This daily progress report provides status updates across 22 tasks for erecting and assembling a cooling tower over a 15 day period. Key tasks included erecting scaffolding, assembling and erecting spider and spacek components, installing distribution pipes, drift eliminators, fans, screens, and completing the structure with handrails and FRP panels.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
38 views1 page
Daily Work Plan Form
This daily progress report provides status updates across 22 tasks for erecting and assembling a cooling tower over a 15 day period. Key tasks included erecting scaffolding, assembling and erecting spider and spacek components, installing distribution pipes, drift eliminators, fans, screens, and completing the structure with handrails and FRP panels.