Pacing Why Hurry Up and Wait
Pacing Why Hurry Up and Wait
Pacing Why Hurry Up and Wait
Planned Completion
Pacing Delay - No
Effect on Planned
Completion
2
Employer allegations that it failed to progress1 the Works during e. The alleged pacing did not cause further delay to the
the currency of an Employer delay and, consequently, this has completion of the Works and in the event of the Employer
reduced or negated Contractor entitlement to an extension of mitigating the parent delay, the Contractor resumed baseline
time request. productivity (i.e. the pacing measures were suspended and
did not become a cause of critical delay).
Consequently, most pacing defenses are presented
retrospectively, many months or even years after the event. PACING, CONCURRENCY AND
CONCURRENT DELAY
PACING PRINCIPLES The term ‘concurrent delay’ is often used interchangeably with
Certain judicial tests have evolved across different jurisdictions to pacing, has a number of definitions and consequently, is equally
validate pacing arguments, such as: subject to misunderstanding. Below are two definitions of
concurrent delay:
a. The Employer (parent) delay event caused critical delay to the
progress and completion of the Works i.e. the parent delay ‘...a period of project overrun which is caused by two or more
caused float to occur within the paced activities. effective causes of delay which are of approximately equal
b. Evidence of knowledge, and consequently, a reaction by the causative potency.’2
Contractor in implementing pacing measures against the
parent delay. This raises the issue of knowledge or ability ‘Where the Contractor Delay to Completion occurs or has
to forecast the period of the parent delay (cause) and effect concurrently with Employer Delay to Completion……is the
consequently a reasonable assessment of the effect, to allow occurrence of two or more delay events at the same time, one an
pacing measures to be proportionate and realistic in the Employer Risk Event, the other a Contractor Risk Event, and the
circumstances. effects of which are felt at the same time’3 [emphasis added]
Contractor Baseline
1. For example, FIDIC Conditions of Contract for Construction 1999 ‘Red Book’ ‘…proceed with the Works with due expedition and without delay.’ [Sub-Clause 8.1] ‘…the Contractor
shall proceed in accordance with the programme...’ [Sub Clause 8.3]
2. ‘Concurrent Delay’ 2002 and ‘Concurrent Delay Revisited’ 2012, John Marrin QC
3. Society of Construction Law – Delay and Disruption Protocol 2002, UK
3
a. Sub-Clause 8.3 – Programme Revisions However, in discharging these obligations, as with all planning
and programming matters, the depth and quality of information
i. ‘The Contractor….shall submit a revised programme
provided will be crucial. Unfortunately, the monitoring of progress
whenever the previous programme is inconsistent with
and its effect(s), can often be focused on critical delay with the
actual progress or with the Contractor’s obligations…..
implications of non-critical or out of sequence working, which by
ii. ‘Unless the Engineer, within 21 days after receiving a
definition could include pacing, being overlooked.
programme, gives notice to the Contractor stating the
extent to which it does not comply with the Contract,
Crucially, the Contractor needs to demonstrate an intention to
the Contractor shall proceed in accordance with the
pace, in reaction to an Employer (parent) delay event and the
programme, subject to his other obligations under the
actual effect of pacing measures (i.e., the Contractor did not fall
Contract…
behind programme and consume float created by the Employer
iii. ‘…. The Engineer may require the Contractor or submit an delay event) as a consequence of delay for which it is culpable.
estimate of the anticipated effect of the future event or Put another way, is it reasonable for the Contractor to be entitled
circumstances, and / or a proposal under Sub-Clause 13.3’ to an extension of time and relief from damages absent the
[Variation Procedure]. alleged pacing measures?
b. Sub-Clause 4.21 - Progress Reports ’…monthly progress
reports shall be prepared by the Contractor and submitted to
the Engineer…….Each report shall include…list of notices given
under…Sub-Clause 20.1 [Contractor’s Claims]…… comparisons
of actual and planned progress….
4. FIDIC Conditions of Contract for Construction 1999 ‘Red Book’ [Sub-Clause 8.1 & 8.3]
5. FIDIC Conditions of Contract for Construction 1999 ‘Red Book’
4
Level 01 - 10
Level 11 - 20
Level 31 - 40
Level 41 - 50
Substructure Works
Level 01 - 10
Level 11 - 20
Level 21 - 30
Level 31 - 40
Level 41 - 50
MEP
Internal Works
Employer Delay Event
Test, Commission & Handover
Design & Manufacture - Curtain Walling
‘Gross’ Effect
(Prospective)
CASE STUDY - HOW DOES PACING WORK Notwithstanding any notice of an intention to pace, issues to
IN REALITY? consider in demonstrating pacing in this instance would include;
The following scenario is hypothetical and designed for discussion a. Employer Delay Event; what is a reasonable assessment of
and does not seek to present a definitive conclusion, but if we delay to the progress and completion of the Works? Figure 3
take the construction of a 50 floor tower and delay incurred in the illustrates the extent and duration of the Employer Delay Event.
design of the curtain walling caused by Employer changes. b. Evidence and records of the introduction of pacing measures
by the Contractor to the R.C. frame construction such that
The delay to the design of the curtain walling delayed the the period of float created by the curtain walling delay was
planned start of installation on site and consequently, the reduced or completely consumed. This may include changes
completion of the Works. In the intervening period, progress to resources such as labour, management, supervision and
to the reinforced concrete (“R.C.”) frame incurred delay to the work shift hours and working days.
extent that when the curtain walling installation commenced on
site, the Contractor had only just completed the construction of
the R.C. frame in accordance with the original planned sequence.
5
c. When would the Contractor have completed the reinforced MISTAKEN IDENTITY AND REALITY?
concrete frame construction absent the alleged pacing
After a thorough examination, it is not unusual for what would
measures? That is, what is the feasibility of the original
initially appear to be a substantial Employer delay event, to
planned intent considering issues such as;
actually be a series of discrete Employer delay events and
•• Planned and actual resources;
potentially, a series of discrete Contractor pacing actions.
•• Working calendars (holiday periods, work shift hours and
working days) Given a reasonable period to consider and implement measures,
•• Seasonal constraints; and the practical considerations of sustaining pacing measures,
pacing is more likely to be associated with medium to long
•• Month of Ramadan;
term delay events. This is true especially where the effect of the
•• Initial learning curve; and
delay can be reasonably forecast such that the Contractor can
•• Actual productivity prior to implementation of alleged implement pacing within a defined ‘window’ of time.
pacing measures.
In this instance, the Contractor has demonstrated the effect Post Employer delay event, progress may succumb to the
of the parent employer delay on the remaining critical path principles of Parkinson’s Law, ‘work expands so as to fill the
and, in particular, the float created in the previously critical time available for its completion’ (i.e., delay is incurred on
activity of the concrete frame construction, as shown in activities that have become non-critical due to the effect of the
Figure 3. The initial analysis of alleged pacing would therefore critical Employer delay, but the Contractor fails to undertake
focus on the period of the alleged parent delay together with any corrective action in the knowledge that the revised planned
the immediate succeeding and preceding periods to identify completion date is not in jeopardy, despite the delay to the non-
actual pacing measures. critical activities). This circumstance fails to meet the pacing test
because of the absence of a notice to pace and actual pacing
d. Demonstration that the alleged pacing measures did not
measures (i.e., the Contractor incurred delay in the course of
cause any further delay to the completion of the Works (i.e.,
progress caused by delay events for which it is culpable). An
did not delay the start of the curtain walling installation) as
example of this could be an unfeasible programme and/or poor
shown in Figure 4.
management and execution of the Works.
Substructure Works
Level 01 - 10
Level 11 - 20
Level 21 - 30
Level 31 - 40
Level 41 - 50
MEP
Internal Works
Planned Completion
Employer Delay Event
‘Gross’ Effect
(Prospective)
FINAL THOUGHTS ABOUT THE AUTHOR
The retrospective nature of pacing disputes highlights the need Andrew White is a Director in Navigant’s Global Construction
for the Contractor to implement and maintain good practices in Practice and is based in Doha, Qatar. He is experienced in both
project time controls throughout the currency of the works. By the preparation and defence of claims and has been appointed
doing so, this allows the effects of progress and change to be as an Expert for both Employer and Contractor organisations in
assessed, the programme revised and corrective and/or pacing delay analysis, construction methodologies, project resourcing,
actions to be implemented contemporaneously. and site logistics and has given evidence in report form and
under cross examination. Prior to his career in consulting,
For a Contractor to protect its entitlement to an extension of he spent more than 25 years working for major contractor
time absent pacing measures, the likely effect of the parent delay organisations in various roles from site engineer through projects
needs to be assessed in the first instance, allowing the Contractor director, responsible for the commercial, project management
to consider, notify and then implement pacing measures across a and planning function on projects across a variety of industry
discrete period of time and during a particular period of delay. sectors from inception and feasibility stages through tender,
construction and project handover. This includes considerable
Therefore, to end where we started, ‘Why hurry up and wait?’ experience in the management of design and construction
suggests that the Contractor is already in culpable delay and contracts and project time controls.
is effectively considering acceleration measures to achieve its
baseline plan whereas Parkinson’s Law, ‘Work expands so as to
fill the time available for its completion’ provides a more realistic
description of the circumstances and risks to the successful
demonstration of pacing.
Navigant Consulting is not a certified public accounting firm and does not provide audit, attest, or public accounting services.
See Navigant.com/Licensing for a complete listing of private investigator licenses.