Managing Risk in Projects What's New
Managing Risk in Projects What's New
Humans have been undertaking projects for millennia, with more or less formality, and
with greater or lesser degrees of success. We have also recognised the existence of
risk for about the same period of time, understanding that things don’t always go
according to plan for a range of reasons. In relatively recent times these two
phenomena have coalesced into the formal discipline called project risk management,
offering a structured framework for identifying and managing risk within the context of
projects. Given the prevalence and importance of the subject, we might expect that
project risk management would be fully mature by now, only needing occasional minor
tweaks and modifications to enhance its efficiency and performance. Surely there is
nothing new to be said about managing risk in projects?
While it is true that there is wide consensus on project risk management basics, the
continued failure of projects to deliver consistent benefits suggests that the problem of
risk in projects has not been completely solved. Clearly there must be some mismatch
between project risk management theory and practice, or perhaps there are new
aspects to be discovered and implemented, otherwise all project risks would be
managed effectively and most projects would succeed.
So what could possibly remain to be discovered about this venerable topic? Here are
some suggestions for how we might do things differently and better, under four
headings:
1. Principles 3. People
2. Process 4. Persistence
There are two potential shortfalls in the way most project teams understand the concept
of risk. It is common for the scope of project risk management processes to be focused
on managing possible future events which might pose threats to project cost and
schedule. While these are undoubtedly important, they are by no means the full story.
The broad proto-definition of risk as “uncertainty that matters” encompasses the idea
that some risks might be positive, with potential upside impacts, mattering because they
could enhance performance, save time or money, or increase value. And risks to
objectives other than cost and schedule are also important and must be managed
proactively. This leads to the use of an integrated project risk process to manage both
threats and opportunities alongside each other. This is more than a theoretical nicety: it
maximises a project’s chances of success by intentionally seeking out potential upsides
and capturing as many as possible, as well as finding and avoiding downsides.
A second equally vital omission is the lack of a “post-project review” step in most risk
processes. This is linked to the wider malaise of failure to identify lessons to be learned
at the end of each project, denying the organisation the chance to learn from its
experience and improve performance on future projects. There are many risk-related
lessons to be learned in each project, and the inclusion of a formal “Post-project Risk
Review” will help to capture these, either as part of a more generic project meeting or as
a separate event. Such lessons include identifying which threats and opportunities arise
frequently on typical projects, finding which risk responses work and which do not, and
understanding the level of effort typically required to manage risk effectively.
The use of approaches based on emotional literacy to address the human behavioural
aspects of managing risk in projects is in its infancy. However some good progress has
been made in this area, laying out the main principles and boundaries of the topic and
developing practical methods for understanding and managing risk attitude. Without
taking this into account, the project risk management process as typically implemented
is fatally flawed, relying on judgements made by people who are subject to a wide range
of unseen influences, and whose perceptions may be unreliable with unforeseeable
consequences.
Even where a project team has a correct concept of risk that includes opportunity and
addresses the wider context, and if they ensure that risk responses are implemented
effectively and risk-related lessons are learned at the end of their project, and if they
take steps to address risk attitudes proactively – it is still possible for the risk process to
fail! This is because the risk challenge is dynamic, constantly changing and developing
throughout the project. As a result, project risk management must be an iterative
process, requiring ongoing commitment and action from the project team. Without such
persistence, project risk exposure will get out of control, the project risk process will
become ineffective and the project will have increasing difficulty in reaching its goals.
Insights from the new approach of “risk energetics” suggest that there are key points in
the risk process where the energy dedicated by the project team to managing risk can
decay or be dampened. A range of internal and external Critical Success Factors
(CSFs) can be deployed to raise and maintain energy levels within the risk process,
seeking to promote positive energy and counter energy losses. Internal CSFs within the
control of the project include good risk process design, expert facilitation, and the
availability of the required risk resources. Equally important are external CSFs beyond
the project, such as the availability of appropriate infrastructure, a supportive risk-aware
organisational culture, and visible senior management support.
So perhaps there is still something new to be said about managing risk in projects.
Despite our long history in attempting to foresee the future of our projects and address
risk proactively, we might do better by extending our concept of risk, addressing weak
spots in the risk process, dealing with risk attitudes of both individuals and groups, and
taking steps to maintain energy levels for risk management throughout the project.
These simple and practical steps offer achievable ways to enhance the effectiveness of
project risk management, and might even help us to change the course of future history.
Note: All of these issues are addressed in the book “Managing Risk in Projects” by David
Hillson, published in August 2009 by Gower (ISBN 978-0-566-08867-4) as part of the
Fundamentals in Project Management series. For information about the book, visit
http://www.gowerpublishing.com/default.aspx?page=641&calcTitle=1&isbn=9780566088674&a
mp;lang=cy-GB.
Author