YPMT OPS PR 0027 - 旁路管理程序 OverrideBypass Management Procedure
YPMT OPS PR 0027 - 旁路管理程序 OverrideBypass Management Procedure
YPMT OPS PR 0027 - 旁路管理程序 OverrideBypass Management Procedure
YPMT PM
旁路管理程序
Override/Bypass Management Procedure
文档编号:
Document Number:
YPMT-OPS-PR-0027
签字 Signature: 日期 Date:
SCP Private. © Copyright 2016 SCP, Unpublished Work. All rights reserved. This work contains the confidential and
proprietary trade secrets of SCP and may not be copied or stored in an information retrieval system, transferred, used,
distributed, translated or retransmitted in any form or by any means, electronic or mechanical, in whole or in part, without
the express written permission of the copyright owner.
Approval
签字 Signature: 日期 Date:
SCP Private. © Copyright 2016 SCP, Unpublished Work. All rights reserved. This work contains the confidential and
proprietary trade secrets of SCP and may not be copied or stored in an information retrieval system, transferred, used,
distributed, translated or retransmitted in any form or by any means, electronic or mechanical, in whole or in part, without
the express written permission of the copyright owner.
旁路管理程序 Override/Bypass Management Procedure YPMT-OPS-PR-007
版本号 日期 说明
Revision No Date Description
1.0 160913 First Issue
SCP Private
序言 Preface
本文档的主要目的是确保资产/项目设施的作业活动符合适用标准,满足安全,效率和
成本效益方面的基本要求。本文件也为设施运行提供指导,从而尽量减少健康,安全
和环境风险,符合适用法律法规。
The objective of this document is to ensure that Operation of asset/project facilities are
carried out to a satisfactory standard, recognizing the fundamental principles of safety,
efficiency and cost- effectiveness. This document also provides guidance on operation of
facilities in order to minimize Health, Safety and Environmental risks and to be in full
compliance with applicable laws and regulations.
SCP Private
third parties. Unauthorized disclosure reported as a Light accident or Near miss.
This document will be subject to annual review and update, when document holders will
have the opportunity to express opinions and suggest improvements.
同时,在文件控制系统内可进行持续更新,文档使用人可向项目发起人或文件控制专员提出任
何修改或改进建议。
However, the document control system allows for continuous update of this document. As
such, any user may at any time identify an error or suggest an improvement to the project
originator or the document controller.
Users of this document may register for automatic updates via the SPM Document
Management System.
This document is uncontrolled when printed. A controlled version of this document is stored
in the SPM Document Management System (4Projects).
SCP Private
YPMT:
Zhou Wei [email protected]
Carlos Sanitá [email protected]
Yan Zelong [email protected]
SCP Private
目录 Table of Contents
4 职责 Responsibility .................................................................................... 2
4.1 控制和自动化工程师 Control &Automation Engineer .......................................... 2
4.2 PTW 申请人 PTW Applicant ................................................................................. 2
4.3 PTW 现场批准人 Site PTW Approver .................................................................... 3
4.4 批准人 PTW Authorizer ........................................................................................ 3
SCP Private
5.1 旁路管理程序 Override/Bypass Management Procedure ..................................... 3
5.1.1 系统旁路类型 Types of System Override/Bypass 3
5.2 旁路流程 Override/Bypass Process ...................................................................... 6
5.3 超过 7 天的旁路 Override/Bypass exceeding 7 days ............................................. 7
5.4 旁 路 状 态 记 录 以 及 旁 路 检 查 确 认 Override/Bypass Status Records &
Verification of Override/Bypass ............................................................................ 8
6 培训 Training ............................................................................................. 8
7 培训 Training ............................................................................................. 9
SCP Private
部设施和设备。 它也适用于资产单位的所有生产作业和维护组员工。
This document is applicable to all facilities and equipment for the operation and
maintenance (POM) of the Y113-133 gas field. It also applies to all production operations
and maintenance team staff.
本文件的目的,就是对操作旁路和安全关键设备(SCE)旁路操作进行管理,以及安全
关键设备降级使用的管理。
SCP Private
equipment (SCE) Override/Bypass, and the management of SCE downgrade.
4 职责 Responsibility
(PTW)授权,来执行或者监督承包商执行相关工作,包括系统软件的更新、变更配
置、系统维护和控制修正。其他任何员工不得在没有系统管理员直接监督的情况下执
SCP Private
行类似工作。
动 MOC 流程。
The Override/Bypass needs the PTW. The PTW applicant is responsible for initiating
Override/Bypass request including risk assessment& mitigation measure. The PTW applicant
is also responsible for initiate the reinstatement request. For the Override/Bypass is more
than 7 days, The PTW applicant is responsible for initiating the MOC process.
The Site PTW approver is responsible for supervising implement& reinstatement the
Override/Bypass.
负责审核和授权旁路申请启动以及相应的风险评估及其控制措施。
PTW Authorizer is responsible for review and authorizes the Override/Bypass start up
including risk assessment & mitigation measure.
SCP Private
5.1 旁路管理程序 Override/Bypass Management Procedure
需要 PTW 授权并且需要风险评估使风险减小到可接受的范围内。
ESD system Override /Bypass is for operation or maintenance requirement. Such as PM, CM
for process equipment. All the Override/Bypass require PTW and should conduct risk
assessment and risk mitigation measure to reduce the risk to acceptable level.
生产运行过程中由于生产的运行的需要进行旁路。除了启动旁路其所有的旁路都需要
PTW 授权并且需要风险评估使风险减小到可接受的范围内。
PCS system Override /Bypass is for operation requirement. All the Override/Bypass except
start-up override need PTW and should conduct risk assessment and risk mitigation measure
to reduce the risk to acceptable level.
启动旁路是设备启动必须要有的, 已经默认在在操作启动程序中。启动旁路应尽快恢
复正常,最好恢复正常是自动完成。
A start-up override is a default that is identified within the operator’s start-up procedure,
which is required to enable the unit to be started. A start-up override must be removed as
soon as it is possible and it is preferred that this is done automatically.
SCP Private
如果启动旁路自动复位则不需要这个程序控制,这个已经在设计的时候审查过了。
Start-up overrides with automatic resets do not require to be controlled under this
procedure, as they have been specifically designed and reviewed during the design of the
unit and during development.
启动旁路手动复位不需要任何风险评估,但他们也需要被记录旁通记录表上。旁路操
作过程中操作员实时监控操作盘,直到启动旁路被移除.。
Start-up overrides with manual resets do not require any risk assessment but they do
require to be recorded in the override logbook. Unless the operator remains at the override
panel until the start-up override is removed.
险评估使风险减小到可接受的范围内。
In addition, there are some PM/CM or Operator intervention activities such as gas/flame
detectors testing/calibration during normal operations. PTW is required for FGS
Override/Bypass. All the Override/Bypass should conduct risk assessment and risk mitigation
measure to reduce the risk to acceptable level
报警消除系统,用于在采取了补救措施,或者等待维修工作
完成期间,临时性的抑制/消除来自故障设备的低风险、可追溯的重复性报警
多余的报警信号干扰工厂的正常运行,以及对于其它报警信号的反应和管理。所有的
SCP Private
旁路都需要 PTW 授权并且需要风险评估使风险减小到可接受的范围内。
Alarm Off is temporarily inhibit/suppress the repeated audible alarms coming from
malfunctioned devices of low risks (such as IOP alarms for over/under-range of instrument
measurement etc.) with mitigations in place or pending CM work to be carried out. The
purpose of the Alarm Off is to ensure these nuisance alarms would not adversely affect the
normal operations of the plant as well as alarm reading and treatment. All the
Override/Bypass requires PTW and should conduct risk assessment and risk mitigation
measure to reduce the risk to acceptable level.
此类安全关键设备上安防系统的旁路期间,必须有正确的授权及 PTW。所有的旁路都
需要风险评估和风险减小措施使风险在可接受的范围之内。现场安全设备旁路有可能
需要机械隔离/解除隔离准工票
SCP Private
所有需要 PTW 的旁路由 PTW 申请人申请,获得生产总监的批准授权。生产总监不在现
场时,需要通过生产总监电话批准并且记录下来。 按照下面流程图进行签署,并按照
旁路记录表进行适当的记录。
All the Override/Bypass with PTW request need raised by PTW applicant and get approval
for Production Superintendent. If the Production Superintendent is not on duty, need get
approval by telephone, and recorded. The Override/Bypass need following below process
and record as Override/Bypass list.
生产旁通Start Up
Yes
Override?
工作小于 7天结束?Work
No 启动MOC Raise MOC
completed <7days?
启动正常后恢复 No
Override must be
removed after start up Yes
No
风险评估?控制措施?
Risk assessed?Mitigation in
No
place?
Yes
复位旁通完成
reinstatement
completed?
Yes
SCP Private
5.3 超过 7 天的旁路 Override/Bypass exceeding 7 days
为了工厂安全运行,对于任何需要超过 7 天的旁路或者其它处于旁路/隔离状态下的安
经按照偏差及变更管理程序的要求。
For any Override/Bypass or any other safety system under bypass/isolation that need to be
in place for more than 7 days in order to run the plant safely, deviating from the operating
envelope, an MOC needs to be raised. This is to ensure that these Override/Bypass can be
reviewed and in accordance with MOC procedure in Operations.
和井区中空室。CPF 中控室和井区中空室操作员是这些记录表的管理员,并且有责任确
保所有的旁路都有正确的申请和批准文档.
Override/Bypass list showing the current status of all Override/Bypass in place with
authorized signatory approved must be maintained in CPF CCR & Well pad/Hub CCR. The CPF
CCR& Well pad/Hub CCR operator is the custodian for all the logs and has the responsibility
to make sure all Override/Bypass must have proper application/approval documentation
and following the Override/Bypass Process.
所有的监督,工程师和操作工都可以通过中空 PTW/旁路展示板去审查设施旁路状态。
All supervisors, engineers, operators working can review the status of all Override/Bypass on
SCP Private
the facility at the PTW/Override/Bypass display board in CCR.
在每天的操作会议中进行沟通,确保所有的旁路都已经正确记录存档,并且在交接班
过 程中进行了沟通。
All the Override/Bypasss need to be communicated in the daily operation meeting and to
make sure all Override/Bypasss are documented and communicated in the handovers
between shifts.
所有的记录需要保存至少 2 年。
6 关键指标 KPIs
procedure •
2 风险评估(%) 100%
旁路都需要风险评估
Risk Assessment(%)
All Override need risk assessment
3 超过 7 天的旁路 100%
超过 7 天的旁路需要 MOC 管理
Override/Bypass exceeding 7
Override/Bypass exceeding 7 days need MOC
days management
4 紧急旁路(#) 紧急 Override 项目数量 Number of emergency 0
Emergency Override(#) Override items.
5 所有旁路 全部都需要完整的记录在记录表上。Totally and 100%
All Override fully record in Bypass/Override Log Sheet.
7 培训 Training
所有的操作人员应该参加这个程序的培训。工艺安全工程师负责这个程序的培训。
All the operation people need to attend this training. Process Safety Engineer is responsible
to conduct this training.
SCP Private
8 评审和审计 Review and Audit
8.1 评审 Review
这个程序需要每年评审一次, 如果有变动需要更新,更新完的部分需要通知相关人员
并组织培训。
The procedure shall be reviewed every year. Any updated, the relevant person need attend
the updated information training.
8.2 审计 Audit
要求定期开展程序内部审计,采气经理负责组织相关部门代表,至少每一年对该程序
的执行情况进行内部审计。
Regular procedural internal audit shall be implemented; the Gas Production Manager shall
organize relevant department representatives to execute internal audit for performance of
this document at least once a year.
9 参考文档 References
10 附件 Appendix
SCP Private
安全系统旁路/跨越
准工票 准工票编号:
SAFETY SYSTEM BYPASS/OVERRIDE Certificate No.
CERTIFICATE
___________
SCP Private
override
日期 Date:从 From _________ 到 to ________
时间 Time 从 From _________ 到 to ________
8. 批准 Approve
批准(工作票批准人填写)Permit Authorizer
在保证安全防护措施的情况下,我授权此安全系统旁路/跨越作业可以进行。I authorize the
Bypass/ override work to be carried out, subject to the nominated safety precautions and
conditions being maintained.
SCP Private
签名 Name______日期 Date _____________
9.复原 Reinstatement
复原授权 Reinstatement Authorized by
姓名 Name ______(申请人 Applicant))
签字 Signed _____ 时间 Time _____日期 Date ______
工作许可号/准 现场批准人
工票编号: 变更管理
隔离设备 风险及措施 原因 号 复原 复原发起人
旁路描述 日期/时间 发起人 PTW 批准人 CRO 接受
PTW Site
Override/Bypass PTW No Approver
Description Date/Time Initiator Reinstatement
项 Item Tag No Risk& Mitigation Reason /Certificate No. MOC No Reinstatement Initiator
PTW Authorizer CRO Acceptance
3
Date: Date:
…………… ……………
4
Date: Date:
…………… ……………
5
Date: Date:
…………… ……………
6
Date: Date:
…………… ……………
7
Date: Date:
…………… ……………
SCP Private
8
Date: Date:
…………… ……………