This document outlines an inspection and test plan for sewer reticulation and carrier laying works. It details 21 construction and inspection activities to be completed according to Sydney Water standards, including excavation, welding, testing of welds, installation of maintenance holes and shafts, embedment, surface fittings, surveys, and connection to the sewer system. The plan requires inspection and sign off by the constructor, water servicing coordinator, and Sydney Water representative at various hold and surveillance points to validate that construction meets specifications.

Uploaded by

fargo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
284 views2 pages

ITP LTS - v3

This document outlines an inspection and test plan for sewer reticulation and carrier laying works. It details 21 construction and inspection activities to be completed according to Sydney Water standards, including excavation, welding, testing of welds, installation of maintenance holes and shafts, embedment, surface fittings, surveys, and connection to the sewer system. The plan requires inspection and sign off by the constructor, water servicing coordinator, and Sydney Water representative at various hold and surveillance points to validate that construction meets specifications.

Uploaded by

fargo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

SYDNEY WATER

INSPECTION AND TEST PLAN - SEWER RETICULATION/ CARRIER LAYING


ALL WORKS TO BE CARRIED OUT TO SYDNEY WATER STANDARDS AND LEAK TIGHT SEWER SPECIFICATION
Developer: Water Servicing Coordinator: WSC Site Representative:
Constructor: Constructor Site Representative:
Welding Supervisor:

Case No: Sub-contractor: Witness, Hold & Surveillance points added to ITP
Works classification: Field Tester:

Works description: ITP Prepared by: Reviewed by: Sydney Water Representative:
Date / / Date / / Date / /
No Construction/Inspection Inspection Procedure & Acceptance Criteria Const- WSC** Sydney Record Comment
Activity ructor Water*
1 Prestart/Site establish Visual check. X H S Checklist
2 Approved materials on Visual check approved materials. Quantity and condition. Checklist completed. X W S Checklist
Site and delivered
3 Accredited personnel on site Check Accreditation (ensure that accreditation for welding is checked) X H S Checklist
4 Pilot Weld for each welding Visual check that pilot welds are done, Welds to be checked to WSA-01-2004-3.1 X H S Checklist
machine and each pipe size
5 Welding procedure Butt welding/Electro fusion welding to WSA-01-2004-3.1 X H S Checklist
prequalification
6 Excavation and pipe laying Visual and dimensional check to Sydney Water Standards and Leak Tight Sewer X W S Checklist
(including sidelines and IO’s) Specification. Checklist completed.
7 Welding on site Welding to be carried out to pre-approved procedure X W S Checklist
8 For Butt welding only: De- All internal weld beads to be removed for visual examination by an approved X W S Checklist
beading bead removal tool
9 Selecting Welds for testing Ensure that test welds are taken (Frequency shown in Leak Tight Sewer X H S Checklist
Specification)
10 Maintenance Holes, Visual and dimensional check to Sydney Water Standards and Leak Tight Sewer X H S Checklist
Maintenance Shafts and Specification. Checklist completed.
Terminal Maintenance Shafts.
Ensure connection to MH’s,
MS’s and TMS’s done
according to Leak Tight
Sewer Specification
11 Structural MH’s to Visual and dimensional check to Sydney Water Standards, Design plans X H S Checklist
specification – either to (structural details), DTC drawings (if applicable) and Ventshaft guidelines.
design plans or to DTC Checklist completed.
drawings
12 Ventshafts/Overflows to Visual and dimensional check to Sydney Water Standards, Design plans X H S Checklist
specifications (structural details) and Ventshaft guidelines. Checklist completed.
13 Embedment and Trench Fill Visual check and compaction testing to Sydney Water Standards X H S Checklist ,
Compaction
test results

BMIS number: ACDP0384 Version: 3 7 April 2015


Doc. Owner: Manager, Urban Growth – Land Development Page 1 of 2
SYDNEY WATER
14 Surface fittings Visual and dimension check to Sydney Water Standards X H S Checklist

15 Survey of main (curved Survey of pipe location before backfill X H S Checklist


sewers only)
16 Survey of PCS (to be done by Survey of pipe location before backfill H S S Checklist
constructor)
17 Survey of sewer in easement Survey of pipe location before backfill H H S Checklist
(if applicable)
18 WAC survey of Structures WAC survey W H S Checklist
(MH/MC/MS/TMS/RP) and
invert levels
19 Testing Pressure/vacuum (100%), deflection, compaction and infiltration testing tests to X W S Test Results
Sydney Water Standards and Leak Tight Sewer Specification. CCTV of main
sewers and PCS’s.
Testing of sample welds
20 Pre-Connection Inspection – Visual inspection to all parties standards H H H WAC. Sewer
Main Flow Management procedures as per Job Specific Schedule Letter Main
Connection
Report
21 Connection to System Visual and dimensional check to Sydney Water Standards X X W Sewer Main
Connection
Report
22 Restoration Visual inspection against photographs. Clearance letter from Council/property X W S Clearance
owner letter
23 Validation No Amendment Date Reviewed Symbol Legend
I certify that the works have been X Inspection by
constructed in accordance with
Sydney Water Standards and the H Mandatory Hold Point
Inspection and Test Plan.
W Option given to inspect
Water Servicing Coordinator
S Surveillance
Date / /
* Sydney Water Corporation reserves the right to vary these requirements at any time **Sydney Water’s written approval MUST be obtained prior to varying these requirements

BMIS number: ACDP0384 Version: 3 7 April 2015


Doc. Owner: Manager, Urban Growth – Land Development Page 2 of 2

You might also like