CORPORATION CORPORATION S/D required for replacement of Turret Gasket for 2018- 2018- 354 ICT (POWERGRID) CONTINUOUS 10:00 18:00 32 -- PENDING OF INDIA OF INDIA arresting Oil leakage 05-05 05-06 (PGICT4000023)/500 LIMITED LIMITED POWER GRID POWER GRID ICT01 BALLABGARH-PG (400KV) CORPORATION CORPORATION S/D required for replacement of Turret Gasket for 2018- 2018- 355 ICT (POWERGRID) CONTINUOUS 10:00 18:00 32 -- PENDING OF INDIA OF INDIA arresting Oil leakage 05-07 05-08 (PGICT4000022)/500 LIMITED LIMITED POWER GRID POWER GRID ICT01 MANDOLA (220KV) ORING REPLACEMENT WORK BY M/S EMCO TEAM ON CORPORATION CORPORATION 2018- 2018- 356 ICT (POWERGRID) CONTINUOUS ALL HV,IV,LV BUSHING, TURRETS AND OLTC 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-01 05-02 (PGICT4000051)/500 CHAMBERS LIMITED LIMITED POWER GRID POWER GRID ICT02 MANDOLA (220KV) ORING REPLACEMENT WORK BY M/S EMCO TEAM ON CORPORATION CORPORATION 2018- 2018- 357 ICT (POWERGRID) CONTINUOUS ALL HV,IV,LV BUSHING, TURRETS AND OLTC 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-03 05-04 (PGICT4000052)/500 CHAMBERS LIMITED LIMITED POWER GRID POWER GRID ICT03 MANDOLA (220KV) ORING REPLACEMENT WORK BY M/S EMCO TEAM ON CORPORATION CORPORATION 2018- 2018- 358 ICT (POWERGRID) CONTINUOUS ALL HV,IV,LV BUSHING, TURRETS AND OLTC 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-05 05-06 (PGICT4000053)/500 CHAMBERS LIMITED LIMITED POWER GRID POWER GRID ICT04 MANDOLA (220KV) ORING REPLACEMENT WORK BY M/S EMCO TEAM ON CORPORATION CORPORATION 2018- 2018- 359 ICT (POWERGRID) CONTINUOUS ALL HV,IV,LV BUSHING, TURRETS AND OLTC 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-07 05-08 (PGICT4000054)/500 CHAMBERS LIMITED LIMITED POWER GRID POWER GRID ICT01 GURGAON (400KV) CORPORATION CORPORATION Disconnector switch 401-89A modification & its 2018- 2018- 360 ICT (POWERGRID) CONTINUOUS 09:00 18:00 57 -- PENDING OF INDIA OF INDIA associated bays (401 & 206) will be also in outage 05-14 05-16 (PGICT4000029)/315 LIMITED LIMITED POWER GRID POWER GRID ICT02 GURGAON (400KV) Disconnector switch 405-89A modification & its CORPORATION CORPORATION 2018- 2018- 361 ICT (POWERGRID) CONTINUOUS associated bays (405 & 207) will be also in 09:00 18:00 57 -- PENDING OF INDIA OF INDIA 05-07 05-09 (PGICT4000030)/315 outage. LIMITED LIMITED POWER GRID POWER GRID For rectification in E/S module & installation of PD CORPORATION CORPORATION 2018- 2018- 362 ICT ICT-IV(PGICT40000152)/500MVA CONTINUOUS sensor at Gurgaon & its associated bays (411 & 09:00 18:00 57 -- PENDING OF INDIA OF INDIA 05-21 05-23 211) will be also in outage. LIMITED LIMITED POWER GRID POWER GRID ICT01 BHIWADI-PG (400KV) CORPORATION CORPORATION 2018- 2018- 363 ICT (POWERGRID) DAILY Cap and Tan delta of 33KV Bushing 09:00 11:00 2 -- PENDING OF INDIA OF INDIA 05-05 05-05 (PGICT4000016)/315 LIMITED LIMITED POWER GRID POWER GRID ICT02 BHIWADI-PG (400KV) CORPORATION CORPORATION 2018- 2018- 364 ICT (POWERGRID) DAILY Cap and Tan delta of 33KV Bushing 09:00 11:00 2 -- PENDING OF INDIA OF INDIA 05-06 05-06 (PGICT4000017)/315 LIMITED LIMITED POWER GRID POWER GRID ICT01 SIKAR (400KV) CORPORATION CORPORATION Verification of operation of new Digital RTCC panel 2018- 2018- 365 ICT (POWERGRID) DAILY 09:00 18:00 9 -- PENDING OF INDIA OF INDIA after upgradation. 05-03 05-03 (PGICT4000068)/315 LIMITED LIMITED POWER GRID POWER GRID ICT02 SIKAR (400KV) CORPORATION CORPORATION Verification of operation of new Digital RTCC panel 2018- 2018- 366 ICT (POWERGRID) DAILY 09:00 18:00 9 -- PENDING OF INDIA OF INDIA after upgradation. 05-04 05-04 (PGICT4000069)/315 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Final testing of CSD Relay of MAIN Bay of 500 MVA 2018- 2018- 367 ICT ICT-3(PGICT40000153)/500 DAILY 09:00 18:00 33 -- PENDING OF INDIA OF INDIA ICT-3 at Sikar S/s 05-07 05-08 LIMITED LIMITED POWER GRID POWER GRID S/D Required for Erection of Bus Isolator and CVT CORPORATION CORPORATION BUS-1 AT 400 KV 2018- 2018- 368 BUS CONTINUOUS in Bus-I under Series Reactor package work of M/S 10:00 18:00 104 -- PENDING OF INDIA OF INDIA BALLABHGARH(PGABS4000024) 05-15 05-19 GE LIMITED LIMITED POWER GRID POWER GRID S/D Required for Erection of Bus Isolator and CVT CORPORATION CORPORATION BUS-II AT 400 KV 2018- 2018- 369 BUS CONTINUOUS in Bus-II under Series Reactor package work of M/S 10:00 18:00 104 -- PENDING OF INDIA OF INDIA BALLABHGARH(PGABS4000025) 05-21 05-25 GE LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS-I Disconnector switch 404-89A & 403-89A 2018- 2018- 370 BUS CONTINUOUS 09:00 18:00 129 -- PENDING OF INDIA OF INDIA GURGAON(PGABS4000056) modification 05-01 05-06 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS-I Disconnector switch 405-89A & 402-89A 2018- 2018- 371 BUS CONTINUOUS 09:00 18:00 129 -- PENDING OF INDIA OF INDIA GURGAON(PGABS4000056) modification 05-07 05-12 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS-I 2018- 2018- 372 BUS CONTINUOUS Disconnector switch 401-89A modification 09:00 18:00 57 -- PENDING OF INDIA OF INDIA GURGAON(PGABS4000056) 05-14 05-16 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 2018- 2018- 373 BUS BUS-I(PGABS2200051) DAILY AMP WORK 09:00 19:00 10 -- PENDING OF INDIA OF INDIA 05-25 05-25 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 2018- 2018- 374 BUS BUS-II(PGABS2200052) DAILY AMP WORK 09:00 19:00 10 -- PENDING OF INDIA OF INDIA 05-26 05-26 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR BAGHPAT (400KV) AMP WORKS & its associated bays no 406 will be 2018- 2018- 375 REACTOR DAILY 09:00 19:00 10 -- PENDING OF INDIA OF INDIA (PGBR4000099)/80.00 also in outage. 05-09 05-09 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR MANESAR (400KV) 2018- 2018- 376 REACTOR DAILY AMP WORK 09:00 19:00 10 -- PENDING OF INDIA OF INDIA (PGBR4000041)/125.00 05-11 05-11 LIMITED LIMITED POWER GRID POWER GRID Hisar-2 L/R at bhiwadi For the installation of CORPORATION CORPORATION 2018- 2018- 377 REACTOR REACTOR(PGLR4000024)/63.00 CONTINUOUS Transformer protection system on line reactor by 09:00 18:00 249 -- PENDING OF INDIA OF INDIA 05-12 05-22 M/s Sergi India. LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION For the installation of Transformer protection 2018- 2018- 378 REACTOR REACTOR(PGLR4000025)/63.00 DAILY 09:00 19:00 10 -- PENDING OF INDIA OF INDIA system on line reactor by M/s Sergi India. 05-10 05-10 LIMITED LIMITED POWER GRID POWER GRID 400kV Future - Bus Reactor Tie CORPORATION CORPORATION Bay (408 bay) at sikar(400KV IPS tube erection between CB ,CT and isolators of 2018- 2018- 379 BAY DAILY 09:00 18:00 57 -- PENDING OF INDIA OF INDIA FUTURE - BUS REACTOR TIE BAY Future Line(400kV Bhinmal-Barmer) bay at Bus-1 05-07 05-09 LIMITED LIMITED (408 BAY) AT SIKAR) POWER GRID POWER GRID CORPORATION CORPORATION SIKAR (400KV)(POWERGRID)- 2018- 2018- 380 LINE DAILY AMP work of line 08:00 18:00 34 -- PENDING OF INDIA OF INDIA RATANGARH (400KV)(RRVPN) 1 05-05 05-06 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION BUS-I AT 400KV 2018- 2018- 381 BUS DAILY Busbar relay testing in AMP at 400 kV Sikar S/S 09:00 18:00 9 -- PENDING OF INDIA OF INDIA SIKAR(PGABS4000020) 05-10 05-10 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION BUS-I AT 400KV IPS tube erection between CB ,CT and isolators of 2018- 2018- 382 BUS DAILY 09:00 18:00 57 -- PENDING OF INDIA OF INDIA SIKAR(PGABS4000020) Future Line(400kV Bhinmal-Barmer) bay at Bus-1 05-07 05-09 LIMITED LIMITED POWER GRID POWER GRID Stringing of jack Bus & Erection of isolators and CORPORATION CORPORATION BUS-II AT 400KV 2018- 2018- 383 BUS DAILY IPS tube of Future Line(400kV Bhinmal-Barmer) bay 09:00 18:00 81 -- PENDING OF INDIA OF INDIA SIKAR(PGABS4000021) 05-11 05-14 at Bus-2 LIMITED LIMITED POWER GRID POWER GRID For Support Structure & Equipment Erection for CORPORATION CORPORATION 220KV Bus-I at 2018- 2018- 384 BUS DAILY Bay extension of ICT-III under construction. 09:00 18:00 33 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400003) 05-07 05-08 (Rescheduled from 144 OCC.) LIMITED LIMITED POWER GRID POWER GRID BHIWADI-PG (400KV) CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 385 LINE (POWERGRID)-HISSAR-PG DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA insulators 05-22 05-22 (400KV)(POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID HISSAR-PG (400KV) CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 386 LINE (POWERGRID)-BHIWANI BBMB DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA insulators 05-23 05-23 (400KV)(BBMB) LIMITED LIMITED POWER GRID POWER GRID MOGA (400KV)(POWERGRID)- CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 387 LINE HISSAR-PG (400KV) DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA insulators 05-24 05-24 (POWERGRID) 1 LIMITED LIMITED POWER GRID POWER GRID HISSAR-PG (400KV) CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 388 LINE (POWERGRID)-KAITHAL (400KV) DAILY 08:00 18:00 34 -- PENDING OF INDIA OF INDIA insulators 05-25 05-26 (POWERGRID) I LIMITED LIMITED POWER GRID POWER GRID For Support Structure & Equipment Erection for CORPORATION CORPORATION 220KV Bus-II at 2018- 2018- 389 BUS DAILY Bay extension of ICT-III under construction. 09:00 18:00 33 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400004) 05-09 05-10 (Rescheduled from 144 OCC.) LIMITED LIMITED POWER GRID POWER GRID For Quad Jack bus Erection above 220KV Bus-I,II CORPORATION CORPORATION 220KV Bus-I at 2018- 2018- 390 BUS DAILY and Transfer Bus and pipe connection for ICT-III 08:00 20:00 36 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400003) 05-15 05-16 under construction. (Rescheduled from 144 OCC.) LIMITED LIMITED POWER GRID POWER GRID For dropper connection and Bus bar stability test CORPORATION CORPORATION 220KV Bus-I at 2018- 2018- 391 BUS DAILY for ICT-III under construction. (Rescheduled from 09:00 18:00 33 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400003) 05-26 05-27 144 OCC.) LIMITED LIMITED POWER GRID POWER GRID For Quad Jack bus Erection above 220KV Bus-I,II CORPORATION CORPORATION 220KV Bus-II at 2018- 2018- 392 BUS DAILY and Transfer Bus and pipe connection for ICT-III 08:00 20:00 36 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400004) 05-15 05-16 under construction. (Rescheduled from 144 OCC.) LIMITED LIMITED (a) Replacement of porcelain insulators with POWER GRID POWER GRID ICT01 HISSAR-PG (400KV) polymer insulators. (b) 220KV side Jack bus CORPORATION CORPORATION 2018- 2018- 393 ICT (POWERGRID) DAILY conductor (of R, Y & B-PH)over the ICT-1 to be 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-28 05-29 (PGICT4000086)/315 made twin moose. At present these are single LIMITED LIMITED moose. POWER GRID POWER GRID For dropper connection and Bus bar stability test CORPORATION CORPORATION 220KV Bus-II at 2018- 2018- 394 BUS DAILY for ICT-III under construction. (Rescheduled from 09:00 18:00 33 -- PENDING OF INDIA OF INDIA Fatehabad(PGABS400004) 05-28 05-29 144 OCC.) LIMITED LIMITED PUNJAB STATE TRANSMISSION NAKODAR (400KV)(PSTCL)- 2018- 2018- 395 SLDC Punjab LINE DAILY General Maintenance 10:00 16:00 6 -- PENDING CORPORATION MAKHU (400KV)(PSTCL) 1 05-23 05-23 LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 396 BUS BUS-I HISAR(PGABS4000070) DAILY 08:00 18:00 130 -- PENDING OF INDIA OF INDIA insulators 05-21 05-26 LIMITED LIMITED PUNJAB STATE NALLAGARH (220KV) Tightening of nut bolts of jumpers, dampers , TRANSMISSION 2018- 2018- 397 SLDC Punjab LINE (POWERGRID)-MOHALI (220KV) DAILY suspension clamps and cleaning of Disc insulators 10:00 17:00 7 -- PENDING CORPORATION 05-25 05-25 (PSTCL) 2 of Tower No 40 to 50 LIMITED PUNJAB STATE TALWANDI SABOO TPS (400KV) TRANSMISSION 2018- 2018- 398 SLDC Punjab LINE (PSPCL)-DHURI (400KV)(PSTCL) DAILY Line jumper/ Nut Bolt tightening 09:00 17:00 32 -- PENDING CORPORATION 05-28 05-29 2 LIMITED POWER GRID POWER GRID CORPORATION CORPORATION REACTOR I HISSAR-PG (400KV) Replacement of porcelain insulators with polymer 2018- 2018- 399 REACTOR DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA (PGBR400003)/50.00 insulators 05-21 05-21 LIMITED LIMITED PUNJAB STATE TRANSMISSION KANGRA (132KV)(PSPCL)- Disc cleaning & Jumper tightening and other mtc. 2018- 2018- 400 SLDC Punjab LINE DAILY 10:00 16:00 6 -- PENDING CORPORATION PATHANKOT (132KV)(PSTCL) to be done 05-28 05-28 LIMITED PUNJAB STATE TRANSMISSION NAKODAR (400KV)(PSTCL)- 2018- 2018- 401 SLDC Punjab LINE DAILY General Maintenance 10:00 16:00 6 -- PENDING CORPORATION MAKHU (400KV)(PSTCL) 2 05-28 05-28 LIMITED PUNJAB STATE TRANSMISSION MOGA (400KV)(POWERGRID)- 2018- 2018- 402 SLDC Punjab LINE DAILY General Maintenance 10:00 16:00 6 -- PENDING CORPORATION NAKODAR (400KV)(PSTCL) 05-30 05-30 LIMITED PUNJAB STATE TRANSMISSION MUKTSAR (400KV)(PSTCL)- tightening/checking of jumpers and cleaning of 2018- 2018- 403 SLDC Punjab LINE DAILY 10:00 17:00 7 -- PENDING CORPORATION MAKHU (400KV)(PSTCL) 1 disc insulators in polluted area 05-31 05-31 LIMITED POWER GRID POWER GRID 400KV AGRA M/BAY 406 AT CORPORATION CORPORATION 2018- 2018- 404 BAY BASSI(400KV AGRA M/BAY 406 CONTINUOUS Retrofittment of circuit breaker AT BASSI 08:00 18:00 730 -- PENDING OF INDIA OF INDIA 05-01 05-31 AT BASSI) LIMITED LIMITED POWER GRID POWER GRID 400KV BASSI-I M/BAY 552A at CORPORATION CORPORATION Retrofittment of circuit breaker at Heerapura GSS 2018- 2018- 405 BAY HEERPURA(RAJ)(400KV BASSI-I CONTINUOUS 08:00 18:00 730 -- PENDING OF INDIA OF INDIA of RRVPNL (bay belongs to POWERGRID) 05-01 05-31 M/BAY 552A AT HEERPURA(RAJ)) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS-1 at New 2018- 2018- 406 BUS DAILY For Isolator Alignments & AMP works. 09:00 17:00 32 -- PENDING OF INDIA OF INDIA Wanpoh(PGABS4000072) 05-07 05-08 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 400KV BUS-2 at New 2018- 2018- 407 BUS DAILY For Isolator Alignments & AMP works. 09:00 17:00 32 -- PENDING OF INDIA OF INDIA Wanpoh(PGABS4000073) 05-11 05-12 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Replacement of porcelain insulators with polymer 2018- 2018- 408 BUS BUS-I HISAR(PGABS4000070) DAILY 08:00 18:00 34 -- PENDING OF INDIA OF INDIA insulators 05-28 05-29 LIMITED LIMITED PUNJAB STATE TRANSMISSION MAKHU - BUS BAR 2018- 2018- 409 SLDC Punjab BUS DAILY Perodical/routine Maintenance 09:00 18:00 9 -- PENDING CORPORATION 1(ABS4000038) 05-28 05-28 LIMITED PUNJAB STATE TRANSMISSION MAKHU - BUS BAR 2018- 2018- 410 SLDC Punjab BUS DAILY Perodical/routine Maintenance 10:00 17:00 7 -- PENDING CORPORATION 2(ABS4000039) 05-29 05-29 LIMITED PUNJAB STATE TRANSMISSION ICT01 RAJPURA (400KV)(PSTCL) 2018- 2018- 411 SLDC Punjab ICT DAILY Maintenance of ICT conservator tank 08:00 18:00 10 -- PENDING CORPORATION (ICT40000128)/500 05-23 05-23 LIMITED PUNJAB STATE TRANSMISSION ICT01 MAKHU (400KV)(PSTCL) 2018- 2018- 412 SLDC Punjab ICT DAILY Perodical/routine Maintenance 09:00 17:00 8 -- PENDING CORPORATION (ICT4000053)/315 05-14 05-14 LIMITED PUNJAB STATE TRANSMISSION ICT02 MAKHU (400KV)(PSTCL) 2018- 2018- 413 SLDC Punjab ICT DAILY Perodical/routine Maintenance 09:00 17:00 8 -- PENDING CORPORATION (ICT4000054)/315 05-15 05-15 LIMITED PUNJAB STATE TRANSMISSION ICT01 MUKTSAR (400KV)(PSTCL) 2018- 2018- 414 SLDC Punjab ICT DAILY General Maintenance 09:00 17:00 8 -- PENDING CORPORATION (ICT4000051)/315 05-01 05-01 LIMITED PUNJAB STATE TRANSMISSION ICT01 DHURI (400KV)(PSTCL) 2018- 2018- 415 SLDC Punjab ICT DAILY Protection Testing 09:00 18:00 33 -- PENDING CORPORATION (ICT4000090)/500 05-02 05-03 LIMITED PUNJAB STATE TRANSMISSION ICT03 DHURI (400KV)(PSTCL) 2018- 2018- 416 SLDC Punjab ICT DAILY General Maintenance 09:00 18:00 9 -- PENDING CORPORATION (ICT40000200)/500 05-04 05-04 LIMITED PUNJAB STATE TRANSMISSION ICT02 RAJPURA (400KV)(PSTCL) 2018- 2018- 417 SLDC Punjab ICT DAILY C-wedge clamp installation 09:00 17:00 8 -- PENDING CORPORATION (ICT40000129)/500 05-02 05-02 LIMITED PUNJAB STATE TRANSMISSION ICT02 MUKTSAR (400KV)(PSTCL) 2018- 2018- 418 SLDC Punjab ICT DAILY General Maintenance 09:00 17:00 8 -- PENDING CORPORATION (ICT4000093)/315 05-03 05-03 LIMITED POWER GRID POWER GRID PITHORAGRH (220KV) Laying of OPGW at tower no 366-367-368 to CORPORATION CORPORATION 2018- 2018- 419 LINE (POWERGRID)-BAREILY-CB GANJ DAILY interconnect Sitarganj-Tanakpur 220KV line. (now 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-01 05-02 (220KV)(UPPTCL) charged at 220KV level) LIMITED LIMITED POWER GRID POWER GRID BAREILY-PG (400KV) CORPORATION CORPORATION For creation of OPGW joint box for which OPGW to 2018- 2018- 420 LINE (POWERGRID)-KASHIPUR DAILY 08:00 18:00 58 -- PENDING OF INDIA OF INDIA be lay at tower no 268-269-270 at IIM Kashipur. 05-04 05-06 (400KV)(PTCUL) 1 LIMITED LIMITED POWER GRID POWER GRID Laying of OPGW at Tower No 16-17-18 to CORPORATION CORPORATION TANAKPUR (220KV)(NHPC)- 2018- 2018- 421 LINE DAILY interconnect Bareilly-Pithoragarh CKT-II 400 KV 08:00 18:00 34 -- PENDING OF INDIA OF INDIA SITARGANJ (220KV)(POWERGRID) 05-01 05-02 (now charged at 220KV level). LIMITED LIMITED POWER GRID POWER GRID To attend the shut down nature defects (Fixing of CORPORATION CORPORATION TANAKPUR (220KV)(NHPC)- 2018- 2018- 422 LINE DAILY Missing Jumper Bolts, Spacer Damper,cottor 08:00 18:00 34 -- PENDING OF INDIA OF INDIA SITARGANJ (220KV)(POWERGRID) 05-12 05-13 Pin,Broken Insulator Replacement etc) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus Reactor-2 , at Construction of remaining portion of Firewall 2018- 2018- 423 REACTOR DAILY 09:30 17:30 296 -- PENDING OF INDIA OF INDIA Sohawal(PGBR40000125)/80.00 between Bus Reactor-2 & ICT-1 05-05 05-17 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION 2018- 2018- 424 BAY ICT-1 BAY, at Kanpur(BAY1055) CONTINUOUS CB hydraulic mechanism overhauling work 09:00 17:00 80 -- PENDING OF INDIA OF INDIA 05-07 05-10 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus-2, at 2018- 2018- 425 BUS DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Lucknow(PGABS4000086) 05-01 05-01 LIMITED LIMITED POWER GRID POWER GRID Replacement of 400kV 80Mvar Bus Reactor with CORPORATION CORPORATION REACTOR 2018- 2018- 426 REACTOR CONTINUOUS 125Mvar Bus Reactor of BHEL make (Dismantling of 09:00 18:00 225 -- PENDING OF INDIA OF INDIA I(PGBR40000106)/80.00 05-01 05-10 80Mvar and ETC of 125 Mvar Reactor) LIMITED LIMITED POWER GRID POWER GRID REACTOR(B)-II LUCKNOW-Kursi Replacement of 400kV 80Mvar Bus Reactor with CORPORATION CORPORATION 2018- 2018- 427 REACTOR Road (400KV) CONTINUOUS 125Mvar Bus Reactor of BHEL make (Dismantling of 09:00 18:00 225 -- PENDING OF INDIA OF INDIA 05-01 05-10 PG(PGBR40000118)/125.00 80Mvar and ETC of 125 Mvar Reactor) LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION BUS-I LUCKNOW-Kursi Road 2018- 2018- 428 BUS DAILY For stringing and connection under STATCOM pkg. 09:00 18:00 9 -- PENDING OF INDIA OF INDIA (400KV) PG(PGABS400001) 05-18 05-18 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus-2, at 2018- 2018- 429 BUS DAILY For stringing and connection under STATCOM pkg. 09:00 18:00 105 -- PENDING OF INDIA OF INDIA Lucknow(PGABS4000086) 05-23 05-27 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SINGRAULI 400KV BUS - Extension of Main Bus 03 for 400 kv Singrauli - 2018- 2018- 430 BUS DAILY 09:00 18:00 9 -- PENDING OF INDIA OF INDIA III(ABS4000064) Allahabad -3 (New line ) Bay, at Singrauli (NTPC) 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SINGRAULI 400KV BUS - Extension of Main Bus 04 for 400 KV Singrauli - 2018- 2018- 431 BUS DAILY 09:00 18:00 9 -- PENDING OF INDIA OF INDIA IV(ABS4000065) Allahabad -3( New line ) Bay , at Singrauli(NTPC) 05-17 05-17 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Transfer Bus, Singrauli (NTPC) Extension of Transfer Bus for 400 KV Singrauli - 2018- 2018- 432 BUS DAILY 09:00 18:00 9 -- PENDING OF INDIA OF INDIA (PGABS4000089) Allahabad #3 (New line) Bay, at Singrauli (NTPC) 05-18 05-18 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus-2, at 2018- 2018- 433 BUS DAILY AMP of 220 KV Bus-2 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Lucknow(PGABS2200069) 05-04 05-04 LIMITED LIMITED POWER GRID POWER GRID ICT-2, 315 MVA , at Agra CORPORATION CORPORATION 2018- 2018- 434 ICT HVDC(PGICT40000154)/315 DAILY AMP works of ICT & associated bay 08:00 18:00 34 -- PENDING OF INDIA OF INDIA 05-10 05-11 MVA LIMITED LIMITED POWER GRID POWER GRID ICT-1, 3X105 MVA, at Agra CORPORATION CORPORATION 2018- 2018- 435 ICT HVDC(PGICT40000155)/315 DAILY AMP works of ICT-1 (315 MVA ) & associated bay 08:00 18:00 58 -- PENDING OF INDIA OF INDIA 05-12 05-14 MVA LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus - 1 , at Agra Tightening,Cleaning ,alignment & testing of 2018- 2018- 436 BUS DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA HVDC(PGABS2200070) Isolators & CVT connected to Bus-1 05-15 05-15 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus - 2 , at Agra Tightening,Cleaning ,alignment & testing of 2018- 2018- 437 BUS DAILY 08:00 18:00 10 -- PENDING OF INDIA OF INDIA HVDC(PGABS2200071) Isolators & CVT connected to Bus-2 05-16 05-16 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus Coupler Bay , at Agra 2018- 2018- 438 BUS DAILY AMP work of bay 08:00 18:00 10 -- PENDING OF INDIA OF INDIA HVDC(PGABS2200072) 05-17 05-17 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Transfer Bus Bay , at Agra 2018- 2018- 439 BUS DAILY AMP work of bay 08:00 18:00 10 -- PENDING OF INDIA OF INDIA HVDC(PGABS2200073) 05-18 05-18 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus-1, at Extension of 220 KV Bus-1 for Sarh-1 & Sarh 2 New 2018- 2018- 440 BUS DAILY 09:30 18:00 8 -- PENDING OF INDIA OF INDIA Fatehpur(PGABS2200074) Line of (UPPTCL) 05-01 05-01 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION Bus-2, at Extension of 220 KV Bus-2 for Sarh-1 & Sarh 2 New 2018- 2018- 441 BUS DAILY 09:30 18:00 8 -- PENDING OF INDIA OF INDIA Fatehpur(PGABS2200075) Line of (UPPTCL) 05-02 05-02 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION ICT-2 MAIN BAY, at Kanpur(MAIN 2018- 2018- 442 BAY CONTINUOUS CB hydraulic mechanism overhauling work 09:00 17:00 80 -- PENDING OF INDIA OF INDIA BAY (1058)) 05-11 05-14 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SVC-1, at 2018- 2018- 443 SVC DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Kanpur(PGSVC400003) 05-04 05-04 LIMITED LIMITED POWER GRID POWER GRID CORPORATION CORPORATION SVC-2, at 2018- 2018- 444 SVC DAILY AMP Work 09:00 17:00 8 -- PENDING OF INDIA OF INDIA Kanpur(PGSVC400004) 05-05 05-05 LIMITED LIMITED POWER GRID POWER GRID ALLAHABAD (400KV) CORPORATION CORPORATION STRINGING OF 400KV S/C SINGRAULI - ALLD LINE ON 2018- 2018- 445 LINE (POWERGRID)-KANPUR GIS DAILY 08:00 18:00 178 -- PENDING OF INDIA OF INDIA MULTI CKT PORTION 05-03 05-10 (765KV)(POWERGRID) 1 LIMITED LIMITED POWER GRID POWER GRID ALLAHABAD (400KV) CORPORATION CORPORATION STRINGING OF 400KV S/C SINGRAULI - ALLD LINE ON 2018- 2018- 446 LINE (POWERGRID)-KANPUR GIS DAILY 08:00 18:00 178 -- PENDING OF INDIA OF INDIA MULTI CKT PORTION 05-03 05-10 (765KV)(POWERGRID) 2 LIMITED LIMITED BHAKRA BEAS BHAKRA BEAS BHAKRA LEFT (220KV)(BBMB)- 2018- 2018- 447 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of S/Station equipment. 08:00 17:00 33 -- PENDING GANGUWAL (220KV)(BBMB) 1 05-07 05-08 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BHAKRA LEFT (220KV)(BBMB)- 2018- 2018- 448 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of S/station equipment. 08:00 17:00 33 -- PENDING GANGUWAL (220KV)(BBMB) 2 05-10 05-11 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BHAKRA LEFT (220KV)(BBMB)- 2018- 2018- 449 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of S/station equipment 08:00 17:00 33 -- PENDING GANGUWAL (220KV)(BBMB) 3 05-14 05-15 BOARD BOARD BHAKRA BEAS BHAKRA BEAS GANGUWAL (220KV)(BBMB)- 2018- 2018- 450 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of S/station equipment 08:00 17:00 33 -- PENDING JAGADHRI (220KV)(BBMB) 05-17 05-18 BOARD BOARD BHAKRA BEAS BHAKRA BEAS GANGUWAL (220KV)(BBMB)- 2018- 2018- 451 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of S/station equipment 08:00 17:00 33 -- PENDING GOBINDGARH (220KV)(PSTCL) 05-21 05-22 BOARD BOARD POWER GRID KANPUR GIS (765KV) CORPORATION AMP of Line Equipments and Main bay, at Kanpur 2018- 2018- 452 NRPC LINE (POWERGRID)-LUCKNOW-Kursi DAILY 09:00 17:00 8 -- PENDING OF INDIA GIS 05-03 05-03 Road (400KV) PG(POWERGRID) II LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400 kV Main Bus-I at 765 kV Connection/extension of 400 kV BUS I for new 2018- 2018- 453 BUS DAILY 09:00 20:00 11 -- PENDING Rajasthan PRASARAN GSS Anta(ABS4000074) Chhabra- Dhara LILO line . 04-24 04-24 NIGAM LIMITED RAJASTHAN SLDC RAJYA VIDYUT 400 kV Main Bus-II AT 765 kV Connection/extension of 400 kV BUS II for new 2018- 2018- 454 BUS DAILY 09:00 20:00 11 -- PENDING Rajasthan PRASARAN GSS Anta(ABS4000075) Chhabra- Dhara LILO line 04-23 04-23 NIGAM LIMITED Haryana SLDC Vidyut JHAJJAR-CLP (400KV)(CLPHR)- 2018- 2018- 455 LINE DAILY Replacement of porcelain insulators by polymer 08:00 15:00 7 -- PENDING Haryana Prasaran KABULPUR (400KV)(HVPNL) I 05-03 05-03 Nigam LTD Haryana KABULPUR (400KV)(HVPNL)- SLDC Vidyut 2018- 2018- 456 LINE DEEPALPUR (400KV)(KT JHAJJAR) DAILY Replacement of porcelain insulators by polymer 08:00 15:00 7 -- PENDING Haryana Prasaran 05-04 05-04 1 Nigam LTD Haryana KABULPUR (400KV)(HVPNL)- SLDC Vidyut 2018- 2018- 457 LINE DEEPALPUR (400KV)(KT JHAJJAR) DAILY Replacement of porcelain insulators by polymer 08:00 15:00 7 -- PENDING Haryana Prasaran 05-05 05-05 2 Nigam LTD Haryana To attend the oil leakage, mtc activities,sharp rise Power in Hydrogen Gas concentration in T/F . Note:- SLDC ICT01 KABULPUR (400KV) 2018- 2018- 458 Generation ICT CONTINUOUS shutdown already approved in 145th OCC for 09:00 17:00 224 -- PENDING Haryana (HVPNL)(ICT4000015)/315 04-20 04-29 Corporation 06.04.18 but the same will be availed during the Limited revised period mentioned above. Haryana DEEPALPUR (400KV)(KT JHAJJAR)- Replacement of porcelain insulators by polymer SLDC Vidyut 2018- 2018- 459 LINE ABDULLAPUR (400KV) DAILY Note:- Now the CLP-Dhanonda D/Ckt has been 08:00 16:00 8 -- PENDING Haryana Prasaran 04-27 04-27 (POWERGRID) revived on dated 31.03.18 Nigam LTD Haryana KABULPUR (400KV)(HVPNL)- Replacement of porcelain insulators by polymer SLDC Vidyut 2018- 2018- 460 LINE DEEPALPUR (400KV)(KT JHAJJAR) DAILY Note:- Now the CLP-Dhanonda D/Ckt has been 08:00 16:00 8 -- PENDING Haryana Prasaran 04-28 04-28 1 revived on dated 31.03.18 Nigam LTD Haryana KABULPUR (400KV)(HVPNL)- Replacement of porcelain insulators by polymer SLDC Vidyut 2018- 2018- 461 LINE DEEPALPUR (400KV)(KT JHAJJAR) DAILY Note:- Now the CLP-Dhanonda D/Ckt has been 08:00 16:00 8 -- PENDING Haryana Prasaran 04-29 04-29 2 revived on dated 31.03.18 Nigam LTD BHAKRA BEAS BHAKRA BEAS Bhatinda(PSTCL)-LEHRA 2018- 2018- 462 MANAGEMENT MANAGEMENT LINE DAILY Half yearly maintenance of line. 08:00 17:00 9 -- PENDING MOHABAT (200KV)(PSTCL) 05-07 05-07 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BHIWANI BBMB (220KV)(BBMB)- 2018- 2018- 463 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of line 08:00 17:00 9 -- PENDING BAPOORA(HVPNL) I 05-10 05-10 BOARD BOARD BHAKRA BEAS BHAKRA BEAS BHIWANI BBMB (220KV)(BBMB)- 2018- 2018- 464 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of line 08:00 17:00 9 -- PENDING BAPOORA(HVPNL) II 05-11 05-11 BOARD BOARD BHAKRA BEAS BHAKRA BEAS CHARKHI DADRI (220KV)(BBMB)- 2018- 2018- 465 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of line 08:00 17:00 9 -- PENDING LULAHIR(HVPNL) S/C 05-07 05-07 BOARD BOARD BHAKRA BEAS BHAKRA BEAS PANIPAT BBMB (220KV)(BBMB)- 2018- 2018- 466 MANAGEMENT MANAGEMENT LINE DAILY half yearly maintenance of line 08:00 17:00 9 -- PENDING CHAJJPUR(HVPNL) I 05-07 05-07 BOARD BOARD BHAKRA BEAS BHAKRA BEAS PANIPAT BBMB (220KV)(BBMB)- 2018- 2018- 467 MANAGEMENT MANAGEMENT LINE DAILY Half yearly maintenance of line. 08:00 17:00 9 -- PENDING CHAJJPUR(HVPNL) II 05-08 05-08 BOARD BOARD BHAKRA BEAS BHAKRA BEAS JALLANDHAR BBMB (220KV) 2018- 2018- 468 MANAGEMENT MANAGEMENT LINE DAILY Half yearly maintenance of substation equipment. 08:00 17:00 9 -- PENDING (BBMB)-BUTARI(PSTCL) 05-16 05-16 BOARD BOARD