Project Schedule Unit 1

This document outlines a maintenance schedule for unit #1 from November 16th to December 11th. The schedule includes 11 maintenance tasks such as inspecting and testing the generator stator, rotor, and other electrical equipment. Each task is broken down into specific activities with assigned duration and dates for completion. The overall schedule is designed to complete all planned yearly maintenance for unit #1 by December 11th.

Uploaded by

Keev Lis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views6 pages

Project Schedule Unit 1

This document outlines a maintenance schedule for unit #1 from November 16th to December 11th. The schedule includes 11 maintenance tasks such as inspecting and testing the generator stator, rotor, and other electrical equipment. Each task is broken down into specific activities with assigned duration and dates for completion. The overall schedule is designed to complete all planned yearly maintenance for unit #1 by December 11th.

Uploaded by

Keev Lis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

ID Task Name Duration Start

Nov 9, '15 Finish Nov 16, '15


T F S S M T W T F
1 Plan schedule 20 days Mon 11/16/15 Fri 12/11/15
2 Yearly maintenance 2016 unit # 1 xeset 2 20 days Mon 11/16/15 Fri 12/11/15
3 I. Generator stator 5 days Mon 11/16/15 Fri 11/20/15
4 1.1 Prepare equipment and facility 1 day Mon 11/16/15 Mon 11/16/15
5 1.2 Disconnect & remove main lead 1 day Mon 11/16/15 Mon 11/16/15
6 1.3 Disconnect & remove nuetral piont 1 day Mon 11/16/15 Mon 11/16/15
7 1.4 Visaul inspection of stator winding 1 day Mon 11/16/15 Mon 11/16/15
8 1.5 Electrical test 2 days Tue 11/17/15 Wed 11/18/15
9 1.6 Assembly & connection main lead 1 day Fri 11/20/15 Fri 11/20/15
10 II. Generator rotor 4 days Mon 11/23/15 Thu 11/26/15
11 2.1 Visaul inspection of rotor winding 1 day Mon 11/23/15 Mon 11/23/15
12 2.2 Cleanig slip ring 3 days Tue 11/24/15 Thu 11/26/15
13 2.3 Electrical test 1 day Thu 11/26/15 Thu 11/26/15
14 III. Current transformer at neutral piont 3000/1A 2 days Thu 11/19/15 Fri 11/20/15
15 3.1 Visaul inspection (bolt, nut & loosen part) 1 day Thu 11/19/15 Thu 11/19/15
16 3.2 Insulation resistance measurement 1 day Fri 11/20/15 Fri 11/20/15
17 3.3 Resistance measurement 2 days Thu 11/19/15 Fri 11/20/15
18 3.4 Ratio & polarity measurement 2 days Thu 11/19/15 Fri 11/20/15
19 3.5 Magnetization curves (CT saturation) 2 days Thu 11/19/15 Fri 11/20/15
20 IV. Current transformer at miduim switch gear 3000/1A 2 days Thu 11/26/15 Fri 11/27/15
21 4.1 Visaul inspection (bolt, nut & loosen part) 1 day Thu 11/26/15 Thu 11/26/15
22 4.2 Insulation resistance measurement 1 day Thu 11/26/15 Thu 11/26/15
23 4.3 Resistance measurement 1 day Fri 11/27/15 Fri 11/27/15
24 4.4 Ratio & polarity measurement 1 day Fri 11/27/15 Fri 11/27/15
25 4.5 Magnetization curves (CT saturation) 1 day Fri 11/27/15 Fri 11/27/15
26 V. 11kV Voltage transformer 2 days Mon 11/30/15 Tue 12/1/15
27 5.1 Isolate equipment 1 day Mon 11/30/15 Mon 11/30/15
28 5.2 Visaul inspection (bolt, nut & loosen part) 1 day Mon 11/30/15 Mon 11/30/15
29 5.3 Insulation resistance measurement 1 day Tue 12/1/15 Tue 12/1/15
30 5.4 Resistance measurement 1 day Tue 12/1/15 Tue 12/1/15
31 5.5 Ratio & polarity measurement 1 day Tue 12/1/15 Tue 12/1/15

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 1
ID Task Name Duration Start
Nov 9, '15 Finish Nov 16, '15
T F S S M T W T F
32 VI. Excitaion Power transformer (Dry type) 2 days Wed 12/2/15 Thu 12/3/15
33 6.1 Disconnect & remove main lead 1 day Wed 12/2/15 Wed 12/2/15
34 6.2 Visaul inspection (bolt, nut & loosen part) 1 day Wed 12/2/15 Wed 12/2/15
35 6.3 Insulation resistance measurement 1 day Thu 12/3/15 Thu 12/3/15
36 6.4 Resistance measuremnet 1 day Thu 12/3/15 Thu 12/3/15
37 6.5 Assembly & connection main lead 1 day Thu 12/3/15 Thu 12/3/15
38 VII. 11kV Gen Circuit breaker 1 day Fri 12/4/15 Fri 12/4/15
39 7.1 Isolate equipment 1 day Fri 12/4/15 Fri 12/4/15
40 7.2 Visaul inspection (bolt, nut & loosen part) 1 day Fri 12/4/15 Fri 12/4/15
41 7.3 Cleaning control cubicle 1 day Fri 12/4/15 Fri 12/4/15
42 7.4 Check gas SF6 pressure & operating counter 1 day Fri 12/4/15 Fri 12/4/15
43 VIII. Resistance temperature detector (RTD) 2 days Mon 12/7/15 Tue 12/8/15
44 8.1 Visaul inspection (check terminal & loosen part) 1 day Mon 12/7/15 Mon 12/7/15
45 8.2 Resistance measurement 1 day Mon 12/7/15 Mon 12/7/15
46 8.3 Re-check temperature monitoring (WX1, WX2 & WX3) 2 days Mon 12/7/15 Tue 12/8/15
47 IX. Turbine governor control system 3 days Wed 12/9/15 Fri 12/11/15
48 9.1 Visaul inspection (check terminal & loosen part) 1 day Wed 12/9/15 Wed 12/9/15
49 9.2 Cleaning control cubicle 1 day Wed 12/9/15 Wed 12/9/15
50 9.3 Check transducer of guide vane position 1 day Thu 12/10/15 Thu 12/10/15
51 9.4 Check and calibrate of pressure switches / level switches 1 day Fri 12/11/15 Fri 12/11/15
52 X. Governor oil pumps 3 days Wed 12/9/15 Fri 12/11/15
53 10.1 Visaul inspection (bolt, nut & loosen part) 1 day Wed 12/9/15 Wed 12/9/15
54 10.2 Cleaning control cubicle 1 day Wed 12/9/15 Wed 12/9/15
55 10.3 Resistance measurement 1 day Thu 12/10/15 Thu 12/10/15
56 10.4 Insulation resistance measurement 2 days Thu 12/10/15 Fri 12/11/15
57 XI. Cooling water system 3 days Mon 12/7/15 Wed 12/9/15
58 11.1 Visaul inspection (bolt, nut & loosen part) 1 day Mon 12/7/15 Mon 12/7/15
59 11.2 Cleaning control cubicle 1 day Mon 12/7/15 Mon 12/7/15
60 11.3 Check and calibrate of pressure switches / level switches / flow switches 1 day Tue 12/8/15 Tue 12/8/15
61 11.4 Resistance measurement 1 day Wed 12/9/15 Wed 12/9/15
62 11.5 Insulation resistance measurement 1 day Wed 12/9/15 Wed 12/9/15

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 2
ID Task Name Duration Start
Nov 9, '15 Finish Nov 16, '15
T F S S M T W T F
63 XII. Drainage system 3 days Wed 12/2/15 Fri 12/4/15
64 12.1 Visaul inspection (bolt, nut & loosen part) 1 day Wed 12/2/15 Wed 12/2/15
65 12.2 Cleaning control cubicle 1 day Wed 12/2/15 Wed 12/2/15
66 12.3 Check and calibrate of pressure switches / level switches 1 day Thu 12/3/15 Thu 12/3/15
67 12.4 Resistance measurement 1 day Fri 12/4/15 Fri 12/4/15
68 12.5 Insulation resistance measurement 1 day Fri 12/4/15 Fri 12/4/15
69 XIII. PLC & SCADA 5 days Mon 11/23/15 Fri 11/27/15
70 13.1 Visaul inspection (bolt, nut & loosen part) 1 day Mon 11/23/15 Mon 11/23/15
71 13.2 Cleaning control cubicle 1 day Mon 11/23/15 Mon 11/23/15
72 13.3 Check power supply 220Vac, 110Vdc & 24Vdc 1 day Tue 11/24/15 Tue 11/24/15
73 13.4 Check DI, AI & DO module 5 days Mon 11/23/15 Fri 11/27/15
74 XIV. Generator protection 2 days Thu 11/19/15 Fri 11/20/15
75 14.1 Visaul inspection (bolt, nut & loosen part) 1 day Thu 11/19/15 Thu 11/19/15
76 14.2 Cleaning control cubicle 1 day Thu 11/19/15 Thu 11/19/15
77 14.3 Check relay setting value 1 day Fri 11/20/15 Fri 11/20/15
78 XV. Main Power transformer 10 days Mon 11/23/15 Fri 12/4/15
79 15.1 Visaul inspection (bolt, nut & loosen part) 2 days Mon 11/23/15 Tue 11/24/15
80 15.2 Cleaning control cubicle, LV & HV Bushing 2 days Wed 11/25/15 Thu 11/26/15
81 15.3 Check condition of oil and winding thermormeter 1 day Thu 11/26/15 Thu 11/26/15
82 15.4 Check & tightness oil leakage 2 days Wed 11/25/15 Thu 11/26/15
83 15.5 Oil testing 3 days Mon 11/30/15 Wed 12/2/15
84 15.6 Painting fire protection 5 days Mon 11/23/15 Fri 11/27/15

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 3
Nov 23, '15 Nov 30, '15 Dec 7, '15
F S S M T W T F S S M T W T F S S M T W T F S S

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 4
Nov 23, '15 Nov 30, '15 Dec 7, '15
F S S M T W T F S S M T W T F S S M T W T F S S

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 5
Nov 23, '15 Nov 30, '15 Dec 7, '15
F S S M T W T F S S M T W T F S S M T W T F S S

Task Inactive Task Manual Summary


Split Inactive Task Start-only
Milestone Inactive Milestone Finish-only
Project: Project schedule unit 1
Summary Inactive Summary Progress
Date: Tue 3/6/18
Project Summary Manual Task Deadline
External Tasks Duration-only
External Milestone Manual Summary Rollup

Page 6