Critical Path Analysis For Word
Critical Path Analysis For Word
Objectives
After studying this chapter you should
• be able to construct activity networks;
• be able to find earliest and latest starting times;
• be able to identify the critical path;
• be able to translate appropriate real problems into a
suitable form for the use of critical path analysis.
12.1 Introduction
A complex project must be well planned, especially if a number of
people are involved. It is the task of management to
undertake the planning and to ensure that the various tasks
required in the project are completed in time.
A prepare foundations 7
B make and position door frame 2
C lay drains, floor base and screed 15
D install services and fittings 8
E erect walls 10
F plaster ceiling 2
G erect roof 5
H install door and windows 8
I fit gutters and pipes 2
J paint outside 3
5
A G H
10
7
0 5 8
E
2 10
0 8 2 2 3 Finish
Start B D F I J
15
0
In this network
each activity is represented by a vertex;
Original Shadow
vertices vertices
Start Write down the original vertices and then a second copy of
them alongside, as illustrated on the right. If activity Y A A
must follow activity X draw an arc from original vertex Y B B
to shadow vertex X. (In this way you construct a bipartite C . C
... ....
graph.) .
X X
Step 1 Make a list of all the original vertices which have no arcs Y Y
incident to them.
Step 3 Repeat Steps 1 and 2 until all the vertices have been used.
The use of this algorithm will be illustrated using the first case
study, constructing a garage, from Section 12.1.
The precedence relations are:
D must follow E A A
E must follow A and B B B
C C
F must follow D and G
D D
G must follow E E E
H must follow G F F
I must follow C and F G G
H H
J must follow I I I
These are illustrated opposite. J J
Applying the algorithm until all vertices have been chosen is shown
below.
shown E E
F F
Step 3 - repeat iteration G G
H H
II
J J
J J
A
D F
B E I J
G H
C
8
A D F
0 10
7 2
5
0 2 2 3
Start B E I J Finish
10
0 5 8
G H
C
15
Indicate the duration of the activity on any arc coming from the
vertex representing the activity.
Exercise 12A
1. Use the algorithm to find the activity network for The following chart shows the order of doing the jobs.
the problem in Activity 1. B must be after A C
2. Suppose you want to redecorate a room and put must be after A D
in new self-assembly units. These are the jobs
that need to be done, together with the time each must be after A E
takes: must be after D
time F must be after D and E
activity (in hrs) preceded by
G must be after D and E
J paint outside 3
A D F
0 8
0 10
7 2
B E 5 I Finish
J
0 0 2 2 3
Start
10 G H
8
0 5
C
0
15
The numbers in the top half of each circle will indicate the
earliest possible starting time. So, for activities A, B and C, the
number zero is inserted.
A D F
0 17 8 25
0 10
7 2
E 5 Finish
B I J
0 0 2 7 27 2 29 3 32
Start
32
10 G H
0 17 5 22 8
C
0
15
J 32 3 29
I 29 2 27
F 27 2 25
H 32 8 24
D 25 8 17
G the minimum of 25 5 20 and 24 5 19
A 7 7 0
B 7 2 5
C 27 15 12
0 10
7 2
B E 5 Finish
I J
0 0 2 7 27 2 29 3 32
Start
5 7 27 29 32
10 G H
0 17 5 22 8
19 24
C
0
12 15
The vertices with equal earliest and latest starting times define
the critical path. This is clearly seen to be
A E D F I J.
start times
activity earliest latest float
A 0 0 0
B 0 5 5
C 0 12 12
E 7 7 0
D 17 17 0
G 17 19 2
F
25
25
0
H 22 24 2
I 27 27 0
J 29 29 0
So now you know that if there are enough workers the job can
be completed in 32 days. The activities on the critical path (i.e.
those with zero float time) must be started punctually; for
example, A must start immediately, E after 7 days, F after 25
days, etc. For activities with a non-zero float time there is scope for
varying their start times; for example activity G can be
started any time after 17, 18 or 19 days' work. Assuming that all
the work is completed on time, you will see that this does indeed
give a working schedule for the construction of the garage in the
minimum time of 32 days. However it does mean, for example,
that on the 18th day activities D and C will definitely be in
progress and G may be as well. The solution could well be
affected if there was a limit to the number of workers available,
but you will consider that sort of problem in the next chapter.
Exercise 12B
1. Find the critical paths for each of the activity
networks shown below.
2
(a) C
1
E H
11 1 2
0 7 11 5 4
Start A B F I Finish
7 10 3
5
D G
(c) B E
10
10
7 4
8 0 10 7 6
(b) B E
Start A C G Finish
7 8
10
5 5
8 12
D F
0 3 3
Start A D G Finish
7
5 5 11
C F
7
2. Find the critical path for the activity network in K decide on musical 1 week
Question 4, Exercise 12A.
L organise lighting 1 week
3. Your local school decides to put on a musical.
M dress rehearsals 2 days
These are the many jobs to be done by the
organising committee, and the times they take: N invite local radio/press 1 day
P choose stage hands 1 day
A make the costumes 6 weeks
Q choose programme sellers 1 day
B rehearsals 12 weeks
1
R choose performance dates day
C get posters and tickets printed 3 weeks 2
1
S arrange seating day
D get programmes printed 3 weeks 2
F get rights to perform the musical 2 weeks G V display posters last 3 weeks
preceding preceding
activity duration activities activities activity duration
C, F, J A 7
A 10 -
E B 6
B 4 -
- C 9
C 8 B
B, H D 7
D 6 C
C, J E 3
E 8 I
- F 8
F 5 -
A, I G 4
G 10 A, D
J H 9
H 2 G
E, F I 9
I 4 -
- J 7
J 10 D, F, I
B, H, I K 5
Using the algorithms in Section 12.2, (a) Construct an activity network for the project.
(a) construct an activity network for this
(b) Find:
project;
(i) the earliest starting time of each activity
(b) find a critical path in this activity network;
in the network;
(c) find the latest starting time for each activity.
(ii) the latest starting time of each activity.
(c) Calculate the float of each activity, and
hence determine the critical path.
Chapter 12 Critical Path Analysis
6. Write the major activities, duration time and (b) Find the earliest and latest start time for each
precedence relationship for a real life activity, state the minimum time for
project completion of the work and identify the
with which you are involved. Use the methods in critical path.
this chapter to find the critical path for your (c) Which activities have the greatest float time?
project.
(AEB)
7. Consider the following activity network, in
which the vertices represent activities and the the 9. At 4.30 pm one day the BBC news team hear of a
numbers next to the arcs represent time in weeks: Government Minister resigning. They wish to
prepare an item on the event for that
6
A G evening's 6 o'clock news. The table below
0 4 2
2 D lists the jobs needed to prepare this news
0
Start B 4 H
3
Finish item, the time each job takes and the
2 5 constraints on when the work can commence.
0 E
C 4 7 Time needed Constraints
Job (in minutes)
4 F