1.1 General: Chabahil Road in Kathmandu District, Bagmati
1.1 General: Chabahil Road in Kathmandu District, Bagmati
INTRODUCTION
1.1 GENERAL
The proposed bridge will give market access not only to the people of Chabahil.
There is an urgent need of the construction of bridge lying about this road for all
weather accessibility to Chabahil area and for the continuation as well as growth of
economic activities within the area. The report describe about findings of the
topographical, geological and hydrological studies as well as proposed parameters,
which the Project Team intends to adopt for detailed design of the Dhobi Khola Bridge.
The desk study of bridge site has been prepared with the study
of available regional, district, geological and topographical maps and other relevant
information regarding the bridge site in internet and the available manual and report
in HIST engineering college New Baneshwor, Katmandu and a team of Project and
equipment has been mobilized to the proposed site for field investigation.
1.4 INTRODUCTION OF BRIDGE
According to NBS 2067, the cross drainage structure whose span is more than
6m is termed as bridge and cross drainage structure having span less than 6m is known
as culvert.
The line of bridge should not have serious deviation from the line of
approach road.
It should be in level
The width of bridge should be sufficient to cater future traffic
Bridge should carry standard loading with reasonable factor of safety
Bridge should not produce undue obstruction of stream, hence provide
adequate waterway width
Foundation should be kept on firm (strong) ground and they should be
kept at sufficient depth to avoid damage by floods.
Bridge should fit into surrounding landscape
Bridge should provide passage for services like water pipe, telephone etc
Bridge surface should be similar to road surface
Bridge should be economical in terms of construction and maintenance
According to structure
According to materials
Timber bridge
RCC bridge
Masonry bridge
Steel bridge
Float bridge, Pontoon bridge or Boat bridge
c) Timber bridges.
d) Truss bridges.
e) Plate girder bridges.
Pre-stressed concrete solid slab are used for the span range of 10 to 20 m,
while T-beam slab decks are suitable for span in the range of 20 to 40 m . Single or
multi-cell box girders are preferred for large spans of the order of 30 to 70 m .
Prestressed concrete has been widely used throughout the world for simply
supported, continuous, balanced cantilever and various other types of bridges.
According to some studies it has been observed that the economy associated
with the majority prestressed structural elements would be non-existent if the
elements were not pre-cast. In the present context of Nepal in connection to the use
of prestressed concrete, this aspect needs serious consideration.
b) Timber Bridge
c) Truss Bridge
Steel bridges have become the alternatives of concrete bridges in most of the
bridge construction practices in Nepal, particularly when the span of the bridge is
larger. In the design of steel bridges there are general practices of using mild steel
section. In recent years advances have been made in term of using high strength steel
rolled sections. But many of the suppliers and fabricators prefer mild steel, as it is
easily available. So the steel bridge is not feasible.
Plate girder bridges are constructed with the combination of plates and angles
welded or bolted. There are not good manufactures in Nepal for specified welding.
Bolted girders are feasible but there is difficulty in the transportation of angles and
plates of specified length due to road geometric conditions.
The super structure of the bridge consists of RCC slab with railing details
provided by the Department of Roads. This system covers RCC T-beams with RCC slab
and railing details.
RCC T-beams of span 16.0 m have been provided. The depth of the RCC
beam with slab is about 1.6 m and the web width is 0.3m. The girders are placed at a
distance of 3.50 m center to center. The deck slab is overhung by two cantilevers of
length 1.50m on either side of the main beams. T-beams are laterally supported by
five cross beams along the length. The depth of the cross beam below slab is 1.3 m
having the width of 0.3m.
A RCC slab with a total depth of 160 mm has been provided over main and
cross girders. The carriageway width of the slab is 7.5 m. Total width of deck slab with
two kerbs and footpath on either side is 10.5 m. Deck slab has been designed as one-
way slab for cantilever and one-way for inner slab. A finishing coat of average 75mm
thickness of plain concrete has been provided with a cross slope of 2.5% from center
towards kerb to drain out the rain water.
1.8.4 KERB
The deck slab is provided with kerb at both ends of the cantilever portion. The
depth of kerb is 300mm. the kerb width at the bottom is 600mm
The vertical posts are of RCC type 1.0m high over the kerb top level. The size
of the vertical post is 150mm*150mm. The handrails are of galvanized iron pipes of
50mm diameter. The rails have been placed at the vertical spacing of 206.25mm
center to center. The top handrail is provided 50mm from the top of the handrail.
1.8.6 SUBSTRUCTURE
1.8.7 ABUTMENTS
Abutments consist of abutment cap and back wall. The abutment is of RCC
type. The length of the both left and right abutments is 10.5m. This dimension has
been fixed with the distance between main girders, size of bearings and expansion
joint to be provided. Other requirements such as provision of stoppers have also been
considered while fixing the length of the abutment. The abutment is rectangular in
plan.RCC back wall has been provided monolithic with the RCC abutment to retain the
earth fill at the back. The masonry wing walls on the both sides of left abutment and
monolithic with abutments. In addition, the abutments and wing walls are provided
with weep holes to allow for the drainage. To prevent the clogging of weep holes,
appropriate filter material will be provided at the back of the abutment and the wing
walls. The filter material will be packed with the thickness of 1000 mm with smaller
size against the soil filling and bigger size against the wall as the area is composed of
boulder mix soil.
The abutments cap is the block resting over the top of the abutment. It
provides the immediate bearing surface for the support of the super-structure at the
abutment and disperses the strip loads from the bearings. The abutment caps are of
RCC types. The overall thickness of cap is 0.50m. Abutment cap is over-hanged on front
face. The size of over-hanged of the abutment cap is 0.15m. The adequate
reinforcement have been provided in the abutment caps.
1.8.9 BEARINGS
The bearings have been provided to limit the bearing stresses induced in the
cap within permissible values. In comparison to various other bearings, elastomeric
bearings are proved to be excellent choice for short span simply supported bridges.
Elastomeric bearings are both low in cost for installations and future maintenance. In
addition, removal and replacement is very during maintenance. Elastomeric bearings
have been provided below RCC beam. The appropriate dimension of elastomeric are
shown respective drawings.
The coefficient of expansion is taken as 11.7*10^-6 per oC. the Wabo WA250
compression seal type expansion joint with details as shown in drawing, will be
provided. This type of joints allows a horizontal movement up to 40mm.
1.8.11 FOUNDATION
In the proposed bridge no deep foundation has been envisaged. All the
foundations are open. The height of the both abutments foundation bed from the top
of the abutment cap is 10.5 m. The soil strata, maximum scouring level and bearing
capacity govern the depth of foundation. The open foundation rests on lean concrete
of 10cm thick on gravel. The length and breadth of the open foundation of both
abutments are 10.5 m and 6m.The depth of the footing of both abutments is 4.1m.
1.8.12 MATERIALS
Almost all the members of the bridge superstructure are designed with
concrete grade M25. All the reinforcements are of grade Fe 415. General information
of concrete used in different elements of the bridge is as follows
Table 5.2 Concrete Grade Used for Different Types of Bridge Elements
A. Foundation
Abutment M25
B. Substructure
Abutment M25
C. Superstructure
Since two girders system has been adopted for main girders the distribution of
live load has been determined by Courbon’s method assuming the supports of the
deck slab as unyielding. The center-to-center spacing of the main girder has been fixed
as 3.5 m.
Maximum bending moment and shear force for RCC beams due to the dead
and live loads have been determined at various sections of the RCC beams and for
various elements of the truss with the help of influence line diagram. The detailed
calculations are presented in the design calculation.
Dead load, bending moment in the cross girder has been calculated as
considering trapezoids distribution of weight of the slab and the wearing coat. Cross
girders have been considered as partially fixed beams over two supports.
Live load bending moment in the cross girder has been computed considering
different dispositions of standard loadings over the crossbeam. Similar computation
procedure has been used to determine the shear forces. Calculations of cross girders
are given in structure design calculation.
The interior panel of the deck slab has been designed as single slab. The
moment due to live load has been computed using Pigeaud’s Curves.
On both sides of the outer portion of the main beam the slab functions as
cantilever structure. So, this portion of slab has been designed accordingly. Special
consideration has been made while designing the cantilever slab at the end portions
as well as at other portions along the length of the bridge. In addition, distribution
reinforcement have been provide assuming the summation of 0.3 times the maximum
live load bending moment and 0.2 times the dead load bending moment in accordance
with IRC 21-2014 Clause 305.18.1.This is applicable to the cantilever portion of the
slab also.
1.8.16 ABUTMENTS
Abutments have been designed as RCC column. In the design of abutments the
following load cases were considered and the worst case was adopted.
It provides the direct access for the area influenced to the dhobi khola corridor
. There is an urgent need of the construction of bridges lying about this road for all
weather accessibility to isolated villages and for the continuation as well as growth
of economic activities within the area.
The present study has been carried out to find out the present condition of
the bridge site, which shall serve as the base for taking important decisions regarding
execution of this project. During the field visit inquiry was made at bridge site to
collect the following information
Availability, quality and location of the nearest quarries for boulders, sand
and concrete aggregates.
The proposed bridge site lies along Dhobikhola along chabahil Road in
Kathmandu District, Bagmati Zone, and Central Development Region.
Geographic location :
Easting : 336797 m
CHAPTER 2
METHODOLOGY
2.1 GENERAL
For efficient and proper completion of the job, the whole work has been
subdivided in the following three phases: Desk Study, Field work and Data
interpretation, Design & Drawing and report preparation work. Separate teams has
done all works successfully and the total Reporting work.
In this phase the plans of action formulated during the desk study were carried
out. Various teams comprising of experts in their field were dispatched so that the
information gathered were relevant, accurate and sufficient. The following specific
jobs were carried out
Fixing the bridge axis.
Hydrological study.
The design work involved the design of a bridge based on the design
parameters collected during the field work and the relevant standard documents.
Design of bridge is done as per NRS-2045 and the relevant IRC standards. The
detailed design calculation is presented in this report.
Google view of the proposed bridge site
CHAPTER 3
HYDROLOGICAL STUDY
3.1 GENERAL
The hydrological study of the bridges at Dhobi Khola links the road to dhobi
khola corridor at left and right bank. The hydrological study has been carried out to
find out the hydrological design parameters required for the design of bridge.
Maximum design discharge for 100 yrs return period, Linear water way, Normal and
maximum scour depths, and vertical clearance and afflux are main hydrological
parameter required for design and are determined on basis of in depth study.
The Dhobi Khola is a perennial river. The catchment area of the Khola at
proposed bridge site is found to be 21.122 Km2 according to basin area delineation
in topographic map. Elevation of the river varies from 2682 m msl to 1292 m msl
along the length of the river and length is about 10.9 km. The catchment area is
covered with more than 75% of core city, Forest, agriculture land and other lands. The
average slope of the river from its origin to the proposed bridge site is about 0. 12752
3.3 RAIN FALL DATA AROUND THE CATCHMENT
DHM data of 24 hours Maximum rainfall are generated and shown station
name:
Station : Budhanilkantha
RAINFALL
YEAR
(mm)
1997 76
1998 82
1999 69
2000 76
2001 50.4
2002 159
2003 147.4
2004 71.4
2005 92.2
2006 47.8
2007 90.2
2008 106
2009 78
2010 66.2
2011 50.4
2012 81.4
2013 60
2014 100.2
Fig : Catchment Area
There are various method to analysis of hydrological data. Some of them are
as follows:
3.5 DESIGN DISCHARGE
Since the bridge medium type and the catchment are quite big
the discharge for return period of 100 years is recommended for design discharge. The
maximum discharge using above method for return period of 100 years are
summarized below in table 2.
Table 2: Summary of flood Discharge.
Method Discharge m3/s for 100 year
The table above shows that the discharge calculated by Rational method is
maximum and discharge calculated by Fuller method is minimum. So the discharge
calculated by this method is near to the authentic. Considering the catchment
characteristics and hilly regions in Nepal and the flood generally seen exceeding the
design flood in existing bridge, the discharge calculated from Modified Dickens
method is adopted for design discharge. So the design discharge is adopted 106.72
m3/s.
For the design flood of 106.798 cumecs, the high flood level is RL
1292.996 m.
The site plan was prepared in 1:1000 scale and presented. The following
features are shown in the site plan.
Three comparable sites were chosen for the study and comparison. The
chosen alternatives bridge sites were mainly based on the following consideration.
Span length
Straightness of the river
River channel type, bed and bank material characteristics
Availability of construction material
Alignment of road/approach to the bridge from both sides of the river
Condition of the riverbanks etc.
4.3 AVAILABILITY OF CONSTRUCTION MATERIALS AND MANPOWER
Local construction materials like: gravel, stone and wood are easily available
near the site. The material like steel, cement, gravel, stone and wood should be
transported from nearest market. Unskilled labors and skilled labors have to supply
from the various companies.
CHAPTER 5
DESIGN OF BRIDGES
Based on the above considerations RCC T-Beam bridge has been selected for
the present case.
3 to 30 600
Above 30 to 300 900
Above 300 to 3,000 1,200
Above 3,000 1,500
21
FINAL REPORT
DETAILED ENGINEERING SURVEY, SOIL INVESTIGATION, HYDROLOGICAL STUDY AND DETAILED DESIGN OF BRIDGE (S); DHOBI KHOLA BRIDGE
For the design of bridge IRC Class A loading is taken. In order to compute
maximum stresses in any member of a bridge the following loads have been
considered:
Dead load - This is the self-weight of the structure and any permanent
loads fixed therein.
Live load - The proposed bridge has been designed for IRC Class A
loading .
Impact effect - For RCC bridges IRC Class A loading the impact
fraction has been determined as described in IRC Code.
d) Wind load - Super structure has been designed for wind load.
Velocity and intensity of wind pressure are taken from IRC Code.
e) Longitudinal forces - The longitudinal forces such as frictional
resistance of expansion bearing, braking or tractive force has been
considered in design. These forces have been calculated as specified in
IRC Code.
5.4 DESIGN
5.4.2 SUPERSTRUCTURE
The standard design and drawing for 16 m span RCC Cast In Sturbridge has
been used which is provided by DoR, Bridge Branch.
22
FINAL REPORT
DETAILED ENGINEERING SURVEY, SOIL INVESTIGATION, HYDROLOGICAL STUDY AND DETAILED DESIGN OF BRIDGE (S); DHOBI KHOLA BRIDGE
5.4.3 SUBSTRUCTURE
The abutment will be supplement by RCC back wall and RCC wing walls
monolithic with the RCC abutment to support the approach slab and to contain the
earth fill at the back. In addition, the abutment and wing walls will be provided with
weep holes to allow for the drainage. To prevent clogging of weep holes, appropriate
filter material will be provided at the back of the abutments and the wing walls. The
filter material will be well packed to a thickness of 500 mm with smaller size against
the soil filling and bigger size against the wall.
Design of Abutment
As the abutment supports one end of the bridge span and at the same time
supports the embankment upon which the approach roadway to the bridge rests.
Abutment Cap
Abutment cap is block resting over the top of the abutment stem. It provides
the immediate bearing surface to support the superstructure and disperses the
concentrated loads from the bearing to the abutment stem more evenly. The
abutment caps will be of RCC type.
Bearings
23
FINAL REPORT
DETAILED ENGINEERING SURVEY, SOIL INVESTIGATION, HYDROLOGICAL STUDY AND DETAILED DESIGN OF BRIDGE (S); DHOBI KHOLA BRIDGE
The bridge serves the inhabitants within the influence area of the river around
villages and the people of many Metropolitan City of Kathmandu District throughout
the whole year without any obstruction for transportation and link to Dhobi Khola
Corridor Left to Right Bank after upgrading of road into gravel standard. After
construction of bridge, agricultural market of this area will be promoted. There is an
urgent need of the construction of bridges lying about this road for all weather
accessibility to isolated villages and for the continuation as well as growth of economic
activities within the area.
24
FINAL REPORT
DETAILED ENGINEERING SURVEY, SOIL INVESTIGATION, HYDROLOGICAL STUDY AND DETAILED DESIGN OF BRIDGE (S); DHOBI KHOLA BRIDGE
REFFERENCES
1. Nepal Road Standards (First Revision, 2045, Department of roads,
Kathmandu, 2045
2. IRC: Special Publication 13, Guidelines for the design of small bridges and
culverts, New Delhi, 1986.
3. IRC:21-2014, Standard Specification and Code of Practice for Road Bridges,
Section III-Cement concrete (Plain and Reinforced), First Revision
4. IRC:6-2014, Standard Specification and Code of Practice for Road Bridges,
Section II-Load and stress (Third Revision)
5. IRC:78-2014, Standard Specification and Code of Practice for Road Bridges,
Section VII-Foundation and Substructures (First Revision)
6. IRC:5-2014, Standard Specification and Code of Practice for Road Bridges,
Section I-General Features of Design (Sixth Revision)
7. IS Code 456-2000
8. Swami Saran, Analysis and Design of Substructure.
9. DHM Climatological Records of Nepal, Department of Hydrology and
Metrology.
10. A.C. Sarkar, A Seismic Design of Bridge.
11. D. Johnson Victor, Essential of Bridge Engineering
12. SP Bindra. Principle and Practice of Bridge Engineering
13. Methodologies for Estimating Hydrologic Characteristics of Un-gauged
catchments, column I, Main Report, 1990
14. DHM 1998 Hydrological records of Nepal
15. IS 1893:1984, Criteria for earthquake resistant design of structures.
16. IS 800:1962, Criteria of Practice for use of structural steel in General Building
Construction.
17. S Punnuswami, Bridge Engineering
18. Wayne Teng, Foundation Design
19. K.R. Arora, Soil Mechanics and Foundation Engineering
20. Alam Sigh, Moder Geotechnical Engineering
21. R.V. Farraday/F.G. Charlton, Hydraulic factors in Bridge Design
22. K.N. Mutreja, Applied Hydrology
25