Tuban Plant,
Site
East Jawa
Power
28MW
Generation
GHG Emission 122,000t-CO2
Reduction /year
PJ Site
Tuban
Jakarta
appx100km Surabaya
Surabaya
JCM Agreement
Contract Formation on JCM
GHG
Reductions
International Consortium
Construction Engineering
Operation Equipment Supply
Maintenance
MRV
Criterion 1 The project utilizes waste heat from a cement production facility by waste
heat recovery (WHR) system to generate electricity
Criterion 2 WHR system consists of a Suspension Preheater boiler (SP boiler) and/or Air
Quenching Cooler boiler (AQC boiler), turbine generator and cooling tower
Criterion 3 WHR system utilizes only waste heat and does not utilize fossil fuels as a heat
source to generate steam for power generation
Criterion 4 WHR system has not been introduced to a corresponding cement kiln of the
project prior to its implementation
Criterion 5 The cement factory where the project is implemented is connected to a grid
system and the theoretical maximum electricity output of the WHR
system, which is calculated by multiplying maximum electricity output of the
WHR system by the maximum hours per year (24*365=8,760 hours), is not
greater than the total amount of the electricity imported to the cement
factory from the grid system:
> During the previous year before the validation, if the validation of
the project is conducted before the operation of the project, or
> During the previous year before the operation of the project, if the
validation of the project is conducted after the operation of the project
Criterion 6 The WHR system is designed to be connected only to an internal power grid
of the cement factory.
Copyright 2017 © JFE Engineering Corporation All Rights Reserved 6
DISCUSSION PURPOSE ONLY
Reference Emissions
Reference
Reference is the situation where WHR system has not been
introduced. Diffusion rate of WHR system is very low in
Indonesian Cement Industry 1 plant installed / 25 plants total
Conservativeness
Electricity consumption of WHR system is calculated by the
theoretically maximum load of auxiliary equipment
=> Rated capacity of installed equipment (EGCAP) related to WHR
system and max. hours/period
Emission Reductions
= Reference Emissions – Project Emissions
No additional fuel
Project Emissions = 0
Monitoring
20 80
% % Coal-fired Power Plant
SP Boiler AQC Boiler
Hot Exhaust
Gas
Cement Production
Process
Suspension
Preheater
EP EP
Rotary Kiln Clinker
Cooler
Stack Raw Mill Stack