DSP Overview 10-07-2017
DSP Overview 10-07-2017
Contents:
7. Sinter Plant
8. Blast Furnace
9. SMS Complex
Rourkela Steel Plant:Sutuated in Orissa this plant was set up with a 1 million tonne per annum ingot capacity with
German assistance. Pig iron production began in the plant on 3rd February 1959. The capacity was later expended to 1.8
million tonne per annum. This was the first plant in Asia to introduce Basic Oxygen Furnace (BOF) process at a time when
this process was yet to receive recognition from the established steel producers at home and abroad. The plant produces
a wide range of flat steel products like hot and clod rolled sheets, strips and narrow plates, galvanized plain and
corrugated sheets, electrical steel sheets, tin plates and large diameters ERW and SW pipes.
After modernization in early 90s the capacity of the plants is 2 million tons of hot metal per annum, 1.9 million tonne of
liquid steel and 1.671 million tonnes of salable steel. New units for producing Cold Rolled Grain Oriented (CRGO) and Cold
Rolled Grain Not-Oriented (CRGNO) electrical sheets have come up.
Bhilai Steel Plant: This plant come up with Russian assistance in the state of Chhatisgarh. Commissioning of Blast Furnace
was done on 4th February 1959. Present capacity of the plant is 4 million tonne per annum. This plants (mainly for long
products) has huge Rail and Structural Mill, one of the biggest of its type in the world producing heavy rails to Indian and
International specification. This plant also has Wire & Rod Mill, Heavy Plates are also produced here. The plant was the
first in India to produce 3600 mm wide heavy plates. The Plate Mill, DalliMechanised Mines and Rail Mill of the plant have
ISO 14001 certification for the environment management system. All salable products of the plant have ISO certified.
Durgapur Steel Plant: This plant was built up with British assistance in West Bengal. The Plant started iron production on
26th December 1959. The plant produces Wheel and Axles mainly for Indian Railways. The other products being Light and
Medium Sections, Merchant products, Shleps, Blooms and Billets. The present capacity of the plant is 2 million tonne of
hot metal per annum. All the production units of the plant are covered by ISO 9001:2000 certification.
Bokaro Steel Plant: Situated in the coal belt of Jharkhand, this plant also was set up with Russian collaboration.
Commissioning of the first Blast Furnace was done on 2nd October 1972. Present capacity of the plant is 4 million tonne
per annum. This plant is mainly for the flat products like hot and cold rolled sheets and coils, Slit coils and galvanized
sheets. The special features of the plant is its Universal Slabbing Mill and 2000 mm continuous Hot Strip Mill, one of the
fastest of its type in the world. Some of the special steel products of the plant are SAILCOR, SAILMEDS, SAILRIM, HRNO,
SAILMA, WTCP, BSL-46 etc.
The plant, covering an area by a group of British Companies in late fifties, With an investment of Rs. 189.6 Crores
including Rs. 17.36 Crores for township development. The plant operated almost at the rated capacity during the years
1963, 1964-65 and 1965-66. The capacity was expanded to 1.6 MTPA in late sixties with an additional investment of Rs.
67.83 Crores out of which Rs. 6.31 crores was paid for the Township.
The performance of the plant after expension was much below the rated capacity which called for setting up of a number
of committees to investigate into and suggest remedial measures. The constraints as identified by almost all the
committees are as follows –
Deterioration in raw materials quality to a great extent
Aging of the Plant
Obsolete technology
High energy consumption
Later in early eighties, British Steel Corporation (a British firm), MECON(an Indian consultancy firm) and the Japanese Iron
& Steel Federation were entrusted with the job of making a developmental plan for DSP after studing the problems of the
Plant in detail.
Based on their findings SAIL decided to modernize DSP with a final Government approved definitive cost of RS. 2668
crores in 1989, which later escalated to more than 4500 crores. After modernization the present capacity of the plant is
2MTPA of hot metal.
Process Flow chart of D.S.P
Wheel
Teeming Stage Special Casting Bay
Ingots
CCP
CC Billets
and Blooms Wheels & Axles for
Wheel & Axle Railway Carriages
For
Plant Legend:
Sale
AS – Ammonium Sulphate
BOF – Basic Oxygen Furnace
CC – Continuous Cast
CCP – Continuous Casting Plant
Dolo – Dolomite
I/Ore – Iron Ore
LS – Lime Stone
LNS – Light Solvent Naptha
NLCP – New Lime Calcination
Merchant Mill MSM Section Mill
Plant
PCM – Pig Casting Machine
SGP – Slag Granulation Plant
Plain Rounds & Ribbed Angles, Channels, Joists Angles, Channels, Joists TMT – Thermo Mechanically
Rounds (TMT Bars) Treated
Coke Ovens & Coal Chemicals
Introduction: Coke Oven is an important department in an integrated steel plant. In this department, coal is carbonized
into coke which is an essential raw material for the production of hot metal in Blast Furnaces.
While carbonizing coal into coke, a number of valuable coal chemicals are obtained. These coal chemicals are also
recovered and processed in this department.
Major sections of this department are:
1. Coal Handling
2. Coke Oven Battery, Heating and Coke Handling
3. Coal Chemicals
Benzene
Toluene
Coal Coke Ovens Coal Chemicals LSN
Handling Light Oil
Plant Naphthalene
Creosote Oil
Crude Tar
Amm. Sulphate
B.F. Coke (+20 -80 mm)
Coke Handling Nut Coke (+10 -20 mm)
Plant Coke Breeze (0 -10 mm)
1. Tippling Section:
Major equipments:
Box tipplers - 3 nos
Wing Trippers - 6 nos
Stacking Beds - 12 nos
Conveyors - 10 km long (approx.)
IN CHP Prime Coking Coal (PCC) and Medium Coking Coal (MCC) are received as indigenous coal form different
washery e.g.
Patherdih - PCC
Bhojudih - PCC
Munidih - PCC
Dugdha - PCC
Mahuda - PCC
Swang - MCC
Rajarappa - MCC
Kedla - MCC
Kathara - MCC
Important coal from Australia and New Zealand is also received here. All types of PCC, MCC, Imported (New
Zealand) and Imported (Soft) are sent to stacking Beds as per stacking plan and availability and Imported (Hard) is
normally sent to earmarked Blending Silos. Layer by layer stacking in bed is done by means of Wing Tripplers.
During stacking in beds special care is taken so that best possible average coal blend is prepared; otherwise coke
quality will suffer.
2. Reclaiming Section:
Blending Silos
(14 Nos)
Cap.: 1200 T/TSilo
SRU
Primary Crusher
(4 Nos)
Service Bunkers
No of Bunkers : 4 Pneumatic Classifier
Cap: 4000 T each (4 Nos)
Secondary Crusher
(4 Nos)
Coal for BF Coke
making
+ ½ inch = nil
+ ¼ inch = 3% max
+ 1/8 inch = 10 – 14.5%
+ 36 mesh = > 70%
+ 60 mesh = > 80%
Ash = 14.5 + 0.5%
Moisture = 8%
Coal Washery
Raw coal is washed to reduce its ash content before using it for blend preparation. Raw coal received in CHP is sent to
washery after sizing it to -75 mm. According to its size fraction this coal is beneficiated through three different
procedures.Size fraction ranging -75 mm to + 0.5 mm is washed, fraction below -0.5 mm is recovered through thickener
and filter and mixed with washed coal. Different size fraction, types of corresponding washers and their capacities are
given bellow:
BATAC Jig
It is a electronically controlled pneumatic Jig, Where coal is subjected to periodic pneumatic pulse. It leads to
stratification of coal bed where heavier coal particles settle in bottom layer and lighter particles at the top. The bed can
be divided according to bed height. Hence clean coal is separated from middlings.
Spiral Washer
Slurry containing 1.4 mm to 0.5 mm coal is allowed to fall through a spiral down comer tray suitably inclined towards the
center of the spiral. Adjustable cutting knife divides the slurry into two streams, one stream containing tray peripheral
flow, and other contains tray center flow. While former contains clean coal the letter middlings
Coal is charged into the oven and is heated in absence of air to produce coke. All the volatile material is removed from
the coal as raw gas and the mass which is left behind is coke. When coke formation is complete, it is pushed out of the
oven and quenched with water.
There are four special cars. One takes coal from the service bunkers and charge in individual ovens is called Changing Car,
The second one pushes the coke out of individual oven is known as Ram/Pusher Car, the third one guides the coke during
pushing operation is known as Guide Car and the fourth one which receives the hot coke for quenching is called Hot Coke
Car, which is driven by Electric Loco. Coal tower capacity is 4000 tonnes.
Normal working pushing potential for all batteries is 96 ovens/day.
From the Hydraulic Mains both gas and liquid phase reach the Down comer where both phases become separated from each other.
Liquid phase enters into Decanter where liquor and tar gets separated. Liquor is pumped to battery again (for cooling the gas) and tar
is pumped to Tar Tank. Gas phase enters into Primary Cooler where it is cooled to 35 - 40°C. There are 12 Primary Coolers in 1.0 mt
side and 11 in expansion side.
Gas from the battery is sucked into Coal Chemicals plant by means of Exhauster. There are 3 Exhausters in each side. It maintains 130
mm Wg of suction before exhauster (for 78 ovens battery). Exhausters suck gas from battery through Hydraulic Main and Primary
Cooler and force it through Detarrer, Ammonia Absorber and Benzol Plant. Back pressure on Exhauster is not allowed to exceed 1100
mm of water column.
In the Detarrer the gas is subjected to the action of a high voltage electrical field. The gas passing through the field is ionized and the
charged tar particles collect on the surface of the grounded positive electrode. Detarrer removes more than 99% of the tar mist from
the gas. Allowable tar mist in the cleaned Coke Oven gas is less than 0.003 gm/Nm 3. There are 8 Detarrers in 1.0 mt side and 6 in the
expansion side.
From Detarrer the gas is delivered to Ammonia Absorbers. Ammonia generated from steam stripping of Ammoniacal liquor (after
caustic dosing) is mixed with the gas. The ammonia present in the gas is absorbed by spraying dilute sulphuric acid (0.8 – 1.5%) in low
acid zone and 8-10% in high acid zone). Ammonium Sulphate liquor thus generated is evaporated in calendria type evaporator;
thereafter salt is generated through Centrifuge. There are 4 Evaporators and Centrifuge. Capacity of ammonium sulphate production
is 100 T/day. Ammonia in the cleaned Coke Oven gas should not exceed 0.05 gm/m 3.
The gas leaving the Absorber at 45°C is cooled to 35-40°C in secondary Cooler cum Primary Napthalene Washer. Here a portion of the
naphthalene is removed from the gas by Wash Oil. Further naphthalene is removed from the gas by wash oil in Secondary
Naphthalene Washer. The naphthalene rich oil is system stripped in the Stripper Column. The separated naphthalene oil is mixed with
tar. The stripped lean wash oil is used again. Allowable naphthalene content in Coke Oven gas is 0.04 gm/m 3.
After removal of naphthalene the gas is further cooled to 20°C by spraying chilled water (10°C), wash oil is also cooled through spiral
plate type or shell & tube heat exchangers to 20°C. Coolent used is chilled water (10°C) The cold gas is scrubbed by cold wash oil in
Benzol Scrubber to absorb Benzol in wash oil.
The gas coming out of the Benzol Plant is clean and usable as fual. Debenzolised wash oil is used again. Wash oil consumption is ̴ 48
L.KL of crude Benzol.
Benzol Plant:
The benzolised washed oil is stripped in the column by stream and crude Benzol is collected. This crude Benzol is washed with caustic
soda and sulphuric acid in CAW (Continuous Acid Washer) plant. The washed Benzol is then fractionated in the rectification unit to
get pure products e.g. Benzene, Toluene, Heavy and Light Solvent Naphtha (LSN).
Tar Distillation:
The crude tar, which is separated earlier is distilled to get the following products:
Light Oil, Naphthalene Oil, Heavy Creosote Oil, CTPD (Crude Tar Partially Distilled).
Capacity of one unit is 125 T/Day. There are two units.
Ammonia Gas from Ammonia Still Sulphuric Acid
To our Fall # 5
To Ammunia
Recovery Unit NG Benzene
Benzol
Rectification
IG & NG Toluene
Plant
LSN
BOD Plant
Liquor and waste water of the plant is treated here before it is allowed to pass OutFall No. 5. Here all waste accumulates in
equalization tank and then it is treated with bacteria to destroy different poisons. The effluent norms are given below:
pH :6–9
NH3 : 50 mg/l
Phenol : 1 mg/l
Cyanide : 0.2 mg/l
MLSS : 100 mg/l
Raw Material Handling Plant is the starting point of the steel making process in Durgapur Steel Plant. RMHP is mainly concerned with
the receiving, loading, storing and processing of all the raw materials viz. iron ore lumps and fines, Limestone and Dolomite. The
preparation of sintermix is also done in RMHP using state of the art automation system.
There are three Wagon Tipplers (Tippler No. 3 came up later in 07.01.95) to unload the raw materials brought in rakes of wagons
from various mines. The materials are conveyed by a series of conveyors from the tippler hoppers to different yards viz. Ore yard and
Flux Yard. They are stacked in the yards at the designated beds by Stacker cum Reclaimers (Capacity 900 TPH) from where they are
reclaimed using same Stacker cum Reclaimers to intermediate surge bunkers for further transportation to customer departments like
Blast Furnace, Sinter Plant, SMS etc.
Sentermix
All Ferro Items
Dolo & I/O Lump
Sinter Plant SMS
I/ Ore Lump
Blast Furnace
All the waste generated in the plant like Ferro Scrap, Mill Scrap, Flue Dust, BOF Slag and Sinter Fines are also added in the sintermix.
These materials are received in wagons and dumpers, offloaded at the track hoppers and conveyed to the sintermix proportationing
bunkers. These materials are used in a ratio based on the final sinter chemistry requirement e.g.
The sinter mix is then sent to Sinter Plant for preparation of Sinter.
The Iron Ore fines are reclaimed from the Ore yard by Stacker cum reclaimers and conveyed to the sintermix proportioning bunkers.
Based on the analysis of these raw materials the rate at which these materials are to be drawn from the bunkers are fixed. There are
weigh feeders below the bunkers which control the rate of feeding the materials.
All the materials are simultaneously withdrawn from the bunkers at the pre determined rate on a common conveyer and stacked on
the sintermix beds in sintermix yard by slewable stacker of capacity 900 TPH. It is reclaimed from the beds by Blender Reclaimer or
Barrel Reclaimer (900TPH) and conveyed to the Sinter Plant.
Material dispatch to Customer Departments
Blast Furnace
There are two screens of capacity 300 TPH in Ore yard for screening the Iron Ore lumps. Screened Iron Ore lumps are stacked on 4
beds in Lump Ore yard using wing Trippers. It is conveyed to Blast Furnace highline after reclaiming from the beds using one of the 5
scrapper reclaimers of capacity 450 TPH each.
Sinter Plant
Sintermix is reclaimed by scrapper reclaimers from the beds in Old Sinter Plant and conveyed to Sinter Plant I. Blender reclaimer or
Barrel Reclaimer is used to reclaim sintermix from sintermix yard and conveyed to Sinter Plant II. There is also a route for sending
limestone fines, dolomite fines and coke fines separately for final trimming addition at the Sinter Plants to compensate for any
variation in sinter quality.
Pollution Control
There are 2 dust suppression systems at Flux and Coke Crushing Unit for pollution control.
Sinter Plant
Sintering as applied to steel industries can be defined as agglomeration of iron bearing fines, as a suitable feed to the Blast furnace by
incipient fusion within the mass, effected by burning coke fines in the prepared burden on a moving grate by draughting of air from
top to bottom. Sintering is carried out by putting mix of iron ore fines, Lime stone, Dolomite fines and Coke fines on a moving grate
machine. Top layer is ignited in the ignition furnace and air is drawn downwards through exhauster. The cold blast drawn through the
bed cools the already sintered layer (at temp. between 1000 –1200 0 C) and thereby gets it self heated. This heat is utilized to burn
the coke in subsequent layers. Due to burning of the coke particles bonding takes place between the grains and a strong and porous
aggregate is formed known as ‘SINTER’. This sintering process is over when bottom layer coke fine burning is completed. The sinter
cake is then crushed and screened and dispatched to Blast Furnace
At the beginning (i.e. under 1.0 MTPA capacity) DSP did not have any Sinter Plant. Two sintering machines were installed with a
capacity of 2500 TPD each during 1.6 MTPA expansion of DSP in 1968. Then the target was to use 40% sinter in Blast Furnace. Later
During modernization of DSP to 1.876 MTPA capacity another sintering machine with a capacity of 5184 TPD was installed in 1995,
making a total installed capacity of 10,184 TPD of sinter. Now the target of sinter in Blast Furnace burden is 75%.
Plant Data
The approximate weights of raw materials required for making one tone of sinter are:
A Layer of previous sintered material called the Hearth Layer is first spread on the Grate Bars, over which the green mix is spread. A
cut off plate adjusts the height of the bed and material is ignited under a set of burners (temperature reaching 1200°C). The machine
is kept moving and suction is applied from the bottom of the bed. The heat travels down the bed and sintering continues. By the time
the material reaches the discharge end, the whole mass is sintered.
The sinter passes through a Sinter Breaker, Hot Sinter Screen, Sinter Cooler and Cold Sinter Screens. The various fractions utilized are
as follows:
For Blast Furnace +25 mm and +6 to -16 mm
For Hearth Layer +16 to -25 mm
Return Fines -6 mm (Re-circulated in Sinter Plant itself)
Return Fines -6 mm (From Blast Furnace to RMHP bed)
There is however slight difference between the SP-1 and SP-2as far as fractional sizes are concerned. Return fines are used for
calculating the load.
Return Fines -
6 mm +10 mm to -20 mm for hearth layer
2 0.8 1.2
Productivity (T/M /Hr)
2 143 180
Area of the Machine (M )
I/ Ore Lump
Sinter Coke
Slag
PCM
SMS
The raw materials are charged into the furnace from top in the required proportions and preheated air from stoves in blown through
a number of symmetrically located openings in the bosh region of the furnace known as Tuyeres. The reducing gases rise up through
the descending burden. The descending raw materials travelling through various temperature zones are heated up and thus get
smelted. The liquid iron and liquid slag formed thus trickles down and accumulates in the hearth which is the bottom most part of the
furnace. The slag separates and floats above liquid metal. Slag is lighter as compared to metal. Whereas the raw materials take about
10-12 hours to descend and get smelted, the ascending gases take a few seconds only to rise through the descending column. This
gas is called BF gas and has high calorific value and is used as fuel at many places inside the plant. Before using this gas as fuel this has
to be cleaned and for this purpose a Gas Cleaning Plant is also located near the Blast Furnace area. The cleaned gas is sent to units
such as Coke Ovens, BF Stoves, Sinter Plant, Soaking Pits and Reheating Furnaces of mills.
This is sent to gas washers. The gas is counter currently washed with water. The gas leaving the washers has a dust content of about
0.5 gm / M3 and then enters a set of Electrostatic Precipitators. The gas leaving the precipitators has a dust content of about 9 – 11
mg / M3.
The dust laden water coming out of the gas washer and electrostatic precipitator is taken to Dor Clarifiers, cooled and re-
circulated. The slurry is taken to slag bank.
Number of precipitators 12
Number of Dorr thickeners 6
Number of washers 8
Blast Furnace
Secondary Dust
Catcher
Washer
ESP
Parameters BF # 2 & 3 BF # 4
Blast Temperature (°C) 1100 1150
Blast Moisture (%) 4 to 8 5 to 10
Blast Pr. at Bustle main (Kg/cm2) 1.7 1.8 to 2
High Top Pressure (Kg/cm2) 0.7 0.7
Theoretical Flame Temperature (°C) 1950 – 2050 1950 – 2050
Sinter charges in burden (%) 75 75
Hot Metal composition
Silicon (%) 0.8 0.6
Sulphur (%) 0.04 (max) 0.04 (max)
Manganese 0.15 0.15
Slag composition:
AL2O3 (%) 21-24 21-24
MgO (%) 8-11 8-11
CaO /SiO (%) 0.95 – 0.98 0.95 – 0.98
Main daily production (Tonne) 1820 2340
Overall Plant production 2.088 MTPA
Furnace productivity 1.3 1.3
Burden composition
(Kg/Tonne of Gross Hot metal)
Flux Skip Sinter 1260 1260
Lump Iron Ore 427 427
Coke Dry Skip 550 530
Yield / Tonne of Hot metal
Slag (Kg) 380 380
Top Gas (NM3) 2080 2080
Number of Cast / day / Fce 9 – 10 9 – 10
Number of Tuyeres 18 20
Number of Tap Holes 2 2
Hearth Diameter (mm) 8600 9400
Top Diameter (mm) 6600 6900
Useful Volume above Big Bell (M3) 45.0 45.0
Big Bell Diameter (mm) 4900 5000
Big Bell Stroke (mm) 750 750
Useful Vol of Receiving Hopper (M3) 8.0 10.0
Small Bell Stroke (mm) 900 900
Skip Winch Lifting capacity (T) 19 25
Number of Stoves per furnace 3 3
Blast Volume (NM3 / Hr) 125000 – 130000 140000 – 160000
Dome Temperature (°C) 1250 1250
Waste Gas Temp max (°C) 400 400
Stove Height (M) 45 45
Stove Efficiency (%) 77.85 77.85
Gas Period (minutes) 110 110
Blast Period (minutes) 60 60
Blast furnace # 3 has been provided with Bell less top (BLT) charging system in place of double bell system in
2014.
The slag contains CaO which is used for Cement Manufacturing. This slag is sold outside. Granulated slag fetches better price. There
are two Slag Granulation Plants (SGP) for BF # 3 and # 4. These are modernized furnaces with latest technology.
Rated Output
Average Rate 2 to 5 T / Min
Maximum Rate 10 T / Min
Glassy Phase Greater than 90 %
Moisture content of Granulated Slag 10 % average
Size range of Granulated Slag 0 – 3 mm
SMS Complex
* Steel making by Basic Oxygen process or LD process was first used successfully in a place called Linz in Austria in 1952. Next year it
was used at another place called Donawitz also in Astria. From the names of these places (Linz & Donawitz) came the term LD
process. This is a very fast process of steel making. In this process hot metal and scrap is taken in a vessel called Converter. Then
Oxygen is blown at high pressure through the molten metal in converter thereby converting it into steel very quickly. Whereas the
conventional open hearth process takes about 6 – 8 hours to complete the process of steel making, this LD process takes just under
one hour for the same.
Basic Oxygen Furnace (BOF) was added under modernization of DSP. This has a installed capacity of 1.876 MTPA (Million Tonnes Per
Annum) of liquid steel. The shop incorporates all environment protection measures.
Terget activity – To convert hot metal (liquid iron) as received from Blast Furnace into liquid steel. This is done by taking the hot metal
into a vessel called Converter and intense blowing of oxygen through the metal. The liquid steel thus produced is then sent to
secondary refining units like Ladle Furnaces (LRF) / Vacuum arc degassing (VAD) unit for further refining . Refined steel from LRF then
directly cast into Billet / Bloom in CCP . Refined and degassed steel from VAD either cast into bottom pouring ingot moulds for making
ingots for wheel & Axle plant / ASP or directly cast into rounds in Bloom Cum Round caster (BRC) . Rounds from BRC also feed to W &
A Plant for making wheel.
Hot metal which comes out from Blast Furnaces is collected in ladles and poured into the Mixers. There are two inactive Mixers of
1300 T capacity each. These Mixers serve the purpose of storing as well as homogenizing the temperature and composition of the hot
metal. Coke Oven gas is used to maintain the temperature at 1320° C (this is the design value, present reference value being 1260°C).
Normal composition range of Hot Metal obtained from Blast Furnace is as follows:
C Si Mn S P
3.8 – 4.2 % 0.8 – 0.9 % 0.1 – 0.2 % 0.045 – 0.060 % 0.18 – 0.25 %
The converters are commission by Mannessmann Demag of Germany. The first converter was commissioned on 07.06.94, second on
11.09.94 and the third on 21.02.95
The quality of various raw materials for producing one tonne of steel are as follows:
There are three converters for steel making in this shop. Each converter has capacity of 110 – 130 T per heat and the average life of a
converter is around 4510 heats(2016 – 17 data). The converter has a tap hole for tapping the slag and steel. Each converter has its
own Lance systems. Lance is used in the converter for blowing oxygen at high pressure so as to form an emulsion on the surface of
metal which increases the surface area to such an extent that the separation of impurities takes place very fast, thus giving this
process a unique distinction i.e. a very fast process for steel making. There are two lances for each converter and these lances are
operated by separate lance carriages. The oxygen blowing rate through the lance is 450 - 650 NM3/min and the blowing pressure is
12.0 to 15.0 bar from top.
BOF shop with 3 Basic Oxygen Furnace (BOF) Converters of capacity 110 – 130 tonne each for steel making by LD process. Converter
tap to tap time is 57 minutes. Installed capacity of the units are as follows.
BOF Gas
Total 57 min
Gas obtained from BOF converter has a calorific value of 2100 Kcal / NM3. At the rate of 80 NM3/T. The slag obtained is around 142
Kg per tonne of crude steel (2016 – 17 data) , dust content is 2% of tap weight.
Oxygen
Oxygen Lance
Tap Hole
Converter Shell
Detechable Bottom
Bottom Blowing Argon Gas
Arrangement
intermediate step of soaking and rolling in Blooming and Billet Mill is bypassed. Furthermore, from 100 tonnes of molten steel, in
traditional route, one gets only 85-86 tonnes of billets, whereas by continuous casting route, as much as 95 to 98 tonnes can be
obtained.
The first machine was commissioned on 09.07.94 and the second one on 09.08.94. The mould is kept oscillating at 80 to 150 per
minute. The lubricating oil used is Rapeseed oil. The minimum temperature at LTS is 1600°C (LTS – Ladle Treatment Station).
He purpose of ladle treatment is to homogenize the temperature and composition, flotation of non-metallic inclusion, removal of
dissolved gases and to facilitate active slag-metal reactions.
The dummy bar is inserted in the mould upto 100 mm (out of 800 mm length of mould from lower to upper side) of the mould with
the help of pinch rolls. The dummy bar is packed by 6 mm asbestos rope and a chiller is placed to chill the first metal to reach mould.
The mould is surrounded by 4 mm water jackets through which primary water (40°C) is circulated internally. Primary cooli8ng of the
mould is thus done during casting by demineralised water. Besides, other zones, i.e. multistage of mould zone 1, zone 2A and zone 2B
are kept cooled by industrial water which is termed as secondary cooling.
The billets thus formed are cut to proper lengths and are allowed to cool in air, then non-destructive testing is done and then packed
and sent to stock yards according to their quality and size.
In the year 2007 – 2008 one Bloom caster and two nos. of Secondary Refining Unit ( LRF 1 & LRF 2) installed in SMS to met the
increasing demand of production with improved quality. In 2 nd phase modernization another secondary Refining Unit ( LRF 3 ) and
Bloom Cum Round caster ( BRC ) has been added in SMS / DSP . All the added units having highly online process automation system.
As the name suggest this plant came up later in 94-95 during modernization of DSP. Previously there was a Lime Plant with two Kilns.
This new plant came up to cater to the needs of BOF shop. The plant was three Annular Shaft type lime Kilns of 300 TPD capacity each
along with limestone and lime handling facilities. Annular Shaft Kilns of Warmestelle design in the first of its kind in any Indian steel
plant.
The main function of this plant is to produce lime from naturally available limestone. Lime is required in steel making process (in BOF)
mainly to reduce the Sulphur and Phosphorus content of the steel. Present calcined lime consumption rate of BOF is about 81 Kg /
TCS. Calcination is a process of controlled heating of limestone to convert it to lime. Presently lime stone from Jaisalmer in Rajastan is
being brought to use as the input material for the plant. Current yield of the plant is 60%.
Weighing Hopper
Rotating Charging
Intermediate Lime Stone
Sklp Hopper Cone
Chute
Exhaust Gas
Coke Oven Gas as Fuel Lower Firing Blower
(LCC) Zone
Lime
Discharging
Device
SILO
Double Sluice
Lock System
-10 mm Lime
Legend:
L/S – Lime Stone
Briquetting Machine LCC – Lower Combustion Chamber
UCC – Upper Combustion Chamber
-15 mm Briquette SMS – Steel Melting Shop
Re-heating
The blooms are heated in two furnaces before being rolled. The two continuous reheating furnace are of the end-charge
end discharge type, divided into zones. There are in all eleven burners in each furnace; four in the end wall at discharge
end to from the soaking zone, four in the roof and three below the hearth level to from the heating zone. Coke oven gas
mixed with Blast Furnace gas is used to heat the blooms is about 1250°C. To improve the efficiency of the furnace,
incoming cold combustion air is preheated by hot flue gases in metallic recuperator. Blooms are discharge from each
furnace on to the delivery table.
Straightening Machine
The structural’s need straightening before dispatch since the bar get bent and camber during cooling. Three cold
straightening machines are installed for this purpose. Each piece is passed through the machines. In the first two
machines there are 3 rolls on the top and 4 rolls in the bottom; the bottom rolls are driven by a motor of 165 HP while
the top rolls are friction driven. The third machine is driven by two KW Slip Ring Induction motors; it has four top rolls and
three bottom rolls.
The products before dispatch are inspected and tested for chemical analysis as well as physical strength such as Tensile
strength etc.
Despatch
After straightening the bars are stacked by overhead cranes. From there they are loaded in wagons carefully by over head
cranes for despatching to stock yards to outside parties.
Finishing Mill Main Motor Room Pusher 2 Pusher 2
Motor Room
1000 HP DC
Motor 3000HP 2500HP
Furnace 2 Furnace 1
40 TPH 40 TPH Bloom
Pinion Housing Pinion Housing
Stock Bay
24” 3 High
Roller Table
Intermediate
Mill Stand # 1
Pinion Housing 26” 2 High
Roughing Mill
Hot Saws Stand
3 2 1
Roller Table
Overview
The Medium Structural Mill (1 MTPA) is one of the main production units of the Phase-I
expansion program of Durgapur Steel Plant (DSP), SAIL set up in their existing plant at Durgapur,
West Bengal, India.
The layout of the rolling mill is based on providing an efficient operating facility with particular
attention given to the flow of material commencing at bloom arrival through to the final delivery
of finished product bundles area.
The mill design makes the maximum use of automation and the progress of each bar is
monitored throughout the heating, rolling, cooling and handling processes providing production
data to the operators and management in a timely and precise manner so that the complete
facility can function smoothly.
• MSM with universal rolling facility can produce universal beams (100mm-300 mm) and also
conventional structural like channels (100mm-300 mm), equal angles (90mm to 200mm),
rounded corner square (RCS) (60mm – 120 mm) and rounds (60mm – 120 mm) in the
desired length.
• MSM is a continuous tandem mill comprising of 16 stands (6 roughing and 10 Finishing), with
maximum mill speed of 6-7 m/sec. The stand configuration comprises of vertical rolls,
horizontal rolls and universal rolls.
• Optimum setting of roll gap upon changing rolling programme.Ability to easily compensate
the varying lateral spread and shrinkage behavior of different steel grades is unique feature
of MSM.
• Universal rolls usage gives better dimensional control and surface finish.
• Pre-setting system of the mill.The basic principal of the Pre-Setting system is to maximize
the profitability of a rolling mill by reducing the idle time due to stand and pass changing and
by achieving quickly a good quality saleable production. This is achieved by Pre-Setting both
rolls and guide equipment "Off-Line" prior to the "change" stand being placed in the mill
ready for rolling. Parallel flange beams can be rolled.
• The mail mill is at +5m level. This ensures better utilization of basement area at 0m level and
ease of material handling in case of input blooms and finished products.
• Input Bloom sizes of 350x240 and 300x150 with length varying from 6m to 12m
Reheating Furnace of MSM
• The reheating furnace of MSM is of 220 TPH, walking beam type furnace, with fuel type
MIXED GAS (BF + CBM) OR (BF + LPG).
• The furnace is an eight (8) zone walking beam furnace. It is fired with six (6) burners in the
top preheat zone; six (6) burners in the bottom preheat zone; six (6) burners in the top heat
zone; six (6) burners in the bottom heat zone; four (4) burners in the south bottom soak
zone; five (5) burners in the north bottom soak zone; twelve (12) roof burners in the south
top soak zone; and twelve (12) roof burners in the north top soak zone. There are a total of
57 burners.
• The furnace is designed for end charging and discharging by machine and is capable of
handling full length product up to 12m long.
Merchant Mill
Merchant Mill was commissioned in the year 1961 with an installed capacity of 240,000 TPA (Tonnes
per Annum). It was modernized in 1992 to have a capacity of 280,000 TPA of plain rounds and
Thermo Mechanically Treated (TMT) ribbed bars. The products of Merchant Mill are plain rounds
and TMT ribbed bars of size 16, 20 & 25 mm. Now, however, Merchant Mill is rolling only TMT bars
of section 16 , 20 , 25 mm.
Billets of 100 mm2 and 9 mtr. long from CCP are stacked quality wise in the billets stock yard. They
are then transferred by cranes to a Charging bed & & then by separating skid mechanism consists of
stationary and power operated carry-over skids arranged to produce a cascade effect which
separates and depiles the billets and places them on the furnace charging roller table. A hydraulically
operated billet turnover and discard device is provide to enable defective billets to be rejected into
adjacent bins and turning the billet faces as per requirement. A Ram charger pushes the billets from
Roller table into the furnace. Billets placed in the furnace are pushed across the hearth by means of
an electrically driven Cross Pusher mounted independently outside the furnace.
The reheating furnace is a two-zone type arranged for side charging and discharging. It is designed
for an output of 70 TPH. The fuel is mixed gas of CV 3000 Kcal./m3. The air for combustion is
preheated in metallic recuperator.
Billets discharged from the furnace are delivered to the first mill stand by push-out bar. A pair of
pinch rolls is located adjacent to the furnace discharge side to pull out and feed the billets into the
first mill stand. Between the pinch roll and first mill stand, a pendulum shear is located as to cut the
front ends of the billets if required.
The mill consists of 13 horizontal stands (Roughing, Intermediate and Finishing). Roughing mill
consists of first seven stands, while the intermediate and finishing mill consists of next four and last
two stands respectively.
In between 7th and 8th stand, a Crop-cum-cobble shear is provided to cut front ends of all the rolled
stocks passing out of the 7th stand. This Crop-cum-cobble shear is also used for cutting the rolled
stock into pieces in case cobble is formed in the intermediate and finishing mill.
Four nos. of 180 Repeaters are provided between stands 9 to 14 (there is no 13th stand in the mill).
These repeaters are provided to reduce the overall length of the mill also for control the loop of the
rolled bars.
After the finishing mill three Thermax Carriage are situated. These Tharmax carriage (2nd and 3rd ) are
meant for water cooling at high pressure on the rolled hot bars as they pass through them. This way
the finished bars receives a short but intense cooling, resulting in the formation of a tempered
martensite structure surrounding the ferrite-pearlite core. The resulting material acquires high
strength combined with toughness and ductility. The technology utilizes the benefit of self
tempering of the bars by the heat of the core.
After Thermax Carriage a rotary shear is provided which cuts the bars into the predetermined
lengths which are then accommodated in the cooling beds(two nos.). From the cooling beds, the
bars go on to Bar Shears (two nos.) where each bar is cut into specified lengths as desired by the
customer. On-line Auto strapping unit (two nos.) is the last section in the mill having state of the art
Automatic strapping & bundling machines. In this section the bars are packed and bound into neat
bundles that are stacked section and quality wise in the despatch bays.
Apart from conventional rolling, Slit Rolling is also done in the Merchant Mill. In slit rolling, the billets
are slit longitudinally into two parts at 11th stand. In conventional rolling, only one bar is obtained
from a billet while in slit rolling, two bars are obtained from a single billet. Slit rolling is practiced for
sections for 16mm and conventional rolling for 20mm & 25 mm.
Wheel & Axle Plant
Wheel & Axle Plant is a special feature of Durgapur Steel Plant. It is the only plant in Public Sector which produces
forged Wheels . The main customer of wheels & axles is Indian Railways, although the wheels are supplied to
some non- railways customers also.
Wheel & Axle Plant was commissioned in 1962 with a capacity to produce 45,000 sets per year. Subsequently, its
capacity was raised further to 75,000 sets/year. The Wheel Plant has undergone a massive modernization in 1992-
93. The present capacity of the plant is as follows:
Capacity (Wheel) : 28,000 Tonnes / annum
Capacity (Axles) : 4,500 Tonnes / annum
Total Plant Capacity : 32,500 Tonnes / annum
In Wheel & Axle Plant of Durgapur Steel Plant, Wheels are produced by forging ,rolling and dishing while axles are
produced by drop forging with the help of a pneumatic hammer. Subsequently both are heat treated, machined
and tested before dispatch to different railways destinations. For the ease of production, wheel manufacturing
sections and axle manufacturing sections are located in two different bays of the plant.
Raw Materials for Wheel Plant
The raw materials for wheel are bottom poured round steel ingots & continuous cast round blooms. The chemical
composition of a typical wheel ingot is given below:
a) Hardening by Rim Quenching : - The above machine is used to spray water on the rim area of the wheel to
quench it. The quenching operation increases the hardness, wear resistance and fracture toughness of the rim
of the wheel and change in microstructure also takes place. After quenching the heat, which remained in the
hub (normalized area) area of the wheel, is transferred partially to the rim area, thus increasing its temperature,
which helps in reducing the brittleness and increasing the ductility of the material besides relieving some
amount of internal stresses developed during rim quenching. After air-cooling the wheels are charged into the
tempering furnace for tempering.
b) Tempering: - The process is designed to modify the properties of steel hardened by quenching at sub-critical
temperature. The wheels after quenching and air-cooling are charged into the tempering furnace where they
are kept as per schedule. The purposes of the tempering process is to:
The final crystal structure of the heat-treated steel is ‘fine pearlite’ with ASTM grain size 6 – 9. After heat
treatment the wheels are tested for various physical & chemical properties as per specific requirements of the
Indian Railways. These tests are destructive in nature and thus are conducted on a specific sample drawn from
every batch of wheels.
Machining
All the tested Ok wheels are subjected to machining operation.
Wheels are subjected to 3 or 4 specified operations depending on the type/specifications.
Operation 1
In this, the front rim face, front boss face, front boss and rim blending, condemning groove, cracking groove and rough
boring for the next operation is performed.
Operation 2
Beside rough boring, finished machining of rim width, web thickness, boss length and profile of gage and tread of the
wheel is performed. CNC vertical machines are used for Operations 1 and 2.
Operation 3
This is applicable where chucking groove is not a part of specification/drawining.BG coach Alt12,EMU etc. are subjected
to this operation where the chucking groove which is deliberatively made clamping of wheel during second operation is
again machined out by a first operation machine before finishing.
Operation 4
Sprag holes are drilled on wheels as per specification.
Cold stamping
The Machined wheels are stamped by a pin stamping machine on front side of the rim face in which following data are
mentioned.
Drawing No
Manufactures identity(DP)
Year of manufacture
Cast No.
Serial No. of wheel
Online testing
The machined wheels are first subjected to magnetic particle testing. In this test a low speed water jet
containing magnetic particles is impinged on the surface of the wheel in the presence of a magnetic field. Due
to presence of the magnetic field the magnetic particles align themselves along the cracks present on the
surface of the wheel. These magnetic particles are not visible with the naked eye. They are viewed with the
help of UV lamps and the presence of any sort of crack is detected.
The ultrasonic test involves passing ultrasonic waves through the rim, web and hub of the wheel. As
per the specifications, the number of Probes vary for a particular type of wheel. The probes for the rim are
kept submerged in water. The rim part of the wheel while testing is also kept under water and the wheel is
rotated at a particular rate (to test the entire rim). These probes measure the soundness and detect internal
defects present in the wheel. The entire facility is computerized. The computer screen displays the magnitude
of defect present in the wheel. When the magnitude crosses a certain critical limit the computer gives a
message to the operator that the particular wheel is unsatisfactory. The unsatisfactory wheels are either
discarded.
After ultrasonic testing the wheels are tested for their hardness in terms of BHN (Brinell Hardness
Number) value. The wheel is slowly clamped by means of a hydraulic cylinder and an indentor impacts the
surface of the wheel thus determining its BHN value. The BHN value is determined and displayed on the
computer screen . If the value is within limits, then the wheel is passed or else it is reworked.
Dimensional Inspection
After the wheels have passed all the previous tests, visual inspection and dimensional checking of all the
wheels are carried out. All visually detectable defects on the surfaces of the wheels are detected in addition to
checking of their metallurgical and ultrasonic test status. If some minute surface defect is detected it is
corrected by a hand grinding machine. Else if a major fault is detected, if possible, it is reworked, otherwise it
is rejected.
Axle Plant
The raw materials is the Round corner surface square(RCS) bloom rolled in ASP. Typical composition of Axle steel (Killed
Steel) is:
Axle steels (IRS R-16/95)
Elements % Permissible Variation
Carbon 0.37 (max) +0.03 / -0.00
Manganese 1.12 (max) +0.06 / -0.00
Silicon (min) 0.15 to 0.46 +0.04 / -0.00
P & S (max) 0.04 (max) +0.005 / -0.000
Cr & Ni (max) 0.30 (max) each +0.05 / -0.00
Mo (max) 0.05 (max)
Cu (max) 0.30 (max) +0.02 / -0.00
V (max) 0.05 (max) +0.02 / -0.00
P+S 0.07 (max)
Blooms are subjected to rigid Ultrasonic Test. Those showing signs of piping ,inclusion etc. are rejected.
Shaping of Axle
Blooms are heated in a continuous pusher type furnace. Cold bloom takes 6 to 8 hours to be ready for forging at 1220C.
Blooms are forged in axle forging hammer. This compressed air hammer has a falling weight of 7 tons. The hammer is
hand operated. It is fitted with a pair of twin swag dies which give the required shape of axle. Manipulators work in
conjunction with the hammer for hoisting, leveling titling and turning of the axle. It takes about 12 to 15 minutes to
forge an axle, the finished temperature being about 850C.
Heat Treatment
Axles are heat treated in a walking beam type furnace. The process that is followed is Normalizing where the
temperature of the furnace is maintained at 860±10C at both the zones . Through discharging door axles are taken out
after heat treatment and are placed for cooling on cooling beds. One foot gap between two axles is maintained for
achieving the required cooling rate.
Testing
After completion of heat treatment of the batch one axle is selected as a sample .A piece is taken out from the wheel
seat portion of the axle and tested for tensile strength. It is also checked for microstructure and grain size.
Machining
Axle is sawed for the required length after which the axle is centered and countersunk at 90 and recessed for ease of
the succeeding operation. Axle is then rough for the journal, dust collar and the wheel seat diameter. Is copying lathes,
the waist is next turned. The axle is then sent to finishing lathes for finished turning of journal, dust collar and wheel
seat diameter.
After finishing operation, the roller bearing axles go for drilling and tapping of 3 holes of 7/8 inch diameter BSW at the
ends of 16.25 ton axles. After this, in center less grinding machine, profile grinding of journal, dust collar and wheel seat
is done to an accuracy of 0.025 mm. for the wheel sets of plain bearing, axles are ground on cylindrical grinding machine.
The journal and dust ring are burnished to obtain polished surface on burnishing machine.
The axles are inspected for dimensional accuracy in each stage of making as well as after completion of all making jobs
for visible surface / diameter defects.
Non destructive testing & Dispatch
After machining of axles, dimensional inspections are carried out by RITES personnel. All dimensionally OK axles are
subjected to MPI to detect any surface defects and then are subjected to Diametrical UT tests all along the axles to
detect any defect at depth. Only rites OK ( Set finished(SF) and Set order(SO) axles are dispatched(SO axles are packed
only) to different destinations specified by Railways.