(05727) - Precast Concrete Technician Study Guide
(05727) - Precast Concrete Technician Study Guide
(05727) - Precast Concrete Technician Study Guide
Table of Contents:
I. GENERAL
This Standard Operating Procedure presents basic principles of a program which insures that precast/prestressed
concrete members and structural precast concrete members are produced in compliance with the Plans, approved
drawings, and specifications. The Office of Materials and Research will administer the program.
Precast/prestressed concrete members and structural precast concrete members produced under this program may be
accepted at the jobsite without additional inspection or testing, provided they arrived properly documented and
undamaged.
Precast/prestressed concrete members and structural precast concrete members that are used in Department work
shall be manufactured at a Certified Plant. Certified Plants are defined as those plants with a Department approved
quality assurance program and with an acceptable record of production of quality products. Certified plants will be
classified into one of two groups: “A” Plants or “B” Plants.
Classification A Plants are defined as those plants that have a quality control supervisor within the company
organization who supervises a Department approved quality assurance program in accordance with the procedures
outlined in this SOP.
Classification B Plants are defined as those plants which employ a testing firm or consultant to perform the
necessary quality assurance functions. The consultant in charge of quality control will be approved by the
Department and shall have the same responsibilities as the quality control supervisor for Class A Plants.
The objective of the program is to assure that only those materials that meet the Department standards are used for
Department work and that production procedures produce acceptable concrete members.
Precast/Prestressed Concrete Members and Structural Precast Concrete Members are defined as precast concrete
items for bridges and structures produced at a casting facility and transported to the project site and incorporated
into the construction work. This Standard Operating Procedure is to be used for both prestressed and non-
prestressed concrete members as it applies to each of these different precast items. Items included are
precast/pretensioned, precast/posttensioned, precast/pretensioned-post tensioned, precast bridge, and structural
precast, concrete members. The terms “precast/prestressed concrete” and “structural precast concrete” hereinafter
will be referred to as “concrete members”.
Precast/Prestressed and Structural Precast concrete producers shall submit a written application for Plant
Certification to the State Materials and Research Engineer annually. This application shall be submitted no later
than December 1 of each year in order to remain an approved source for the following year. This application shall
include the following items:
1. The company name, the plant address, and the principal officers of the company, including the plant
manager, plant engineer, production superintendent, and the quality control supervisor or consultant in
2. An outline of the producer’s quality assurance program. The program must equal the program outlined
herein and specify the sampling and acceptance testing frequencies of all materials used in production
inspections which insures, (1) stressing compliance, (2) proper tendon and reinforcement location, and (3)
dimensional tolerances.
3. A producer’s guarantee stating that all concrete members furnished for use in Georgia Department of
Transportation projects are warranted to meet the specifications. The certification to be submitted by the
producer shall contain the following or similar wording:
“The undersigned guarantees that all concrete members to be furnished by (Producer) from
(Location) for use on Department of Transportation projects in the State of Georgia have been
manufactured under strict quality control, and will meet the applicable specifications for the type of
concrete member shipped, and that all tests are performed in accordance with the latest AASHTO
Standard Methods. (Producer) agrees to have the plant and plant laboratory checked at regular
intervals by a representative of the Georgia Department of Transportation, Office of Materials and
Research. (Producer) will comply with the Georgia Department of Transportation Standard
Operating Procedures for “Quality Control and Quality Assurance of Precast/Prestressed Concrete
Members and Structural Precast Concrete Members,” Laboratory SOP-3.”
The guarantee shall be signed by a responsible officer of the company with authority to bind the company to
contract and shall be notarized.
Producers applying (or reapplying after any period of unapproved status) for certification after January 1, 2011 shall
be certified as follows:
Producers of prestressed concrete bridge beams shall be certified by the Precast / Prestressed Concrete
Institute (PCI) in Category B4 (or higher).
Producers of prestressed products other than bridge beams shall be certified by the Precast / Prestressed
Concrete Institute (PCI) in Category B2 (or higher).
Producers of precast non-prestressed shall be certified by either the Precast / Prestressed Concrete Institute
(PCI) in Category B1 (or higher) or the National Precast Concrete Association (NPCA).
Producers shall submit proof of certification as an active member in good standing with PCI or NPCA as part of the
initial application and yearly application.
The PCI or NPCA certification requirement shall not apply to producers approved prior to January 1, 2011 who
maintain continuous GDOT certification. Any period of unapproved status for any reason, either voluntary or
involuntary, will require PCI or NPCA certification as outlined above for approval.
Applicants for plant certification will schedule an initial inspection for plant approval with the Department. If the
results of the initial inspection and examination indicate an apparent ability to consistently furnish uniform concrete
members which conform to the Specifications, the plant may be certified to perform work for the Department.
The initial plant inspection shall include the approval of quality control personnel to perform the required test, and
the inspection of the producer’s laboratory and facilities. The inspection will include, but is not limited to, a review
of form condition and dimensions, pallet profile and alignment, concrete batching procedures and plant records and
stressing operation for precast/prestressed concrete plants.
A. Quality Assurance
The producer will have a Department approved quality assurance program which shall be operated under the
direct supervision of the quality control supervisor.
1. The quality control supervisor will be responsible for the following functions:
B. Casting Beds
Prior to construction of concrete members, the producer is required to submit plans of casting beds to the State
Materials and Research Engineer for review of structural stability. The proposed method and equipment for
deflected strand hold down anchorages shall be included in the precast/prestressed producer’s plan.
1. Profile and Alignment
Sufficient pallet supports shall be placed at regular intervals transverse to the longitudinal axis of the bed to
insure that the pallet remains within a grade tolerance of 1/8 inch per ten feet (3 millimeters per 3 meters)
as measured from a plane. Place additional pallet supports directly under the ends of beams if required to
maintain the grade tolerance. If wood supports are used, all supports should be of the same type (dressed or
undressed) and kind of wood. This will minimize discrepancies in the pallet profile due to unequal
compression, shrinkage, expansion, or deterioration of wood supports. After the pallet and pallet supports
are in place, a profile shall be taken along the top face of the pallet by the producer. There should be at
least one elevation taken for each ten foot (3 meter) length of pallet. Elevations shall be taken along both
edges of the pallet to reveal any transverse slope. In addition, using a straightedge of at least ten feet (3
meters) in length, verify the entire pallet is smooth and free of defects within a tolerance of 1/8 inch per ten
feet (3 millimeters per 3 meters). The final results of profiling and correction of pallet grade and
straightedge test shall produce units that meet tolerances specified herein. Profiles of a pallet grades and
straightedge tests shall be done before the first pour on any new project. For beams and SIP deck panels,
the pallet profile and straightedge test shall be done at an interval of every five pours or as needed. For
piling, the profile and straightedge test shall be done every two months or as needed. A current plot of the
pallet elevations and the results of the straightedge test of each individual bed shall be submitted to Office
of Materials and Research Plant Inspector and remain on file at the producer’s plant. Adequate provisions
shall be provided for pallet and form expansion and pallets shall be anchored to prevent lateral movement.
2. Anchorage System and Strand Location for Precast/Prestressed Concrete Members.
From the pallet profile, the elevation of the individual strands are determined and checked against the strand
template of the header assembly.
All anchorage systems shall be capable of withstanding 150 percent of the maximum design load with no
significant yielding.
E. Concrete Plant
The Batch Plant mechanical inspection should be performed by an independent scale calibration company or
may be done by the producer provided it is witnessed by the Office of Materials and Research Plant Inspector.
All batching systems for aggregates, cement, water, and admixtures as well as all mixers shall comply with
Specifications. A certification of plant mechanical acceptability issued by the calibration company shall be on
file at the plant. Provide a certified copy of all calibration certificates to the Office of Materials and Research
Plant Inspector at the time of calibration. This inspection shall be made once each four months during
construction.
The Department reserves the right to remove any producer from the Qualified Products List when the source
has not produced products for a Departmental project for a period of twelve (12) months.
1. Producers shall make a written request to the State Materials and Research Engineer requesting to be
reinstated to the approved list. The request will detail the causes and solutions to the problem areas which
caused removal from the approved list. In addition, the supplier shall state measures taken to prevent
reoccurrence of problems.
2. If, after review of the request for reinstatement, it appears the producer’s problems have been solved, an
inspection of facilities will be made and all products in stock will be inspected.
3. After examination of data gained from subparagraph 1 and 2 above, the State Materials and Research
Engineer will decide if the producer may be reinstated to the approved list. Some cases may warrant
conditional reinstatement.
B. Concrete Materials
The sampling and testing of materials must begin early enough to insure acceptability of materials. Department
inspectors will secure initial samples to verify the quality of materials as received from the sources. Plant
control sampling or testing of materials from approved sources unless noted is not required. Materials shall be
sampled and tested in accordance with the following guide:
1. Portland Cement shall be obtained from an approved source. One Independent Assurance sample per
month is to be obtained by the Office of Materials and Research Plant Inspector and sent to the Forest
Park Laboratory.
2. Fine and coarse aggregates shall be obtained from approved sources. The gradation shall be
consistent. One Independent Assurance sample per month is to be obtained by the Office of Materials
and Research Plant Inspector and sent to the nearest Office of Materials and Research Laboratory.
3. Admixtures shall be obtained from approved sources. One Independent Assurance sample per year is
to be obtained by the Office of Materials and Research Plant Inspector and sent to the Forest Park
Laboratory.
C. Steel
1. Tendons
Acceptance of prestressing steel will be made on the results of physical tests made by the Department
in addition to a required certification from the manufacturer showing results of the required test,
including stress/strain curves.
For pretensioning Steel Wire Strand, three Independent Assurance samples shall be obtained from
each heat or lot, fifty-three (53) inches (1.4 meters) in length, and transmitted to the Forest Park
Laboratory by the Office of Materials and Research Plant Inspector.
2. Reinforcement Steel Bars shall be obtained from approved sources. Two Independent Assurance
samples per size, per project, thirty (30) inches (765 millimeter) in length, are to be obtained by the
Office of Materials and Research Plant Inspector.
3. Plain Steel Diaphragm Bars, Bolts, Nuts, and Washers
The manufacturer and/or the fabricator shall furnish a certification setting forth the physical and
chemical properties of the materials and conformance to the Specifications before they may be used
in the work.
D. Bearing Devices
1. Bearing Assemblies, Plates and Hardware
The manufacturer and/or the fabricator shall furnish a certification setting forth the physical and
chemical properties of the materials and conformance to the Specifications before they may be used in
the work.
V. PRODUCTION INSPECTION
Producers shall provide the State Materials and Research Engineer with the following information
well in advance of the fabrication of members:
1. Shop drawings approved by the Office of Bridge and Structural Design for precast/prestressed
concrete members, including elongation calculations, detensioning pattern, and erection drawings. A
complete set of shop drawings bearing the original stamp from a representative of the Office of
Bridge and Structural Design shall be at the plant which is producing the product before any work may
begin.
2. Project number.
3. Location at which members are to be fabricated.
4. Probable casting date.
5. Sources of all materials to be incorporated into the members.
6. The earliest date prior to fabrication that the facilities may be inspected.
C. Placement of Forms
When the side forms have been anchored in position and after all headers have been secured, the producer’s
quality control supervisor shall make a stringline inspection of the forms. A stringline shall be blocked off a
uniform distance from one side of an inside face of the side forms. The distance between the stringline and side
of the form shall be checked at regular intervals. At each interval the width between the inside faces of the
forms shall be measured for deviations in alignment. Alignment tolerance shall be a maximum of 1/8 inch per
ten feet (3 millimeters per 3 meters) as measured from the stringline. The inside face of the forms shall be
plumb or at angles established by the Plans. All joints shall be flush with no separations. The headers shall be
in their correct and final position.
During this inspection, particular attention shall be given to any bearing or embedded plates. They shall be in
their correct position and anchored so that placement of concrete will not displace them. A final check of
strands and reinforcement shall be made to determine that proper concrete cover can be achieved.
D. Concrete Inspection
While the concrete placement operation is in progress, the producer’s Quality Control Supervisor shall be
instantly available to determine cause and remedy for any undesirable changes which occur in the mix. Each
batch of concrete shall be judged for acceptance. Uniformity of concrete is of the utmost importance in
producing uniform development of strength.
1. Sampling and Testing of Fresh Concrete
Initial samples of concrete shall be obtained for determining compliance with air content, and slump
specifications before any of the concrete is placed.
A representative sample of concrete shall then be obtained for each placement to conduct a slump test,
air content determination, and to manufacture the predetermined number of cylinders. The concrete
temperature shall be obtained immediately after sampling. Results of all tests shall be recorded
immediately after completion of the test.
The sample of concrete for the test shall be selected at random between the first delivery of concrete
and the last delivery of concrete. The cylinders shall represent the entire period of concrete placement.
A sufficient number of concrete test cylinders are necessary from each placement of concrete to insure
an adequate number of tests for determination of curing, transfer of stress, and erection or driving
strength. The exact number of test cylinders and concrete placement procedure will be established for
each operation. One set of three 28-day (56-day for HPC) strength cylinders for each day’s production
shall be made and moisture cured by the producer for product acceptance. If required, one set of two
chloride permeability cylinders shall be made and moisture cured by the producer for product
acceptance. Extra cylinders may be necessary for additional testing as required. Each set of cylinders
shall represent no more than 50 cubic yards of concrete. The acceptance cylinders shall be submitted
for test to the Office of Materials and Research or an approved independent laboratory. Independent
laboratories shall be prequalified by the Department to perform laboratory materials testing and shall
meet the requirements of the GDOT’s Manual of Guidance - Class 6.04(a) - Laboratory Materials
Testing. Testing by independent laboratories shall be done at no expense to the Department.
The producer is responsible for delivery of cylinders. The Office of Materials and Research will not
accept cylinders for testing unless they are delivered at least 7 days prior to the required testing date.
Cylinders not delivered on time shall be tested at an approved independent testing facility prequalified
by GDOT, at no expense to the Department Reports of testing at independent labs, on the laboratory’s
letterhead, shall be submitted to the Engineer.
2. Sequence of Concrete Placement
Inspections by the producer’s Quality Control Supervisor shall be performed during concrete
placement to insure that the placement procedures result in properly consolidated concrete.
a. For Beams: AASHTO Type IV beams and larger sizes shall be placed in a minimum of three lifts;
bottom flange, web, and top flange. AASHTO Type III and smaller sized beams shall be placed in
a minimum of two lifts.
b. For Piling: All solid piles may be placed in one lift. 24 inch (610 millimeter) voided piles may
also be placed in one lift. For 30 inch (765 millimeter), and 36 inch (915 millimeter) voided piles,
the forms shall be placed in a minimum of two lifts.
c. Bridge Slabs: The placement of concrete shall be performed in a manner that will keep the work
alive and free of cold joints. Precast or prestressed bridge slabs may be placed in one lift. Voided
box beams shall be placed in a minimum of two lifts. However, no layer shall exceed 24 inches
(610 millimeters).
d. Bridge Caps: Bridge caps may be placed in one lift provided the cap depth is not greater than 24
inches (610 millimeters).
e. All Other Members: All other members are to be cast as set forth in the Standard Specification or
Special Provision or Plans.
3. Curing Concrete
Special care shall be taken to prevent excessive evaporation or drying out of concrete. The surface of
the concrete throughout the curing period shall be covered with a film of free moisture. Curing mats or
curing enclosures shall completely enclose the members. There shall be no gaps or openings in the
curing mats or enclosures which allow the concrete surface to become dry. The relative humidity of
the atmospheres immediately surrounding the concrete shall be maintained at approximately 100
percent.
The producer’s method of steam curing will be reviewed to conform to Specification requirements.
E. Surface Finishes
1. Type I Finish
All concrete members shall have an acceptable and uniform Type I finish before they are shipped to
the project. The initial finish and all pointing shall be completed immediately following the removal
of forms.
2. Type III Finish
The Type III finish shall not be attempted until a satisfactory Type I finish has been obtained.
Members that require the Type III finish will be given a surface preparation at the casting yard. The
Project Contractor will notify the producer when final finish is to be applied at the casting yard to
insure compatibility with other finished areas of the structure.
F. Identification of Members
Immediately after the forms have been removed, the members shall be individually identified with an
identification number and dated by the producer. This is necessary to insure that a record will be available of
the exact location on the bed and date of placement of each member.
A. Dimensional Tolerances
Each member shall be checked for construction tolerances by the producer’s Quality Control Supervisor.
Tolerances, as referenced by the Specifications, are attached.
The limits of tolerances do not necessarily represent fully acceptable construction but are the limits at which
construction may become unacceptable. The producer shall work at a level of quality that is well within the
tolerance limits.
The producer shall document in writing the actual measurements and any required corrections on a post-pour
report. The post-pour report shall be submitted to the Office of Materials and Research Inspector and a copy
shall remain on file at the producer’s plant.
Concrete cover tests over reinforcement and prestressing steel shall be made on each member by the producer’s
Quality Control Supervisor and on randomly selected members by the Office of Materials and Research Plant
Inspector. These measurements will be made with a cover meter and may require selective storage of specific
members. The producer shall document in writing the actual measurements and any out of tolerance
measurement on a Concrete Cover Report. The Concrete Cover Report shall be submitted to the Office of
Materials and Research Inspector and a copy shall remain on file at the producer’s plant.
C. Cracks
Submit, in writing, the details of all cracks, along with the proposed repair method and materials to the Office of
Materials and Research Plant Inspector for disposition.
D. Storage of Members
Provisions for storage of units shall be in accordance with Specification requirements. Storage shall be
reinspected periodically by the producer’s Quality Control Supervisor for adverse changes in dunnage or
supports.
A. Beams
The Office of Materials and Research Plant Inspector shall receive at least 72 hours notice from the producer
prior to shipment of members. All necessary identification shall be applied to each member, all finishing and
dressing of members shall be completed, members shall be properly stored and acceptable for shipment before
the company or consulting laboratory stamp and Prestress Technician stamp is placed on the member. The
company or consulting laboratory stamp and the Prestress Technician stamp shall be on the member before the
GDOT stamp can be placed on the member by the Office of Materials and Research Plant Inspector. The
Prestress Technician stamp will be provided by the producer and shall include the Certification ID number
located on the GDOT prestress technician’s certification card.
B. Piling, Precast or Prestressed Bridge Slabs, Foot Bridges, Caps, and Other Structural Precast
Members
The Office of Materials and Research Plant Inspector shall receive at least 24 hours notice from the producer
prior to shipment of members. All necessary markings shall be applied to each member, all finishing and
dressing shall be completed, the members shall be properly stored, pick up points shall be marked on piling, by
the producer, conforming to Georgia Standard No. 3215 or the approved shop drawings and members shall be
acceptable for shipment before the company or consulting laboratory stamp and Precast Technician or Prestress
Technician stamp is placed on them. The Precast Technician stamp will be provided by the producer and shall
include the Certification ID number located on the GDOT precast technician’s certification card. The Prestress
Technician stamp will be provided by the producer and shall include the Certification ID number located on the
GDOT prestress technician’s certification card.
Precast non-prestressed concrete members shall be stamped with both the company or consulting laboratory
stamp and Precast Technician or Prestressed Technician stamp. The Precast Technician or Prestress Technician
stamp shall not be placed on any member until all required tests are completed and found to meet requirements
of all applicable specifications.
Prestressed concrete members shall be stamped with both the company or consulting laboratory stamp and
Prestressed Technician stamp. The Prestress Technician stamp shall not be placed on any member until all
required tests are completed and found to meet requirements of all applicable specifications.
VIII. SHIPPING
A. Loading
Piling shall be transported with bolster supports conforming to Georgia Standard No. 3215 or the approved shop
drawings and beams shall be transported with supports within 3 feet (1 meter) of the bearing area or as specified
on the approved shop drawings. Bolsters for loading bridge slabs and caps shall be spaced at the lifting points.
No member shall be shipped from the plant until it carries the official GDOT stamp, the approved company
stamp, the consultant laboratory stamp, the Precast Technician stamp, or Prestress Technician stamp whichever
is applicable per Section VII.
B. Project Acceptance
The Project Manager may accept all undamaged members arriving on the project preinspected and “Stamped”,
provided the members are identified on the accompanying copy of the Office of Materials and Research
shipping form. The producer shall transmit the original shipping form to the Office of Materials and Research.
The form will be reviewed, authenticated, and distributed as the acceptance document for each shipment of
members.
IX. DOCUMENTATION
A. Plant Records
The producer is required to have orderly record files maintained and readily available at the plant for inspection.
All records shall be fully accessible to the Office of Materials and Research Plant Inspectors at all times.
Copies of any records requested by the Office of Materials and Research shall be provided. These records are
as follows:
1. Maintain test results and test reports on all materials that are used in the work.
2. Maintain records of all stressing operation, pre-load, elongation, and gauge readings for precast/prestressed
concrete members.
3. Maintain records of concrete production reports.
4. Maintain accurate records of all members cast and shipped.
5. Maintain records of cover readings.
6. Maintain records of pre-pour and post-pour inspection.
7. Maintain records of bed profile and straightedge tests and any corrections made to casting beds.
8. Maintain certified calibration certificates of all stressing equipment, concrete testing equipment, and
concrete plant.
C. Project Records
The Department of Transportation area construction office must keep records for the acceptance of the members
and furnished materials.
1. The Project Manager will maintain records of all shipping reports for each shipment of members to the
project.
2. Maintain records of all acceptance documents furnished by the Office of Materials and Research.
_______________________________
Georgene M. Geary, P.E.
State Materials and Research Engineer
________________________________
Thomas B. Howell, P.E.
Director of Construction
DIMENSIONAL TOLERANCES
FOR MANUFACTURE OF
AND
DEPARTMENT OF TRANSPORTATION
STATE OF GEORGIA
OFFICE OF MATERIALS AND RESEARCH
3. Absolute Volume. The absolute volume of a material is the volume exclusive of the void
spaces between particles. It is expressed as the ratio of the loose materials weight to the
solid weight per cubic foot of the same material.
One sack of cement (94 lbs) occupies approximately one cubic foot of bulk volume, but
the absolute volume of the solid cement particles is only about 0.48 ft3.
94 lbs
0.48 ft3
195.94 lbs/ft3
Example 1: Establish the proportions for a Class “A” mix using the following materials:
Volumes
Cement 611 3.12 ft3
Sand 1168 7.17 ft3
Stone 1918 11.22 ft3
Water 33.0 gals. 4.41 ft3
Air 4% 1.08 ft3
Total Volume = 27.00 ft3
Weight
Absolute Vol.
Solid Wt./ft 3
611 lbs
Absolute Vol. Cement 3
3.12 ft3
195.94 lbs ft
Example 2: Listed below are the one cubic yard proportions for a Class A concrete mix. It has been
determined that this mix produces concrete that has excessive slump (6.0”). Reduce the water by 2.0
gallons per cubic yard and make the necessary adjustment in the sand so as to keep the same volume
of concrete. Remember, in general, one gallon of water per cubic yard will change slump
measurements approximately 1.0 inch.
Materials Proportions (lbs) Sp. Gr. Adj. Abs. Vol. (ft3) Adjusted Proportions
Cement 611 3.14 3.12 611 lbs
Sand 1155 2.63 7.09 1164 lbs
Stone 1899 2.66 11.44 1899 lbs
Water (gals) (34.0) 32.0 4.27 32.0 gals
Air 4% 1.08
611 lbs
Absolute Vol. Cement 3.12 ft 3
195.94 lbs ft 3
1899 lbs
Absolute Vol. Stone 11.44 ft 3
165.98 lbs ft 3
Adjusted Proportions
Cement 3.12 195.94 611 lbs
Sand 7.09 164.11 1164 lbs
Stone 11.44 165.98 1899 lbs
Example 3: Listed below are the proportions for a Class B concrete mix. It has been determined that
the mix will not produce workable concrete because of a lack of sand. Increase the sand by 110
pounds per cubic yard and make no changes in the cement, water, and air. Retain the same volume of
concrete which is one cubic yard.
Materials Proportions (lbs) Sp. Gr. Absolute Vol. (ft3) Adjusted Proportions
Cement 470 3.14 2.40 470 lbs
Sand 1063 2.63 7.15 1173 lbs
Stone 2075 2.66 11.83 1964 lbs
Water 34.0 gals 4.54 34.0 gals
Air 4% 1.08 4 %
Add 110 lbs to sand weight 1063 lbs 110 lbs 1173 lbs
1173 lbs
Absolute Vol. Sand 7.15 ft 3
164.11 lbs ft 3
470 lbs
Absolute Vol. Cement 2.40 ft 3
195.94 lbs ft 3
Adjusted Proportions
Stone 11.83 165.98 1964 lbs
Example 4: The one cubic yard mix proportions listed below will not produce concrete of the
desired consistency on the job. Increase the water by 1.5 gallons per yard and keep the same coarse
to fine aggregate ratio.
Materials Proportions (lbs) Sp. Gr. Absolute Vol. (ft3) Adjusted Weights
Cement 611 3.14 3.12 611 lbs
Sand 1193 2.66 7.09 1177 lbs
Stone 1894 2.71 11.10 1877 lbs
Water (gals) 33.0 gals 4.61 34.5 gals
Air 4% 1.08 4 %
1193 lbs
Sand 7.19 ft 3
165.98 lbs ft 3
1894 lbs
Stone 11.20 ft 3
169.10 lbs ft 3
7.19 ft 3
% fine aggregate to coarse 0.39 100 39 %
18.39 ft 3
611 lbs
Absolute Vol. Cement 3.12 ft 3
195.94 lbs ft 3
Adjusted Weights
Cement 3.12 195.94 611 lbs
Sand 7.09 165.98 1177 lbs
Stone 11.10 169.10 1877 lbs
Water = 34.5 gallons
Air = 4.0 %
Example 5: Listed below are the proportions for a Class A concrete mix. The contractor has elected
to use a fly ash mix with a 15% cement reduction and a 1.25 lbs. to 1.0 lb. replacement factor. Make
this adjustment and maintain the same stone, water, and air volume.
Materials Proportions (lbs) Sp. Gr. Absolute Vol. (ft3) Adjusted Weights
Cement 611 3.14 2.65 519 lbs
Fly Ash 0 2.40 0.77 115 lbs
Sand 1193 2.66 6.89 1144 lbs
Stone 1894 2.71 11.20 1894 lbs
Water (gals) 33.0 gals 4.61 33.0 gals
Air 4% 1.08 4 %
519 lbs
Absolute Vol. Cement 2.65 ft 3
195.94 lbs ft 3
115 lbs
Absolute Vol. Fly Ash 0.77 ft 3
149.76 lbs ft 3
1894 lbs
Absolute Vol. Stone 11.20 ft 3
169.10 lbs ft 3
Total Absolute Vol. of Cement, Fly Ash, Stone, Water, Air = 20.11 ft3
V. Test Procedures
The Technician Examination will also contain questions related to accepted methods of testing
fresh Portland cement concrete.