Detailed Estimates
Detailed Estimates
Detailed Estimates
VIII
1/2"Ø Pvc Pipe (blue pipe) Pcs 24 2,160.00
VIII 90.00
Shower Head Pcs 5 1,900.00 9,500.00
Shower Valve Pcs 5 1,200.00 6,000.00
1/2" Ø Faucet Pcs 12 180.00 2,160.00
4"Ø Pvc Tee Pcs 12 130.00 1,560.00
2"Ø Pvc Tee Pcs 12 38.00 456.00
3"Ø Pvc Tee Pcs 4 76 304.00
4"Ø Pvc Clean-out Pcs 6 60 360.00
2"Ø Pvc P-Trap Pcs 8 80 640.00
4"Ø Pvc Wye Pcs 8 120 960.00
Teflon Tape Roll 30 15.00 450.00
Solvent Cement (400cc) Can 10 85.00 850.00
4"Øx90˚ Pvc Elbow Pcs 8 80.00 640.00
3"Øx90˚ Pvc Elbow Pcs 4 50.00 200.00
2"Øx90˚ Pvc Elbow Pcs 8 20.00 160.00
1/2"Ø G.i. Elbow Pcs 8 32 256.00
1/2"Ø Pvc G.i. Tee Pcs 8 35.00 280.00
TOTAL MATERIALS 101,196.00
TOTAL COST 101,196.00
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
ELECTRICAL WORKS
Panel Board Pcs 4,500.00 1.00 4,500.00
200 Amps CB Pcs 680.00 1.00 680.00
20 Amps CB Pcs 320.00 10.00 3,200.00
30 Amps CB Pcs 385.00 10.00 3,850.00
25mm^2Thhn Rolls 2.00 11,400.00 22,800.00
3.5mm^2Thhnw Rolls 10.00 3,200.00 32,000.00
5.5mm^2Thhnw Rolls 2.00 4,850.00 9,700.00
Ref. Outlet Pcs 4.00 380.00 1,520.00
Aircon Outlet Pcs 4.00 380.00 1,520.00
2-Gang Outlet Pcs 50.00 85.00 4,250.00
IX 2x4 Utility Box Pcs 120.00 28.00 3,360.00
Junction Box Pcs 30.00 20.00 600.00
Electrical Tape roll 15.00 26.00 390.00
Flexible Hose roll 2.00 850.00 1,700.00
#3 Duplex wire L.m. 30.00 50.00 1,500.00
1"Ø Pvc Elect. Pipe Pcs 120.00 110.00 13,200.00
2-Gang switch Pcs 20.00 110.00 2,200.00
1-Gang switch Pcs 6.00 75.00 450.00
40Watts Bulb w/ Receptacl Pcs 50.00 415.00 20,750.00
TOTAL MATERIALS 128,170.00
TOTAL COST 128,170.00
TILE WORKS
60X60 Granite Tiles Pcs 208.00 160.00 33,280.00
Tile Adhesives Pcs 300.00 230.00 69,000.00
Tile Trim Pcs 12.00 25.00 300.00
X
30x30 Ceramic Tiles Pcs 918.00 30.00 27,540.00
0.60x2.40 Granite slab Pcs 13.00 8,000.00 104,000.00
TOTAL MATERIALS 234,120.00
TOTAL COST 234,120.00
XI DOOR JAMBS L.S. 25,200.00
XII WINDOWS L.S.
PAINTING WORKS L.S. 315,000.00
Flat Latex Pail 1,950.00 12.00 23,400.00
Semi-Gloss Latex Pail 2,300.00 44.00 101,200.00
Flat wall Enamel Pail 2,200.00 6.00 13,200.00
Quick Dry Enamel Pail 2,400.00 14.00 33,600.00
XIII Patching Compuond sack 880.00 3.00 2,640.00
Bostik Ultra Fino Skimcoat Sack 550.00 30.00 16,500.00
Flxibond Water Proofing Gal 780.00 15.00 11,700.00
7" Roller Brush Pcs 40.00 12.00 480.00
4" Roller Brush Pcs 28.00 8.00 224.00
Acrylic Emulsion Gal 570.00 4.00 2,280.00
sand paper L.m. 65.00 100.00 6,500.00
TOTAL MATERIALS 211,724.00
TOTAL COST 211,724.00
XIV AINAGE, CATCH BASIN L.S. 58,800.00
XV PLANS, PERMITS, ETC
Plan Preparations sheets 8.00 2,000.00 16,000.00
Printing sheets 50.00 40.00 2,000.00
Civil/Structural Engr. Fee l.s. 4,000.00
Prof. Elect. Engr Fee l.s. 3,000.00
Master Plumber fee l.s. 1,000.00
Building permits l.s. 6,000.00
fire dept. fee l.s. 4,000.00
Zoning fee l.s. 2,000.00
processing l.s. 3,000.00
DOLE safety Manual l.s. 3,000.00
Occupancy Permit fee l.s. 16,000.00
TOTAL COST 60,000.00
1,838,690.00 1,982,690.00
BILL OF MATERIALS FOR THE PROPOSED TWO STOREY RESIDENTIAL BUILDING,
LOCATED AT MABINI ST., ROXAS CITY OWNED BY CARLOS DY/CHERIE DY TUI
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
I EXCAVATION Lot 1 1 8,600.00
II BACKFILLING Lot 1 1 11,340.00
CONCRETE WORKS
1. COLUMN FOOTING
Washed Gravel Cu.m. 20.00 900.00 18,000.00
Washed Sand Cu.m. 10.00 600.00 6,000.00
TOTAL MATERIALS 24,000.00
LABOR COST 11,280.00
TOTAL COST 35,280.00
2. WALL FOOTING
Washed Gravel Cu.m. 1.00 900.00 900.00
III Washed Sand Cu.m. 0.50 600.00 300.00
TOTAL MATERIALS 1,200.00
LABOR COST 564.00
TOTAL COST 1,764.00
3. LINTEL BEAM
Washed Gravel Cu.m. 4.00 950.00 6,650.00
Washed Sand Cu.m. 2.00 650.00 2,600.00
TOTAL MATERIALS 84,068.00
LABOR COST 39,511.96
TOTAL COST 123,579.96
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
4. TIE BEAMS
Washed Gravel Cu.m. 10.00 900.00 9,000.00
Washed Sand Cu.m. 5.00 600.00 3,000.00
TOTAL MATERIALS 12,000.00
LABOR COST 5,640.00
TOTAL COST 17,640.00
5. RC COLUMNS
Washed Gravel Cu.m. 14.00 900.00 12,600.00
Washed Sand Cu.m. 7.00 600.00 4,200.00
TOTAL MATERIALS 16,800.00
LABOR COST 7,896.00
TOTAL COST 24,696.00
III
6. GROUND SLAB
Washed Gravel Cu.m. 16.00 900.00 14,400.00
Washed Sand Cu.m. 8.00 600.00 4,800.00
TOTAL MATERIALS 19,200.00
LABOR COST 9,024.00
TOTAL COST 28,224.00
7. SECOND FLOOR BEAM
Washed Gravel Cu.m. 10.00 900.00 9,000.00
Washed Sand Cu.m. 5.00 600.00 3,000.00
TOTAL MATERIALS 12,000.00
LABOR COST 5,640.00
TOTAL COST 17,640.00
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
8. SECOND FLOOR SLAB
Washed Gravel Cu.m. 11.00 900.00 9,900.00
Washed Sand Cu.m. 6.00 600.00 3,600.00
STEEL DECK 1.00mm THK L.M. 120.00 412.00 49,440.00
TOTAL MATERIALS 62,940.00
LABOR COST 29,581.80
III TOTAL COST 92,521.80
9. ROOF BEAM
Washed Gravel Cu.m. 6.00 900.00 5,400.00
Washed Sand Cu.m. 3.00 600.00 1,800.00
TOTAL MATERIALS 7,200.00
LABOR COST 3,384.00
TOTAL COST 10,584.00
MASONRY WORKS
A. CONCRETE HOLLOW BLOCKS WALL
6" CHB pcs 1,850.00 17.00 31,450.00
4" CHB pcs 2,600.00 13.00 33,800.00
Washed Sand Cu.m. 55.00 600.00 33,000.00
TOTAL MATERIALS 98,250.00
LABOR COST 47,160.00
IV
TOTAL COST 145,410.00
B. PARAPHET WALL
4" CHB pcs 1,200.00 13.00 15,600.00
Washed Sand Cu.m. 12.00 600.00 7,200.00
TOTAL MATERIALS 22,800.00
LABOR COST 10,944.00
TOTAL COST 33,744.00
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
CARPENTRY WORKS
A. FORMWORKS AND SCAFFOLDINGS
2"X2"X10' Coco Lumber Pcs 711.00 100.00 71,100.00
2"X3"X12' Coco Lumber Pcs 300.00 180.00 54,000.00
2"X4"X12' Coco Lumber Pcs 150.00 240.00 36,000.00
TOTAL MATERIALS 161,100.00
V LABOR COST 75,717.00
TOTAL COST 236,817.00
B. CEILING
2"X2"X10' Lumber Pcs 380.00 140.00 53,200.00
TOTAL MATERIALS 53,200.00
LABOR COST 25,004.00
TOTAL COST 78,204.00
STEEL WORKS
A. STEEL TRUSS
VI TOTAL MATERIALS
LABOR COST -
TOTAL COST -
TINSMITHING WORKS
A. ROOFINGS
VII TOTAL MATERIALS
LABOR COST -
TOTAL COST -
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
PLUMBING WORKS 250,000.00
A. SEPTIC VAULT
4" CHB pcs 400.00 17.00 6,800.00
Washed Sand Cu.m. 12.00 600.00 7,200.00
2"X2"X10' Lumber Pcs 35.00 140.00 4,900.00
TOTAL MATERIALS 18,900.00
VIII
LABOR COST 8,883.00
TOTAL COST 27,783.00
B. PLUMBING FIXTURES
TOTAL MATERIALS
LABOR COST -
TOTAL COST -
NO. DESCRIPTION UNITS QTY. UNIT PRICE TOTAL
ELECTRICAL WORKS
TOTAL MATERIALS
IX
LABOR COST -
TOTAL COST -
TILE WORKS
TOTAL MATERIALS
X
LABOR COST -
TOTAL COST -
XI DOOR JAMBS L.S. 25,200.00
XII WINDOWS L.S.
XIII PAINTING WORKS L.S. 315,000.00
TOTAL MATERIALS
LABOR COST -
TOTAL COST -
XIV AINAGE, CATCH BASIN L.S. 58,800.00
XV PLANS, PERMITS, ETC
Plan Preparations sheets 8.00 2,000.00 16,000.00
Printing sheets 50.00 40.00 2,000.00
Civil/Structural Engr. Fee l.s. 4,000.00
Prof. Elect. Engr Fee l.s. 3,000.00
Master Plumber fee l.s. 1,000.00
Building permits l.s. 6,000.00
fire dept. fee l.s. 4,000.00
Zoning fee l.s. 2,000.00
processing l.s. 3,000.00
DOLE safety Manual l.s. 3,000.00
Occupancy Permit fee l.s. 16,000.00
TOTAL COST 60,000.00