The document describes an extra assignment problem for project management. It provides a process with 9 tasks and their optimistic, most likely, and pessimistic durations. It asks to (a) develop the critical path diagram, (b) determine the critical path duration, (c) determine slack times, and (d) calculate the probability of finishing in less than 53 days. The solution shows the critical path diagram with a duration of 54 days. It lists the slack times as 0 for critical tasks and up to 19.7 days for non-critical tasks. It calculates the probability of finishing in less than 53 days as 43.8%.

Uploaded by

Osama Mohsen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
126 views1 page

AdditionalAsstProb Lecture02 ProjMgmt

The document describes an extra assignment problem for project management. It provides a process with 9 tasks and their optimistic, most likely, and pessimistic durations. It asks to (a) develop the critical path diagram, (b) determine the critical path duration, (c) determine slack times, and (d) calculate the probability of finishing in less than 53 days. The solution shows the critical path diagram with a duration of 54 days. It lists the slack times as 0 for critical tasks and up to 19.7 days for non-critical tasks. It calculates the probability of finishing in less than 53 days as 43.8%.

Uploaded by

Osama Mohsen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Extra Assignment Problem for Project Management

Your company had a process with tasks as shown:


Immediate
Task Predecessors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
(a) Develop the critical path diagram for the process.
(b) Determine the duration of the critical path.
(c) Determine slack times for all activities.
(d) What is the probability of finishing the project in less than 53 days?

SOLUTION

a + 4m + b
ET =
(a) 21 32 6
(d)
⎛b−a⎞
2
C(14) E(11)
7 21 32 36
Most Exp. σ2 =⎜ ⎟
⎝ 6 ⎠
A(7) 12 19 H(4) Task Pred. Opt. Likely Pess. Time Var.
7 D(5) F(7) 36 A None 3 6 15 7 4
32 54 B None 2 4 14 5.3
25
I(18) C A 6 12 30 14 16
54 D A 2 5 8 5
5.3 16.3 E C 5 11 17 11 4
B F D 3 6 15 7
G(11)
(5.3) G B 3 9 27 11
25 36
H E,F 1 4 7 4 1
I G,H 4 19 28 18 16
(b) Duration = 54 Days
Sum the variance along
the critical path:
(c) Task Slack 4+16+4+1+16=41
A 0
B 19.7 Z=
D - TE
∑σ
2
C 0 D - TE 53-54
Z = = = -0.156
cp


D 13
E 0
p(t < D)
σcp2 41
F 13 D=53
G 19.7 p(Z < -0.156) = 0.438
H 0 TE = 54 t = 43.8 %
I 0