Estimating Guide: Types of Estimates
Estimating Guide: Types of Estimates
Types of Estimates
Several different levels of estimates are used to project construction costs. Each has a
different purpose. The various types may be referred to by different names and some
may not be recognized by all as necessary or definitive, though most estimators will
agree to several basic levels, each of which has its place in the construction estimating
process. In this text, the levels of estimates are broken down as follows.
Each division is further broken down into individual assemblies. Each individual assembly
incorporates several different items into a system that is commonly used in building
construction.
In the Assemblies format, a construction component may appear within more than one
division For example, concrete is found in Division 1- Foundations, as well as in Divisions
2,3 and 12 (see list above). Conversely, each division may incorporate many different
areas of construction, and the labor of different trades.
A great advantage of the Assemblies estimate is that the estimator/designer is able to
substitute one system for another during design development and can quickly determine
the cost differential The owner can then anticipate accurate budgetary requirements
before final details and dimensions are established.
Final design details of the building project are required for a Unit Price estimate. The
Assemblies method does not require such details, but the estimators who use it must
have a solid background knowledge of construction materials and methods, Building
Code requirements, design options, and budgetary restrictions.
The Assemblies estimate should not be used as a substitute for the Unit Price estimate.
While the Assemblies approach can be an invaluable tool in the planning stages of a
project, it should be supported by Unit Price estimating when greater accuracy is
required.
While analyzing the drawings and specifications, the estimator should evaluate the
different portions of the project to determine which areas warrant the most attention
For example, if a building is to have a steel framework with a glass and aluminum frame
skin, then more time should be spent estimating Division 5-Metals, and Division 8-
Doors, Windows and Glass, than Division 6-Wood and Plastics. The estimator should
determine, for a given project, the relative proportions of each component, and
estimating time should be allocated accordingly. More time and care should be given to
estimating those areas, which contribute more to the cost of the project.
Perhaps the best way for an estimator to approach a project is to begin with a clear
mind and a clear desk. Clutter and confusion can have detrimental effects on the
efficiency and accuracy of the estimate.
Labor Overhead
Equipment Profit
Subcontractors Contingencies
Project Overhead
The Paperwork: At the pricing stage of the estimate, there is typically a large amount
of paperwork that must be assembled, analyzed, and tabulated. Generally, the
information contained in this paperwork is covered by the following major categories:
• Quantity takeoff sheets for all general contractor items
• Material supplier written quotations
• Material supplier telephone quotations
• Subcontractor written quotations
• Equipment supplier quotations
• Cost Analysis or Consolidated Cost Analysis sheets
• Estimate Summary sheet
A system is needed to efficiently handle this mass of paperwork and to ensure that
everything will get transferred (and only once) from the quantity takeoff to the Cost
Analysis sheets. Some general rules for this procedure are:
• Write on only one side of any document where possible.
• Code each sheet with a large division number in a consistent place, preferably
near one of the upper corners.
• Use Telephone Quotation forms for uniformity in recording prices received from
any source, not only telephone quotes.
• Document the source of every quantity and price.
• Keep each type of document in its pile (Quantities, Material, Subcontractors,
Equipment) filed in order by division number.
• Keep the entire estimate in one or more compartmented folders.
• When an item is transferred to the Cost Analysis sheet, check it off.
• If gross subcontractor quantities are known, pencil in the resultant unit prices to
serve as a guide for future projects.
All subcontract costs should be properly noted and listed separately. These costs contain
the subcontractor's markups, and will be treated differently from other direct costs when
the estimator calculates the general contractor's overhead, profit, and contingency
allowance.
The Estimate Summary: When the pricing of all direct costs is complete, the
estimator has two choices: all further price changes and adjustments can be made on
the Cost Analysis or Consolidated Estimate sheets, or total costs for each subdivision can
be transferred to an Estimate Summary sheet so that all further price changes, until bid
time, will be done on one sheet.
Unless the estimate has a limited number of items, it is recommended that costs be
transferred to an Estimate Summary sheet. This step should be double-checked, since
an error of transposition may easily occur. Pre-printed forms can be useful, though a
plain columnar form may suffice.
If a company has certain standard listings that are used repeatedly, it would save
valuable time to have a custom Estimate Summary sheet printed with the items that
need to be listed Appropriate column headings or categories for any estimate summary
form are:
• Material
• Labor
• Equipment
• Subcontractor
• Total
As items are listed in the proper columns, each category is added, and appropriate
markups applied to the total dollar values Generally, the sum of each column has
different percentages added near the end of the estimate for indirect costs.
• Sales tax
• Overhead
• Profit
• Contingencies
Since over 50% of the work on a typical building is performed by subcontractors, two
aspects of bid preparation deserve special attention. The first is a clear understanding of
the contractor's scope of work, which is essential, not only to compare the bids of
competing subs, but to ensure that you have included all the items that the
subcontractors may have excluded (such as cutting and patching, temporary protection,
scaffolding, hoisting, etc). The second is that subcontractor prices typically do not arrive
until bid day, which leaves little time to analyze competing bids, and makes last-minute
gaps in coverage difficult to address if you have not done the necessary coordination
with these subs beforehand.