0% found this document useful (0 votes)
74 views1 page

Work Breakdown Structure (WBS)

This document outlines the work breakdown structure for supplying industrial laundry machines. It breaks down the project into main phases including feasibility, plant layout, costing, construction, testing and running, and production. Within each phase are sub-tasks such as designing the plant layout, site purchasing, site building, equipment installation, testing and running the machines, packaging, and a final project termination report.

Uploaded by

Nurfarhana Jelen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views1 page

Work Breakdown Structure (WBS)

This document outlines the work breakdown structure for supplying industrial laundry machines. It breaks down the project into main phases including feasibility, plant layout, costing, construction, testing and running, and production. Within each phase are sub-tasks such as designing the plant layout, site purchasing, site building, equipment installation, testing and running the machines, packaging, and a final project termination report.

Uploaded by

Nurfarhana Jelen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

WORK BREAKDOWN STRUCTURE (WBS)

Supply Industrial
Laundry Machines

Feasibility Plant Layout Costing Construction Test & Run Production Termination

Inspection for
Market Design plant Site purchasing Site building Packaging Terminate project
measurement

Design safety of Equipment Installation set-


Process up Test & Run Labelling Final report
plant machine

Technology Construction cost