1. A typical title for a Project Manager in a weak matrix structure is:
Project Coordinator
Project Manager
Project Leader
Program Manager
2. Which of the following statements is NOT true about a product lifecycle?
It starts with conception of = new product and ends with its withdrawal
A product can spawn a single project in its life
The five stages of each product lifecycle are product develooment, introduction, growth,
maturity, and dectine
It focuses on managing the properties of 2 product from a company’s business point of view
3. A Project Sponsor appointed a Project Manager to a new project and
asked him to get started immediately, even before the charter got
approved. What should the Project Manager do?
Push to create and spprove the cherter
Start with the team ramp-up and planning
Ask some other Project Menager to take over the project
Start the critical activities4. Which of the following is the MOST appropriate statement to describe a
Project Management Office?
It is the center of excellence for project menagement in en orgsnizetion
Iisa group of people working on project management activities for a project
PMO provides administrative support to Project Managers in an organizetion
tt is council thet includes all the Project Menagers in an organization
5. A manager who manages a collection of projects grouped together to
facilitate effective management to meet strategic business objectives is
called a:
Program Manager
Portfolio Manager
Project Manager
Stakeholder
6. A project sponsor is studying the project contract and going through the
narrative description of products and services to be supplied under
contract. The project sponsor is also meeting key stakeholders and subject
matter experts to evaluate whether the project is worth the required
investment. Which of the following documents would be created as an
output in the process?
Project Statement of Work
Project Charter
Project Management Plan,
Organizational Process Assets7. AS a Project Manager for a pharmaceutical project, you are in the process
of stakeholder analysis. You have identified both internal and external
stakeholders. Which of the following will be least useful for determining
how to engage them?
Using the influence/impact matrix
Correctly identifying the internal and external stakeholders
Determining and agreeing on the responsibilities of the internal and external stakeholders
Giving the stekenolders extra incentives to win them over to your side
8. Which of the following is NOT true about the initiating process group?
Large projects may divide the projects into phases
The project teem members are committed
Initial scone end financial resources are committed
Internal and external stakeholders are identified
9. A project team is working on initiating a project. Which of the following
options is NOT true about this situation?
The sponsor is developing the project charter
The Project Manager is developing the project charter
‘The Project manager is participating in the development of the project charter
The sponsor and the Project Manager together are developing the project charter10. Harry has been assigned the flyover construction project, and he is in
the process of initiating the project. In order to meet the customer's project
expectations based on the business and compliance requirements, which of
the following should Harry define FIRST?
Key deliverables
Project schedule
Project Statement of Work
Product statement of work
M1. Jenny is the Project Manager and is currently in the initiating process
group. She understands that it is critical for project success to identify
stakeholders early in the project. Therefore, she is in the process
“identify stakeholders.“ Of the following, which INPUT may
not be required?
Procurement documents
Project Charter
Expert Judgment
Enterprise environmental factors
12. One phase is planned at any given time, and the planning for the next is
carried out as work progresses on the current phase and deliverables.
Which of the following correctly defines the above text?
Overlapping relationshio
Sequential relationship,
Multi-phase relationship
\terative relationship13. Which of the following statements is TRUE regarding the initiating
process group?
Risk is lowest curing the Initiating process eroup
The project has the highest probability of project success during the Initiating process group
‘The Project Manager and team are elvays identified es part of the Initiating process grous
Initisting process group includes the develop project charter and identify stakeholders process
14. Which of the following is NOT true about the project charter?
It provides the Project Manager the authority to assign organization resources
It formally authorizes the project
It details the business justification of the project
It states what the project is, what the project will deliver, and how all the processes will be
managed
15. You work as a Project Manager at the mobile phone chipset
manufacturer. As predicted by Moore's law, each year your company
introduces new models of mobile phone chipsets which are faster and more
powerful than their predecessors. Mobile phone chipsets that are obsolete
or do not sell are quickly retired from production. The chipsets’ lifecycle
begins in R and D, extends to manufacturing, and finally ends with phase
out. This cycle is often referred to as:
Product lifecycle
Project lifecycle
Feedback loop
Product development16. Project management is the application of knowledge, skills, tools, and
techniques to manage activities to meet the project requirements. Which of
the following is NOT true about managing a project?
It involves identifying requirements
It involves addressing the various needs, concerns, and exoectations of the stakeholders as the
project is planned and carried out
It involves balancing the competing project constraints such as scope, auality, schedule, budget
resources, and risk
The specific project will not influence the constraints on which the Project Manager needs to
focus
17. A Project Manager has defined the key deliverables of the project based
‘on the business and compliance requirements and is now identifying and
documenting high-level risks, assumptions, and constraints based on
current environment, historical data, and/or expert judgment to identify
project limitations and propose an implementation approach. Which
process group is the Project Manager in?
Initiating
Planning
Executing
Closing18. A\ll of the following are functions of the project management office
EXCEPT:
Monitoring compliance with project management standards policies, procedures, and templates
via project audits
Coaching, mentoring, training, end oversight
Managing shared resources across all projects administered by PMO.
Identifying and developing the organization's methodology, administrative practices, and rules
19. Which of the following statements is true?
Cost and staffing levels are high et the start
‘The ability to influence the final characteristics of the product without impacting the cost is
highest at the start
Uncertainty is the least at the start of the project
Stakeholder influences increase over the life of the project
20. Your development team is waiting for the design team to finish its work
Asa Project Manager, you have decided to use this approach to reduce
uncertainty in the project. Which of the following relationship does this
describe?
Iterative relationship
Sequential relationship
(Overlapping relationship,
Common relationship21. Which of the following is NOT TRUE for stakeholders?
Stakeholders can be customers, sponsors, and the performing organization
Stekeholders cannot exert influence over the project, its deliverables, or team members
stekeholder identificetion is a continuous process
A project can be perceived as having both positive and negative results by the stakeholders
22. You are developing the project charter for the new project assigned to
you. Which of the following is NOT a part of the enterprise environmental
factors?
Lessons learned from previous projects
Work authorizetion system
Government and inclustry standards that affect your project
Knowledge of which departments in your company typically work on projects
23. You are being hired to manage a highway construction project for a
contractor working for XYZ. The sponsor is a project officer who works for
the XYZ municipal government. You have three separate teams working all
three shifts with a separate manager for each team. Each team has
members from two different unions, and each union has its own.
representative. Who is the BEST person to approve the project charter?
Project Manager
Union representatives
Project Officer wha works for XYZ
‘Team Managers24. Two members of a team are disagreeing about the right electric
parameters for testing a newly designed chipset. Who is in the best
position to help resolve this issue?
Project Manager
Project Sponsor
Functional Manager
‘Customer
25. A Project Manager is identifying relevant enterprise and environmental
factors in a project. Which of the following is NOT a valid example?
(Orgenizational culture and processes
Stakeholder risk tolerances
Employee performance review records
Historical lessons learned knowledge base
26. A hospital is installing e new management system to computerize the
hospital functions. For this purpose, representatives from several
departments are selected to create a task force assigned to implement the
project. This organization structure is called:
Functional Organization
Projectized Organizetion
Composite Orgenizetion
Balanced Matrix Orgenization27. As a Project Manager, you are in the process of establishing the total
scope of the effort in the project to define project objectives. For this
purpose, you include relevant stakeholders and explore all the aspects of
scope, cost, time, risk quality, etc. Which process group of the project are
you currently in?
Initiation
Planning
Execution
Monitor and Control
28. Project Manager John and his team have finished creating the Work
Breakdown Structure (WBS) and Work Breakdown Structure dictionary.
Then, he prepares a detailed and itemized documentation of all of the
schedule activities that are part of the project. What should he do NEXT?
Create Network Diagram for the project
Determine quality standards, processes, and metrics
Determine high-level project assumptions and constraints
Conduct project progress meeting
29. A Project Manager is working on planning a project that requires review
and oversight for a number of technically complex tasks. Who should
identify the specific resources for performing the reviews?
The Project Manager
The Project Sponsor
Functional Managers
Customer30. A key responsibility of the Project Manager is to ensure the proper
assimilation of the project management processes and coordinate the
process phases through the project management cycle. The Project
Manager also has to ensure that all areas of the project come together to
successfully deliver the project. This involves balancing the basic aspects of
scope, cost, and schedule in addition to managing quality, communication,
customer satisfaction, etc. The role of the Project Manager can be best
described as:
Integrator
Leader
Communicator
Differentiator
31. A key stakeholder from the quality department wants to know more on
how the process tailoring was done by the project team. Additionally, the
stakeholder would like to know the rationale for selecting processes, their
implementation level details, and how they will be used to manage the
intercependencies. Which document should the Project Manager refer the
stakeholder to?
Project Statement of work
Project Scope Statement
Project Management Plan
Work performance information32. A Project Manager has invited key stakeholders and team members for
the first meeting of the project. The agenda of the meeting is to announce
the start of the project, outline the project goals and objectives, as well as.
communicate the project success criteria. The Project Manager also plans
to discuss the individual roles and responsibilities, along with the
commitment of the stakeholders. What is this activity called?
Project sign off meeting
Charter closure meeting
Project launch meeting
Project kick-off meeting
33. You are a Project Manager of a highly visible and critical project in your
company. This project was initiated with much fanfare, and you have some
of the best technical experts as a part of the project team. You are in the
process planning and detailing the scope of the project when you hear the
project is being terminated. What could be the MOST likely cause?
‘The senior management didn't approve the project charter
‘The project team didnt have required technical expertise
‘The project sponsor failed to support the project
‘The project contract was not signed off by the customer34. You are working on a project to build a hybrid car which would run on
both diesel and electricity. This car would have a 1000 cc engine and work
‘on a regenerative braking system. It should be able to seat four passengers
including a driver and comply with Euro 4 emission norms. In which of the
following documents should this information be captured?
Product Scope
Project Scope
Scope baseline
Requirements Management Plan
35. A Project Manager is in the process of documenting and defining a
stakeholder's needs to meet project objectives. What is the output of this
process?
Stakeholder Register
Stakeholder Mansgement Strategy
Requirements Documentation
Issue Log36. You have taken over as a Project Manager of a complex and technically
challenging project. To add to the problems, your team is from diverse
cultures and lacks bonding. You want the team to participate and take
ownership of the project activities, as well as understand the “big
picture of the project.” Which of the following activities would be
most helpful?
Use colocation to heln team bond better which in turn would maximize productivity
Create Work Breakdown Structure (WBS)
Develop Responsibility Assignment Matrix to describe roles and responsibilities of every team
member
Conduct knoviledge sessions where each member appraise the team about his culture
37. You are a Project Manager working on a critical project. You track the
project schedule closely. While going through the critical path, you realize
that the project is showing negative float. What is your BEST response to
the situation?
Use @ schedule compression technique
Reduce the number of resources from the project
Reduce the number of noncritical activities in the project
Revisit the risks and do @ risk analysis of the project38. A Project Manager is in the process of analyzing activity sequences,
durations, resources requirements, and schedule constraints to create an
approved project schedule. What should the Project Manager do NEXT?
Determine Resource Requirement for each activity in the project
Use techniques like Critical Path method and what-if Analysis to calculate optimum duration of
the project
Use this approved schedule duration as a baseline and start tracking the project
Create @ Network diagram of the project using one of the diagramming methods
39. As a Project Manager you are estimating the duration of your project
activities using PERT technique (Program Evaluation and Review
technique). For a particular project activity, your optimistic estimate is 41
days, pessimistic estimate is 89 days, and most Likely estimate is 60 days.
What would be the expected duration and range of the estimate for this
activity?
6167 +/-8.00
3127 +/-8.00
6167 +/-3.00
3127 +/-30040. A project activity has the following values for the earliest and latest it
can start and the earliest and latest it can be completed. An activity’s Late
Start (LS) is 5/day and Late Finish is (LF) 10/day. Similarly Early Start (ES)
is 3/day and Early finish (EF) is 8/day, What is the float of this activity?
O days
4 aays
2deys
“3 deys
41. An activity cannot be started until the predecessor also starts. This is an
example of:
Finish-to-Stert
Finish-to-Finish
Start-to-Start
Start-to-Finish
42. A Project Manager understands the information needs of important
stakeholders and documents how they would be met. Which document is
being prepared?
Stakeholder resister
Stakeholder management plen
Human resources management plan
Communications management plan43. You are managing a project which would provide e-learning solutions to
your customer. The requirements of this project are not clearly defined in
the beginning, and there would be modifications based on customer
feedback as the project evolves. You decide to plan as much as you can and
begin to create work while continuing the planning. Which of the following
techniques would be the most helpful while defi
project?
Relling Wave Planning
Templates
Extreme Progremming
Just in Time
44, The optimistic time estimate for an activity is 11 days, pessimistic is 25
days, and most likely is 15 days. What is the expected time for this activity?
16 days
18 days
2 deys
18 deys
45. A Project Manager wants to determine the variance for an activity
estimate using a three-point estimate with the following data.
Pessimistic=14, Optimistic=2, and Realistic=5. What is the variance?
Not enough information46. Which of the following statements about critical path is TRUE?
It is the shortest path from start to finish
All the activities on the criticel path do not have any float
A project will have only one critical path
4 critical path tekes into consideration logics! as well as resource dependencies
47. You are a Project Manager in the early phase of estimating the cost of
the project. You use the analogous method of estimating and have come up
with the rough order of magnitude. While presenting it to your sponsor and
stakeholders, one of the stakeholders asks if you have also done lifecycle
costing for the project. What is your BEST response?
Project Cast estimating is primarily concerned with cost of the resaurces needed to complete the
project and needn't consider any other costs
Since it is the initial stage of the project, cost details required for lifecycle costing of the project
are not available and hence itis not relevant
Lifecycle costing provides the lowest long-term cost of ownership and should be used as &
management decision tool, in case of alternatives
Lifecycle costing should be done by the Project Sponsor as it impacts long-term business
decisions48. As a Project Manager, you are working with your team to explore
alternatives to decrease project cost without compromising on
performance or scope of the project. Which of the following techniques are
you most probably using?
Benchmarking
Reverse Engineering
Process Analysis
Value Analysis
49. Which of the following is a tool and technique for the Determine budget
process?
Monte Carlo analysis
Delphi technique
Funding Limit Reconciliation
Parametric estimation
50. Which of the following are the MOST important to derive the total
funding requirements and periodic funding requirements of the project?
Management Reserve and Contingency Reserve
Cost Baseline and Management Reserve
Funding Limit Reconciliation
Project Budget and Contingency Reserve51. As a Project Manager for the project in the planning stage, you have
derived the cost estimate by estimating the cost of individual work
packages. It is summarized to higher levels for reporting and tracking. What
would be the range of estimate from the actual?
-50 percent to +100 percent
-50 percent to +50 percent
“10 percent to +25 percent
-B percent to “0 percent
52. You are a Project Manager planning to launch a new product in the
market. For this purpose, you are analyzing the existing products in the
market to understand their best practices. You also compare industry
standards for performance metrics including cost, cycle time, productivity,
and quality to come up with your own product metrics. Which of the
following activities are you doing?
Cost Benefit Analysis
\Velue Engineering
Benchmarking
Process Analysis,53. A Project Manager has derived quality metrics along with tolerance
limits for his project. Which part of the quality management knowledge
area is the Project Manager in?
Plan Quality Management
Perform Quality Assurance
Perform Quality Control
Define Scope
54, Project Manager John wants to capture the details of activities he
would be doing to enhance the value of the process, including their inputs,
outputs, and interfaces with other processes. Which of the following
documents would be MOST helpful?
Project Management Plan
quality Management Plan,
Process Improvement Pian
Product Management Flan
55. In order to determine the target fuel efficiency for a hybrid car being
designed, a Project Manager is looking at published statistics for similar
models in the industry. The technique being used is called:
Brainstorming
Benchmarking
Statistical sampling
Design of Experiments56. Which of the following would NOT be part of cost of conformance?
Prevention cost
Appraisal cost
Internal failure cost
Cost of training
57. A Project Manager is planning a project, and he is creating a plan to
describe how human resource requirements in the project would be met.
He is using a bar chart tool called a Resource Histogram for charting this
requirement. However, he notices that some of the individual bars in the
Resource Histogram extend beyond the maximum allowed hours. What
should the Project Manager do to correct it?
Reduce Scope
Extend Working Hours
Resource Leveling
schedule Compression
58. According to Maslow’s Hierarchy of needs, what comes HIGHEST on the
pyramid?
Social
Safety
Physiological
Hygiene Factors59. A pharmaceutical company wants to launch a new over-the-counter
medication for flu in the U.S. The Project Manager is identifying project
communication constraints. Which of the following is NOT a valid
constraint?
The company should get an FOA approval before producing or selling the medicine
‘The key person responsible for communicating the information on the project may nat be
available through the entire project
‘The milestone meeting should be attended by all the maior key stakeholders
‘The project has teams working in eiferent geographical locations and time shifts
60. You are a Project Manager in a financial firm with multinational dealings.
You feel the financial meltdown in one of the client's countries could affect
your project adversely, and you want to hedge your risks. Although the
probability of occurrence of the event is low, you are advised to play it safe.
In terms of risk attitude, your organization could BEST be described as:
Risk Seeker
Risk averse
Risk Neutral
Risk Mitigator
61. Which of the following is NOT a tool used in the perform qualitative risk
analysis process?
Probability and Impact Matrix
Risk Pronttization
Monte Carlo Simulation
Root cause identification62. Which of the following is an example of Lead?
Pillars for 2 structure can be started 7 days ofter the foundation to allow for curing
Test leb preparation can stert 5 deys before @ product is made aveilable for test
Both test planning and product development can start simultaneously after the design is,
finalized
Crash tests cannot be carried out until ¢ working final model is made available
63. The estimating technique that uses the statistical relationship between
the historical data and other variables to calculate an estimate for an
activity is called:
Analogous Estimating
Parametric Estimating
Three Point Estimating
Monte Carlo technique
64. In which form of contract will the cost risk lie with the seller?
cor
Tend M
cea
Fe65, While responding to a procurement request, the seller outlined the
detailed technical solution, provided a handful of past customer references,
and also made a detailed commercial offer. Which procurement document
would the seller mast likely respond to?
Request for Quotation
Request for Proposal
Invitation for Bid
Bidder conference invitation
66. You are in the process of implementing approved changes, corrective
actions, preventive action, and defect repairs in the project. In which of the
following process groups are you in?
Initiation
Planning
Execution
Monitor and Control
67. You are a finance specialist who has been assigned to an organization-
wide project in a strong matrix structure. The Project Manager requests you
to work on a report, which you feel is unnecessary. You have tried to reason
with the Project Manager about this, but the Project Manager insists it is
required. What should you do?
Escalate to your functional Manager
Provide the report
Set up 2 meeting with the Project Manager to discuss the issue
Ignore the request and work on other important tasks.68. A Project Manager realizes that a lot of time and effort are spent by his
team in capturing the data during product testing. Which is the best option
to address the issue?
Stop capturing the date as it doesn’t edd any value to the project activity
Allocate a time at the end of the day to update all the data together
Ask for an additional resource to capture project data
Automate the data capturing process
69. A Project Manager is facing many serious issues in his project to create
an application for a hospital management system. The project's final
deliverable is scheduled for two weeks from now. It needs to fulfill
compliance with mandatory government health standards. In addition to
that there are some changes required to improve performance which the
Project Manager feels will make the customer happy. Amidst all of this, a
senior test engineer asks the Project Manager for a long leave. Which is the
most critical issue the Project Manager needs to address FIRST?
Ensure the product is complient to government health standards
Find a replacement for the senior tester and ensure he completes knowledge transfer before
leaving
Complete chenge control process to incorporate changes to enhance performance
Notify the customer about probable delay in the final deliverable to avoid surprise later70. You are a Project Manager taking over a project midway. It is in the
execution phase. You would like to know more about project deliverables,
work required to complete those deliverables, project constraints,
assumptions, etc, Which of the following documents would be MOST
useful?
Work Breakdown Structure (WBS)
Requirements Documentation
Activity List
Project Scope Statement
71. Which of the following is an output of the Direct and Manage project
work process?
Project Charter updetes
Work performance information
Approved change requests
Change requests
72. A project is relying on a contractor to deliver a component. The
contractor informs the Project Manager about the likelihood of a 3-week
delay in the delivery date. What should the Project Manager do?
meet with the teem to discuss the issue
Escalate the matter to the senior management of the contractor 2s per the escslation metrix
Issue @ formal show-cause notice asking why the contract should not be submitted
Inform the senior management and the customer about the possibility of delay to the overall
project due to the delayed component73. You are managing an e-banking solution project when the Vice-
President of the company calls you to discuss an opportunity to manage a
critical company project which can boost your career and professional
experience. Your e-banking solution project is due to complete in 3 weeks.
What is your best response to the Vice-President?
‘You would surely like to manage both the projects together as the latter is 2 critical project for
the compeny
‘You would use @ compression techniave to finish your current project faster and then take up this
new project
since the new project is more critical to the orgenization, you could take this project immediately
and your earlier project can be meneged by someone else. It's coming to 4 close anyway.
‘The project shoule first develop an enproved project charter which would formally initiate the
project
74, You are managing a large project team that has some new members
joining. You would like to take the entire team through the project schedule
and update them on where the project stands with respect to the original
plan. Which of the following charts would be most helpful for this purpose?
Gantt Chart
Milestone Chart
Work Breakdown structure
Schedule Baseline75. An infrastructure company had an option of bidding for a toll highway
project, with an NPV of $5 million, but they opted for bidding for a power
plant project with an NPV of $6 million. $5 million represents the
for the company.
Opportunity cost
Depreciation
Sunk Costs
Internal Rate of Return
76. You are a Project Manager for an IT company in the final phases of
project execution. Your project status is well within the budget and you are
almost a week ahead of your schedule. During the final testing phase of the
project, you realize that the performance of the product can be increased
by almost 20% of the expected value by doing minor code changes in two.
modules. This change would require an additional 2 days of work. What
should you do NEXT?
Analyze the various cltematives and do a deteiled impact analysis before proceeding with the
change
Update the change management form and send it to change control board for consideration
Discuss the change and impact with the customer and sexk his approval
Ignore the change as it is gold plating and should be avoided77. A Project Manager is going through the defect report reviewing the
bugs reported during the testing cycle of a software project. The report has
information on the severity of the bugs, origin of the bugs, and possible
resolutions, along with the owner and reporter of the bugs. The Project
Manager wants to prioritize the bug fixing activities by evaluating the three
most frequent reasons for the defects. Which of the following tools should
the Project Manager use?
Control chart
Fishbone diagram
Scatter diagram
Pareto chart
78. A team is complaining that every quality audit invariably audits its
module, but other modules are not audited at the same frequency. What is
the best explanation that can be provided?
A module gets audited more frequently because it has maximum issues
A module may get audited more because itis the most critical
Modules to be audited are picked up based on the quality management plan
Next time, make sure thet all modules get aucited at the same frequency,79. You are managing a critical project with frequent changes in
requirements. You are in the testing phase of the project, and the customer
has requested an additional new feature. You have assessed the impact of
the change on the triple constraints with your team. What should be your
NEXT step?
Reise = chenge request form and send it for approval to the chenge control boarc
Look for alternative options including schedule compression techniques like crashing and test
tracking
Analyze the impact of the change on project quality objectives end quality planning
Undate the project management plans and other project documents including project baselines
80. The method of examining work or a product to determine whether it
conforms to documented standards is called
Inspection
Statistical Sempling
Auait
Verification
81. What is the best time to engage in team building activities?
In the beginning of the project
At the end of the project
‘Throughout the project
In the beginning for some projects and in the end for others82, You are managing one of the most technically challenging and complex
projects for your company. In the beginning of the project, there used to be
heated arguments on the team regarding the best approach to solving a
problem. However, the project is well into the execution stage and the team
has finished designing the architecture of the product. They seem to have
developed a good understanding of the system. What is the most
appropriate way to handle project conflicts at this stage?
You should continue to determine the best solution and ask the team to implement it
‘You should let the team explore the best alternatives amongst themselves while you facilitate and
support them,
You shoul invite ideas fram everyane in the team to arrive at the best solution
‘You should make a decision based on consensus from majority of the teem
83. Your software project is in the critical system testing stage when two of
the senior members of the team come to you with a conflict on usage of
the simulation software during testing. One senior member claims that the
other person keeps the software engaged for almost all the working hours
of the project. You decide to change their working schedules so that they
no longer overlap. Which of the following techniques for conflict resolution
are you using?
Compromising
Collaborating
Forcing
smecthing84. As a Project Manager you decide to create an issue log which captures
issue description, owner, and the target date for issue closure. All of the
following are common examples of issues in the project EXCEPT:
Differences in Opinion
Probable delay in the next delivery
Pending Root cause Analysis,
Delay in receiving feedback from the customer
85. A Project Manager is working on shortlisting, interviewing, and selecting
candidates for the open positions within a project as per the job
descriptions. Which process group is being worked on here?
Planning
Initisting
Controlling
executing
86. A Project Manager likes to involve the project team in the decision-
making process. Whenever there are issues which require urgent decisions,
the Project Manager calls the team to work out a solution together. This
approach is:
Correct because it helps to get team buy- in and its commitment to the change
Correct as brainstorming technique helps to bring out creative ideas to salve the problem,
Incorrect as lot of time and effort of the project team are spent on decisions which could be,
singularly made by the Project Manager
Incorrect 2s nat all the solutions coming of 2 brainstarming session can be implemented,
resulting in disappointment in the team87. A Project Manager working in a matrix project environment feels there
is some discontent in the team members related to their dual reporting and
the role of Project Manager on the project. The Project Manager wants to
communicate with the team to clarify their doubts. What is the BEST form
of communication for addressing this problem ?
Formal Written mail
Informal chat with the teem
Face-to-face-meeting
Informal written mail
88. A Project Manager in an information technology project is discussing a
complex algorithm with a new team member. After a long and thorough
verbal discussion, the Project Manager asks if the team member understood
the algorithm and can put it in the document. The team member implies
that he has understood. However, when the Project Manager goes through
the document, he realizes that the member didn’t understand what was
said thus resulting in an inefficient use of time and effort. Who is
responsible for this loss of time, and how could it have been avoided?
Project Manager, he shouldn't have given the complex essignment to a new tesm member
‘Team Member, since he implied he understeod the discussion and didn't esk his doubts
immediately
Project Manager, he shoule! have elso helped the team member in preparing and reviewing the
document
Project Manager. since it is his responsibility to ensure his message is clear and concise end
confirm that the team member truly understands the message89. You are managing a project with project teams in different geographical
locations, There are approximately 25 team members in 3 different
locations each being led by a team lead. Additionally, there are 3 members
from a supporting group that are working part-time on the project. How
many communication channels are possible in your project?
496
222
424
32
90. A Project Manager is documenting the normal process for escalating
the issues on a project. Which document usually contains this information?
Risk management plan
Stakeholder menagement plan
Project Communication management plan
Quality management plan91. A key stakeholder of the project is contacted for a requirements
document approval but shows no interest. The Project Manager decides to
have a friendly, informal discussion with the stakeholder to understand the
reason for his lack of interest. During the conversation, the stakeholder
expresses his displeasure that two of his key suggestions were not
addressed on the project and feels as though his approval or feedback
doesn't really matter since the main requirements are not being captured.
What is the best option for the Project Manager in this case?
‘Aatee with stakeholder and doesn’t take his approval on requirements. Remove his name from
the list of stakeholders and avoid communicating with him further on project status
Incorporate the requirements of the stakeholder and then take his approval
‘Talk to your Project Sponsor about the issue and take his approval before taking any further
action
Explain to the stakeholder that although his suggestions were appreciated, it is not possible to
address all of them in this release due to proiect constraints. You will revisit them at the next
hese.
92. A key stakeholder expresses his concern over lack of project visibility
and progress and says that project status reports received lack information
relevant to the stakeholder's department. How should the Project Manager
respond?
Review the Project Communication Management Plan to deteimine the stakeholder's needs
Relook at the Manage Communications process to identify the gaps
Raise @ change request to address the stakeholcer's feedback
Relook at the Control Communications process to understand the problem93. A Project Manager in an e-learning project is using free downloadable
tutorials via the Internet to reach out to large audiences. This
communication method is called:
Interactive Communication
Pull Communication
Push Communication
Personal communication
94. In one of the project status meetings, two senior team members get
into an argument regarding the introduction of a new tool to automate time
sheet filling. Which of the following would provide you maximum insight on
the conversation?
‘The content enc timing of the conversation
‘The content enc timing of the conversation and the communicetion technology used
‘Body Language and the words in the conversation
Body language and voice modulation including pitch and tone95. A CEO from his Paris office wishes to communicate with the technical
officer in China. What is the correct procedure to communicate?
The CEO will decode the message from French to Chinese, the technical staff will encode it from
Chinese to French
‘The CEO will encode the message from Chinese to French; the technical staff will decode it from.
French to Chinese
The CEO will decode the message from French to Chinese, the technical staff will encode it from
Chinese to French
‘The CEO will encode the message from French to Chinese; the technical staff will decode it from.
Chinese to French
96. As a Project Manager you are worried about the continuous bad
performance of one of your team members. You have spoken to him over
coffee, but there seems to be no improvement. What is the MOST suitable
way to communicate your dissatisfaction to the concerned team member?
Informal verbal
Formal Verbel
Formal written
Informal written
97. Which of the following is NOT an input to the process Manage
stakeholder engagements?
Stakeholder Management Plan
Communication Management Plan
Change Log
Issue Log98. Which of the tollowing 1s the output of the process manage stakeholder
engagements?
Issue Log
Stakeholder Management Plen
‘Communication Management Plan
Stakeholder Register
99. A Project Manager shares project performance through status reports
via email to all the stakeholders of the project. Which of the following
techniques is he using?
Kick-off meeting
Pull Communication
Push Communication
‘Communication model
100. As a Project Manager, you need to estimate the regression testing for
your product. You would like to do 5 full testing cycles. Each cycle is
estimated to take 4 days. What is your estimated duration for the testing
activity?
25 deys
18 10 22 days
18 days
22 to 2d days101. Which of the following needs is at the lowest level of Maslow’s
hierarchy?
Self actuslization
Esteem
Social
Safety
102. A project team is working on constantly reviewing and making sure
that the right processes are being followed. Which process will the team
use?
Perform Quality Assurance
Control Quality
Plan Quality Management
Quality Metrics
103. A Project Manager working on a construction project identifies the risk
of a heavy storm in the coming months that might affect the construction
activity. However, there is no reliable information on the weather forecast
or the severity of the storm. In this case, what is the BEST that the Project
Manager can do?
Capture the risk in the Risk Register
Ignore the risk as nothing cen be done to avoid it
Actively accent the risk and allocate time and cost reserve in contingency fund
Proceed with Risk Response Strategy to counter the risk104. Which of the following is NOT a likely outcome of trying to fast track a
project?
Reduce the level of risk
Reduce the time taken
Increase the level of risk
Cause more rework
105. You are a Project Manager of a software development project. You
have outsourced a component of your product to a third-party vendor, and
it is due to be delivered next week. You find out that the delivery of the
component may be delayed due to political unrest in the vendor's location.
What is the BEST you can do in this situation?
Report to your senior Manager about prabable delay. along with details on the current political
situetion at vendor's place:
Communicate to the vendor thet eny possible deley would attract = fine and affect future
payments:
Revisit your project schedule and look at alternatives to reduce the impact of the delay
Since there is no official communication from the vendor, you need to use the "weit end watch”
policy
106. A Project Manager is conducting a bidder conference to select the
most suitable sellers. Which of the following tools will NOT be helpful?
Independent Estimates
Analytical Techniques
Procurement Negotiations
Make-or-Buy analysis107. In execution phase, implementation of approved actions happens by
following risk management plan and risk register. For this action, which
option is correct?
Minimize the negative risk and take the opportunities
Minimize the opportunities and increase the negative risk
Minimize only negative risk
Minimize only opportunities
108. While working on a contract, a supplier's factory was severely
damaged due to an earthquake, and the supplier could not deliver the
contracted items on time. The liability of the supplier to pay penalty for
delays is probably restricted due to:
Doctrine of Waiver
Pnvity
Dispute Resolution
Force Mejeure
109. You have recently joined a new construction company, and you find
that your employer is violating the construction permit issued by the local
city government. What should you do?
Inform the city authority of the violation
Talk to your employer to find out if they are aware that they are breaking the law
‘Complain to the legel department of the company
Do nothing as you are new to the organizetionN10. As a Project Manager, you understand the importance of effective
communication with stakeholders. You want to present a project progress
report to the stakeholders in the next project meeting. What should be your
approach?
Moke the report concise end restricted to specific technical details of the project
Prepare @ verbose report but fiter the information to remove details
Focus on specific stakeholders with whom you have good personal relationshios
Research end understand the experience level and expectations of stakeholders
1. You are managing a multinational project with team members from
different countries with varying time zones. In this scenario, you wish to
‘choose a communication medium that is most efficient for the project
requirements. What is the most appropriate way to address this?
Explore communication tools available in the merket and ask for quotations exclusively fer your
project instead of using the existing tool in the organization
Use the most cast effective technique and explain its usage to everyone
Use a comiination of communication technologies
Discuss these communication requirements anc aveilable options with stakeholders to seek their
input
112. You are interviewing candidates for a position in the project. When you
receive the resume of a distant relative who is desperately in need of a job,
what should you do?
Give the candidate the job, but insist on good performance
Ask the candidate to aooly somewhere else
Declare your position and excuse yourself from the selection process
Do nothing and go with the panel decision113. As a Project Manager, you have a large team reporting to you, with two
members working on a new technology for the first time. At the beginning
of the project, you were concerned that the members wouldn't be able to
contribute much due to the technical complexity of the project. However,
you spent time and gave them the required training in order to help them
perform. During your assessment, you find some areas that still require
improvement. What should you do next ?
Discuss this with the Functional Manager and ask him to assign these resources to some other
project as you have already spent enough effort on them
Give them more challenging assignments 50 that they fail and you have a reason to expel them
from the team
Assess their current weak areas and provicle mare focused training with regular feedback
‘Talk to them and and give them @ warning that this is their last chance te perform in the project
114. After working as a Project Manager for more than 25 years, you want to
share your learning and best practices with your industry. You do this by
writing articles in international journals and giving interviews to share your
‘experience. This act can be BEST described as?
Enhancement of professional skills by learning project management and technical skills
Contribution to project management knowledge bese by virtue of vast personal experience:
Capturing professional stint in autobiography purely as a retrospection exercise
Informing others about project management principles and helping the profession grow:15. During project execution, the customer interprets a clause in the
contract differently and demands an elaborate design document as part of
the next deliverable. According to you, this is not included in the
deliverable list. What best can you do to resolve the situation?
Change the centract and cantinue with your project work
‘Accept the customer's demand 25 he is responsible for the project's success
‘Talk to your Project Sponsor about the issue and the implications of accepting such a request on
the schedule and cost of the project
Document the cispute anc refer to the claims aciministration
116. You are working at a customer location in a foreign country where it is
customary to exchange gifts during New Year celebrations. Your company
forbids you to accept any form of gift from your customer, but you have a
strong feeling that if you refuse to accept and reciprocate the gesture, it
can severely affect your relationship with the customer. In this case, it is
BEST to:
Explain your company policy and politely refuse to accept any gifts
Discuss this situation with your Project Sponsor or legal depertment,
Accept the gift and keep it confidential so thet there is na loss of face far your organization
‘Take a break from project work to go an a small vacation during the New Year117. Your project has faced some unforeseen issues that have delayed it. The
project is very critical for the company, and it has to meet the scheduled
deadline. In order to meet the deadline, your team would have to work over
the weekends for the next two weeks. However, you know that many of the
team members will have personal commitments, and it will be very difficult
for them to work for seven consecutive days. What is the BEST option?
Hire adaitional resources and brief them about the project
Inform the customer that this deadline can't be met
Discuss the situation with the team and give them the choice to willingly work overtime
Send an official mail, making it compulsory for the team to work over the weekends
118. You are a Project Manager in the process of performing the work
defined in the project management plan to achieve the project objectives.
Which process are you in?
Develop Project Management Plan
Monitor and Control Project work
Direct and Manage project work
Execution process group119. A Project Manager, Joe, is discussing the observed variations between
planned and actual values of defects with his quality engineer. He realizes
that he has forgotten to identify one of the important metrics to analyze
defects. Which process group is the Project Manager in if he evaluates the
current result for the metric to see if it requires corrective action?
Planning
Executing
Monitor end Control
Quality Audit
120. A Project Manager wants to monitor the performance of a process. She
sets up thresholds for this purpose, and any observation beyond the
threshold would trigger a root cause analysis and corrective/preventive
actions. This is an example of:
Specificetion limits
Control limits
Pareto charts
Tolerances121. The Project Manager is reviewing the issue log as part of his execution
activity. Which of the following would be the LEAST appropriate activity for
the Project Manager to perform as part of the monitoring and controlling
process group activity?
Assess the corrective actions on the issue register
Determine the next steos for unresolved issues
Use appropriate tools and techniques in order to minimize the impact on project schedule, cost,
end resources
Review the issue and determine if the issue should be avoided, mitigated, transferred, or
accepted
122. You are assigned as a Project Manager to a project in the execution
stage. Current schedule and performance indices for the project, SPI and
CPI are 1.12 and 1.15, and project performance are well within the baseline.
The defects found during internal testing for the last deliverable were well
below the organization limits. However, the customer doesn’t seem to be
happy with the project progress. What should be the FIRST thing the
Project Manager should do?
Start managing project es you gain more insight into day to dey responsibilities
Meet with the project team to understand open issues in the project
Conduct ¢ meeting with the customer to understand his concern over project progress
Improve project schedule snd cast control measure so that SP| and CPI reaches above 15123. A Project Manager working in an iterative model of the product
development lifecycle expects many changes during the course of the
project. He wants to establish a robust configuration management system
and also make his team aware of the process. Which of the following
statements is NOT true about configuration management?
‘The purpose of configuration management is to maintain integrity of work product
Configuration management includes configuration audits, configuratien control, configuration
stetus accounting, and configuration identification
Configuration management focuses on establishing end maintaining consistency of a product's
requirements
Configuration management involves measuring project performance with baselines and taking
corrective action when necessary
124. A Project Manager has delivered a major deliverable of the project. The
‘customer comes back a week after the release saying that he is not entirely
satisfied with the deliverable. What should the Project Manager do NEXT?
Continue with the next deliverable as the project has to be finished on time
Telk to the Senior Manager to discuss the customer concern and resolution
Ensure thet the next deliverables have the features that the customer specified end exceed his
expectations
De a scope verification of this deliverable to check itt satisfies project objectives
125. The decision to close a project is taken during which process group?
Planning
executing
Controlling
Closing126. Your project is in the final stages of testing, and the team is interacting
with the customer on a daily basis to update the customer with the project
status and incorporate his feedback. Which of the following would be the
most critical process to be followed in this scenario?
Control Quality
Control Scope:
Menage Communications
Control Risks
127. A Project Manager is proactively managing the change through the
scope control process. Which of the following should he be MOST worried
about?
Value Added Changes
Errors and Omissions
Fisk Response
\Vertsal communication fram key stakeholders
128. The ES of an activity is 2 days, and the duration of the activity is 5
days. The LF for the activity is 8 days. What is the total float for this
activity?
6 days
days
lday
5 days129. As a Project Manager and member of the PMO (Project Management
Office), you want to present a snapshot of the status of various projects
that the organization is working on to the senior management. Which of the
following charts would be most suitable for the purpose?
Milestone chart
Gantt Chart
Precedence diegrem
Control chert
180. You are trying to figure out if there is a correlation between the slack
time available in a shift and the number of rejected components produced
during the shift. Which is the tool that you will use to analyze this?
Pareto charts
Ishikawa diagrams
Histograms
Scatter diagrams131. You are managing an infrastructure project that is nearing completion
when a major stakeholder points out a flaw in the design that could make
the entire structure weak. He suggests that you construct two support
pillars that would provide the necessary support. You are worried that this
change could impact the schedule and cost of the project significantly.
What is your BEST response to the stakeholder?
Refuse his suggestion as the project is already nearing completion and it’s not possible to make
any changes et this stege
Do # root cause anelysis with the team to determine how this design flaw could have been
‘missed, and if there could be more potential problems with the design
Proceed with the chenge end communicate the impact on project schedule and cost to the
customer
Use 2 schedule compression technique as art of integrated change control to investigate end
minimize the adverse impact of the change
132. Project performance reviews using earned value management would
NOT typically incorporate information from:
Voriance Analysis,
Cost Benefit Analysis
Trend Analysis
Earned Value Technique133. As a Project Manager, you realize that the initial budget cost, Budget at
Completion (BAC), for your project is no longer viable. You need to develop
a new Estimate At Completion (EAC) forecast assuming that current
variances would continue in the future. Which of the following formulae
should you use to calculate EAC? Here, AC is the Actual Cost, EV is the
Earned Value, and PV is the Planned Value.
EAC = AC ETC
EAC= AC+ (BAC - EV)
ac = EW/PV
EAC = BAC/Cumulative CPI
134. Earned value management is the tool and technique of which process?
Perform Integrated Change Control
Control Costs
Direct and Manage project work
Control Schedule
135. A project team with a CPI of 0.78 is looking for options to reduce cost
Which of the following would be the BEST option to do so?
Reduce a test cycle in the system testing ahase
Reduce scope by cutting down non-essential features
‘Add more resources to expedite the schedule
Revisit estimates end eliminate risks and then re-estimete136. You are a Project Manager. You need to decide whether to buy
insurance for a temporary manufacturing facility. The likelihood of a mishap
is assessed at 10% and the likely impact is evaluated at $500,000. The cost
of insuring is $20,000 and has a $10,000 deductible. Would you buy
insurance?
‘Yes, because 50,000 > 21000
‘Yes, because 50,000 > 30,000
No, because 30,000 < 500,000
No, because 21,000 < 50,000
137. A project has a CV of -$500 and SPI of 1.2. What can be said about the
project?
Your project is aver budget and behind schedule
Your project is under budget end behind schedule
‘Your project is over budget and ahead of schedule
Your project is under budget and ahead of schedule
138. As a manager, you would like to get the status on the remaining work
with respect to the remaining funds. Which of the following measures will
give you the information?
‘To-Complete Performance index
Earned Value Technique Performance
Variance Analysis
Trend Analysis139. Which of the following is the best use of Pareto charts?
To visualize a workflow
To prioritize issues
To perform deeper causal analysis
To examine trends
140. In a normal distribution, what is the probability of finding the actual
value between 1 standard deviation distance from the mean?
095
09973
08
oss
141. A team is inspecting specific project deliverables to ensure that they
are in accordance with the specifications. Which process is being worked
on?
Perform Guality Assurance
Validate Scope
Plan Quality Management
Control Quality142. Your project is going through an audit cycle. One of the senior auditors
points out that the target value for Schedule Performance Index (SPI) is set
to a low value and should be increased by at least 5 percent. You try to tell
the auditor that this target value is in accordance with the organization
baseline and cannot be changed. Which of the following is the CORRECT
statement in this case?
‘The auditor is right, as the project must meet a critical deadline, target SPI should be increased
‘The auditor is right; the target value of SPI is a benchmark for the project, and it should be kent
high
The Project Manager is night; as the project schedule is not critical, target SPI vslue needn't be
kept too high
‘The Project Manager is right: target SP! is based on organization baseline derived from its
process maturity level and should be followed by the project
143. The customers are performing User Acceptance Tests on the product
that was delivered by the project team. Which process is likely being
performed?
Control Quality
Control schedule
Perform integrated Change Control
Validate Scope144. A Project Manager is working toward improving the competencies,
team interaction, and overall team environment to enhance project
performance. Which of the following tools and techniques would NOT be
helpful here?
Training
Recognition and Rewarcis
Conflict Management
Co-location
145. Which of the following is the top source of conflict in a project?
Schedule
Project priorities
Administrative procedures
Personality
146. Which of the following is NOT an input to the Control Communications
process?
Issue Log
Work perfarmance information
Work performance cate
Project management pian147. A Project Manager wants to present a project performance report to
the management. The report needs to captures project results over the last
3 years to see if the performance is improving or deteriorating. Which of
the following reports should the Project Manager use?
Earned value
Status Report
Forecasting Report
Trend Report
148. As part of project stage review, you are presenting project
performance reports to the stakeholders. The reports show that both cos
and schedule variances are positive for the project. What does this indicz
about the current project status?
Project is under budget and behind schedule
Project is aver budget and behind schedule
Project is under budget anc ahead of schedule
Project is over budget end ehead of schedule
149. A Project Manager wants to perform some tests on the product that
might end up destroying the product. What technique can be used to get
around this problem?
Statistical sampling
Regression testing
Automated testing
stability testing150. A project team is in the process of risk tracking and control. The risk
control action defined by the mitigation and contingency plans is being
implemented in accordance with the details of those plans. Who is
responsible for implementing these actions?
Project Manager
Project Team
Risk Owner
Risk Manager
151. In the PDCA cycle, C stands for?
Control
Check
Card
Carryover152. You are managing a project with a total budget of $36,000 to be
finished in one year. You are at the end of the 6th month and the project is
currently on schedule; however, the actual cost of the project is $20,000.
What is the cost variance on the project?
2000
-2000
16000
-8000
153. Which of the following statements is true about control charts ?
Special causes are easier to predict end handle then common causes
‘Common causes are easier to predict and handle then special causes:
4 process is stable if it has only specia| causes
None of the above
154. After awarding contract to one of the sellers, you realize that you have
missed a clause for delay in the contract and want to modify it. How should
you proceed?
‘The contract is legally binding and cannot be changed once signed
‘The Project Manzger should inform the seller about the change in the next meeting
‘The Project Manger should inform the seller about the change through @ formal written
communication
The Project Manager should proceed with Contract Change Control System at his end
Phase 4 - Project Management Financial Assessments Value in Using PERT, Risk Matrices, and Earned Value Management Memo Joseph M. Rivard Professor: Dr. Gonzalez PM620-1003B-01 September 10, 2010