Institute of Shipbuilding Technology Implant Training
Institute of Shipbuilding Technology Implant Training
Institute of Shipbuilding Technology Implant Training
CHAPTER-1 INTRODUCTION
-WAREHOUSE VERNA
The two Shipyards of Chowgule (one at Loutulim and the other at Rassaim) are
located at a distance of 7 k.m. from each other.They have a Plate preparation and
Pipe bending Plant which is situated at Gadegally.Three Goliath Cranes are present
(two at Loutulim Shipyard & one at Rassaim shipyard) each of 60 Tons capacity and
Two tower cranes are present, each one at the two shipyards.
An Investment of Approximately INR 110 Crores (INR 1100 Million) was made for
creating the SHIPBUILDING DIVISIONS. This is apart from land and other basic
Infrastructure that already existed.
It has been estimated that the Chowgule shipbuilding divisions of both Rassaim and
Loutolim can deliver up-to 9 Ocean going multipurpose general cargo vessels per
year of around 5500 DWT each and One Offshore Patrolling Vessel Hull structure
which is of 2450 DWT.
For the past several Years, CCPL have been participating in various Trade shows such
as INMEX (Mumbai, India), SMM (Hamburg), Gulf Maritime Expo (Sharjah), Posidonia
2010 (Greece), Korea Marine tech (South Korea), Sea Japan (Japan).
The Chowgule Company Pvt Ltd is ISO 9001:2008 Quality System Compliant.
The Loutolim yard is the main Yard for ship Construction since it has an Estimated
Area of about 42,000 square meters which is larger than the area of the Chowgule
yard at Rassaim.Covered shed for hull block fabrication and manufacturing of cargo
hatch covers are present at the Loutulim Yard. It has an End Launching Sequence Bay
with a Slip-way Rail length of about 220 meters.
Welding machines
Inverters - 65 nos.
Rectifiers - 48 nos.
TIG - 6 nos.
Gauging - 3 nos.
Area Statement:
13. Floor area of Temporary Structures(shed & containers).a)Lower floor 3247.80 sq.m
16. Floor Area ratio of Temporary structures (shed and containers) 6.87 %
Stations :1A-6A
Work on Stations:
PRE-FABRICATION
It is a process in which all the parts required for fabrication of the Double bottom
tanks are fabricated.All the Pre-Fabrication work is carried out on station 1A,2A and
3A. This altogether takes 5 days.
Diagonal check
Dry survey.
Diagonal Check.
Dry Survey.
Dry Survey.
Flat welding
Dry survey.
Vertical welding.
Dry survey.
At this Station the Double bottom Tank is Toppled by using EOT crane (70+32).
This is done in order to weld in Flat position,since its difficult to weld in Over
head position.
This is whole process that is being carried out in the Chowgule Shipyard in Loutulim
in order to Fabricate a Double Bottom.
Stations :1B-6B
Work on Stations:
1. Station 1B (prefabrication)
2. Station 2B (prefabrication)
3. Station 3B (prefabrication)
4. Station 4B (Assembly)
Erection Sequence:
1. Side shell
2. Frames
3. Brackets
4. Main deck
5. Raised deck
6. Inner shell
Side shell is shifted to station 4B. After fitting frames, flat welding is carried out
(kx-200). Water level is to be done and then vertical welding is carried out. Inner
shell is to be placed and fitting is started. Dry survey is carried out. This takes place in
4 days.
Station 5B
Flat welding is done. Hatch combings are fitted and welding hooks are welded. So
the section can be lifted by crane and then toppled at station 6. The dry survey is
carried out.
Station 6B
Then supporting Flat bars are fitted which helps during erection. Then dry survey is
carried out.
Ongoing Projects:
Specification
The S-class is 105 meters (344 ft 6in) long with a displacement of 2350 tonnes.
Features include Integrated Bridge System (IBS), Integrated Machinery Control
System (IMCS), Power Management System (PMS) and High Power External fire
Fighting System. They are designed to carry one twin engine Light Helicopter and five
high speed boats including two pal-finger QRIBs for fast boarding operations, search
and rescue, law enforcement and Maritime patrol. This S-class vessel is also capable
of carrying Pollution Response Equipment (PRE) to combat oil spill contamination at
Seas.
General Characteristics:
Block fabrication:
The blocks at the Chowgule shipyard are Constructed in 2 ways. Block
10,20,30,80,100 are constructed in upside down manner on a flat leveled skid
prepared by cutting flat angled bars which are marked at an equal level using the
water level method, the platform deck are fist fitted on the skids and then all the
structural members are fitted step by step for example: bulk