0% found this document useful (0 votes)
237 views27 pages

Rusty Estimates

The document contains 14 tables providing information about concrete mixtures, quantities of cement, sand and gravel for pipes of different diameters, quantities of cement and sand for concrete hollow blocks and plaster, quantities of steel reinforcement bars of different diameters and lengths, and number of lateral ties for steel bar reinforcement in columns. The tables provide specifications for constructing pipes, concrete hollow blocks, plaster and reinforced concrete columns using different mixtures of cement, sand, gravel and steel bars.

Uploaded by

Kim Sapong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
237 views27 pages

Rusty Estimates

The document contains 14 tables providing information about concrete mixtures, quantities of cement, sand and gravel for pipes of different diameters, quantities of cement and sand for concrete hollow blocks and plaster, quantities of steel reinforcement bars of different diameters and lengths, and number of lateral ties for steel bar reinforcement in columns. The tables provide specifications for constructing pipes, concrete hollow blocks, plaster and reinforced concrete columns using different mixtures of cement, sand, gravel and steel bars.

Uploaded by

Kim Sapong
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 27

Table 1 - 2.

Concrete Proportion
Class Cement in Bag
Proportion
Mixture 40 kg
AA 1 1 1⅟2 3 12
A 2 1 2 4 9
B 3 1 2⅟2 5 7.5
C 4 1 3 6 6

Table 1 - 6. Quantity of Cement, Sand and Gravel per Pipe


Diameter Cement in Bags
Sand Gravel
in cm Mixture
D d A B m³ m³
21 15 0.152 0.127 0.009 0.018
26 20 0.195 0.163 0.011 0.022
33 25 0.328 0.274 0.018 0.037
39 30 0.436 0.363 0.025 0.050
50 40 0.635 0.530 0.036 0.072
60 50 0.779 0.650 0.044 0.088
78 60 1.755 1.463 0.098 0.196
90 70 2.260 1.883 0.126 0.252
100 80 2.538 2.115 0.141 0.282
110 90 2.826 2.356 0.157 0.314
120 100 3.110 2.595 0.173 0.346
144 120 4.482 3.735 0.249 0.498
174 150 5.500 4.583 0.306 0.612

Table 2 - 2. Quantity of Cement For CHB Mortar per Square Meter


Size of CHB Number Bags of Cement
cm per m² A B
10 x 20 x 40 12.5 0.762 0.522
15 x 20 x 40 12.5 1.526 1.018
20 x 20 x 40 12.5 2.26 1.500

Table 2 - 3. Quantity of Cement and Sand per 100 Blocks


Size of CHB Number Bags of Cement
cm per m² A B
10 x 20 x 40 12.5 6.336 4.176
15 x 20 x 40 12.5 12.15 8.104
20 x 20 x 40 12.5 18.072 12.000

Table 2 - 4. Quantity of Cement and Sand for Plaster per Square Meter
Mixture Cement in Bags
Class 8 mm 12 mm 16 mm 20 mm
A 0.144 0.216 0.288 0.360
B 0.096 0.144 0.192 0.240
C 0.072 0.108 0.144 0.180
D 0.060 0.090 0.120 0.150
SAND (m³) 0.008 0.012 0.016 0.02

Table 2 - 12. Quantity of Cement and Sand on a Stone Rip - Rap per Cubic Meter
Cement in Bags
Stone Sand
Class Grout Mixture m³
A B C
Class A 2.574 1.716 1.287 0.143
Class B 2.448 1.620 1.214 0.135
Class C 2.232 1.488 1.116 0.124
Class D 1.944 1.296 0.972 0.108

Table 3 - 1. Standard Weight of Plain or Deformed Round Steel bars in Kilogram


Length of steel bars in meters
Ø (mm)
5 6 7.5 9 10.5 12 13.5
8 1.98 2.37 2.96 3.56 4.15 4.74 5.33
10 3.08 3.7 4.62 5.54 6.47 7.39 8.32
12 4.44 5.33 6.66 7.99 9.32 10.66 11.99
13 5.21 6.25 7.83 9.38 10.94 12.5 14.07
16 7.9 9.47 11.84 14.21 16.58 18.95 21.32
20 12.33 14.8 18.5 22.19 25.69 29.59 33.29
25 19.27 23.12 28.9 34.68 40.46 46.24 52.02
28 24.17 29 36.25 43.5 50.75 58 65.25
30 27.75 33.29 41.62 49.94 58.26 66.59 74.91
32 31.57 37.88 47.35 56.82 66.29 75.76 85.23
36 39.96 47.95 59.93 71.92 83.91 95.89 107.88

Table 3 - 5 LENGTH OF REBAR FOR CHB IN METERS


SPACING VERTICAL SPACING HORIZONTAL
(m) LAYER
PER CHB PER SQ. m PER CHB PER SQ. m
0.4 0.235 2.93 2 0.268 3.3
0.6 0.171 2.13 3 0.172 2.1
0.8 0.128 1.6 4 0.138 1.72

TABLE 3-4 AREAS OF GROUPS OF REINFORCING STEEL BARS


Bar Number of Bars (mm²)
Dia. (mm) 1 2 3 4 5 6 7 8
6 28 57 85 113 141 170 198 226
8 50 101 151 201 251 302 352 402
10 79 157 236 314 393 471 550 628
12 113 226 339 452 565 679 792 905
16 201 402 603 804 1005 1206 1407 1608
20 314 628 942 1257 1571 1885 2199 2513
24 491 982 1473 1963 2454 2945 3436 3927
32 804 1608 2412 3216 4021 4825 5629 6433
40 1256 2513 3769 5026 6283 7539 8796 1005

TABLE 3-8 NUMBER OF LATERAL TIES IN ONE STEEL BAR


AND QUANTITY PER METER LENGTH OF COLUMN
Lateral Number of Length of Number of Cut in One
Ties Lateral ties Ties with Steel Bar Length
Spacing per M. ht. Hook & Bend 5 M. 6 M. 7.5 M. 9 M. 12 M.
15 6.70 60 X 10 X 15 20
70 7 X X X 17
20 5.15 80 6 X X 11 15
85 X 7 X X 14
25 4.13 90 X X 8 10 13
95 5 X X X X
30 3.43 100 5 6 X 9 12
105 X X 7 X X
35 3.00 110 X X X 8 X
115 X 5 X X X
40 2.64 120 4 5 X X 10
125 4 X 6 X X
45 2.36 130 X X X X 9
135 X X X X X
50 2.14 140 X 4 X X X
145 X 4 5 6 X
55 1.96 150 X 4 5 6 8
160 3 X X X X
60 1.81 170 X X X 5 7
180 X X 4 5 X
190 X 3 X X 6
200 X 3 X X 6

Table 3-9 NUMBER OF SPIRAL REINFORCING BARS PER METER HEIGHT

Column Pitch No. of Turn Number of Steel Bars from a


Dia. Cm. cm. per Meter ht. 6.00 m. 9.00 m 12.00 m.
5 21 2.604 1.706 1.269
30 6.25 17 2.108 1.381 1.027
7.5 14.3 1.778 1.165 0.866
5 21 2.894 1.896 1.41
32.5 6.25 17 2.342 1.535 1.141
7.5 14.3 1.975 1.294 0.962
5 21 3.183 2.085 1.55
35 6.25 17 2.577 1.688 1.255
7.5 14.3 2.172 1.423 1.058
5 21 3.472 2.275 1.692
37.5
37.5 6.25 17 2.811 1.842 1.393
7.5 14.3 2.37 1.524 1.154
5 21 3.762 2.465 1.833
40 6.25 17 3.045 1.995 1.484
7.5 14.3 2.567 1.682 1.251
5 21 4.051 2.654 1.974
42.5 6.25 17 3.281 2.146 1.598
7.5 14.3 2.765 1.812 1.347
5 21 4.34 2.844 2.115
45 6.25 17 3.513 2.302 1.712
7.5 14.3 2.962 1.94 1.443
5 21 4.63 3.033 2.256
47.5 6.25 17 3.748 2.455 1.826
7.5 14.3 3.159 2.07 1.539
5 21 4.919 3.223 2.397
50 6.25 17 3.982 2.609 1.94
7.5 14.3 3.357 2.199 1.635
5 21 5.498 3.602 2.678
55 6.25 17 4.525 3.017 2.253
7.5 14.3 3.752 2.524 1.888
5 21 6.077 2.981 2.96
60 6.25 17 4.919 3.223 2.396
7.5 14.3 4.146 2.717 2.02
5 21 7.234 4.74 3.524
70 6.25 17 5.856 3.837 2.853
7.5 14.3 4.936 3.234 2.405
5 21 8.391 5.498 4.088
80 6.25 17 6.793 4.451 3.31
7.5 14.3 5.726 3.752 2.79
5 21 9.549 6.256 4.652
90 6.25 17 7.73 5.064 3.766
7.5 14.3 6.366 4.171 3.101
5 21 10.706 7.014 5.216
100 6.25 17 8.667 5.678 4.222
7.5 14.3 7.137 4.676 3.477

TABLE 3-10 QUANTITY OF REINFORCING STEEL BARS IN A ONE-WAY REINFORCED CONCRETE SLAB
Bar Spacing Number of Steel Bars per Square Meter
cm 6.00 m 7.50 m 9.00 m 12.00 m
10.0 3.764 2.937 2.421 1.769
12.5 3.062 2.381 1.934 1.427
15.0 2.584 2.004 1.636 1.197
17.5 2.232 1.726 1.407 1.033
20.0 1.980 1.528 1.258 0.194
22.5 1.786 1.369 1.109 0.810
25.0 1.627 1.250 1.014 0.736

TABLE 3-11 QUANTITY OF TIE WIRE ON A ONE WAY REINFORCED CONCRETE SLAB IN KGS. PER SQUARE METER

Bar Spacing Length of Steel Bars


in 6m 7.5 m 9m 12 m
Centimeters 0.3 0.4 0.3 0.4 0.3 0.4 0.3 0.4
10 0.474 0.632 0.462 0.616 0.46 0.614 0.448 0.598
12.5 0.316 0.422 0.307 0.409 0.295 0.394 0.293 0.391
15 0.228 0.303 0.217 0.289 0.214 0.285 0.207 0.276
17.5 0.168 0.224 0.162 0.216 0.158 0.21 0.153 0.204
20 0.132 0.175 0.126 0.168 0.125 0.167 0.12 0.16
22.5 0.11 0.147 0.102 0.135 0.099 0.132 0.095 0.126
25 0.089 0.118 0.086 0.114 0.081 0.108 0.077 0.103

TABLE 3-12 QUANTITY OF STEEL BARS IN A TWO WAY


REINFORCED CONCRETE SLAB PER SQUARE METER
Bar Spacing Number of Steel Bars
in per Square Meter
Centimeters 6.00 M 7.50 M 9.00 M 12.00 M
10.0 4.369 3.337 2.772 2.022
12.5 3.603 2.662 2.245 1.635
15.0 3.221 2.296 1.921 1.382
17.5 2.647 2.025 1.65 1.196
20.0 2.360 1.775 1.461 1.056
22.5 2.168 1.610 1.312 0.907
25.0 1.977 1.466 1.217 0.862

TABLE 3-13 TIE WIRE IN A TWO-WAY REINFORCED CONCRETE


SLAB IN KILOGRAMS PER SQUARE METER
Bar Spacing Length of Steel Bars
in 6.00 7.50 9.00 12.00
Centimeters 0.30 0.40 0.30 0.40 0.30 0.40 0.30 0.40
10.0 0.592 0.896 0.648 0.863 0.648 0.864 0.596 0.794
12.5 0.416 0.554 0.420 0.560 0.431 0.574 0.421 0.561
15.0 0.350 0.466 0.307 0.409 0.257 0.343 0.297 0.396
17.5 0.247 0.330 0.231 0.308 0.223 0.298 0.206 0.275
20.0 0.174 0.232 0.171 0.227 0.173 0.231 0.163 0.217
22.5 0.168 0.224 0.150 0.200 0.148 0.198 0.130 0.173
25.0 0.142 0.189 0.134 0.178 0.114 0.152 0.116 0.155

STUDS
Board Foot of Studs and Ceiling Joist per Square Meter
Spacing
Dimension
Dimension 0.40 x 0.40 0.40 x 0.60 0.60 x 0.60
(16" x 16") (16" x 24") (24" x 24")
2" x 2" 6.417 5.445 4.474
2" x 3" 9.625 8.312 6.711
2" x 4" 12.833 10.891 8.948

SCAFFOLDING
Column (Board Foot) Beam (Board Foot) Slab

Size Horizontal Vertical Horizontal


Vertical per per Brace per per per Board Foot
Meter Meter Meter Meter Meter per Square
Height Height Height Height Height Meter
2" x 2" 4.67 21.00 11.67 4.00 4.67 6.10
2" x 3" 7.00 31.67 17.50 6.00 7.00 9.10
2" x 4" 9.33 42.22 23.33 8.00 9.33 12.10

TABLE 10. Corrugated Roofing Sheet Effective Coverage


10' End Lap and 2 Corr. 12' End Lap and 2 Corr.
Size Side Lap(>30⁰) Side Lap(<30⁰)
32" x 6' 1.03 m² 1.03 m²
32" x 7' 1.29 m² 1.255 m²
32" x 8' 1.5 m² 1.465 m²
32" x 12' 2.335 m² 2.3 m²
Cement in Bag Sand Gravel
50 kg m³ m³
9.5 0.50 1.00
7 0.50 1.00
6 0.50 1.00
5 0.50 1.00

Gravel


0.018
0.022
0.037
0.050
0.072
0.088
0.196
0.252
0.282
0.314
0.346
0.498
0.612

Cement Sand
B m³
0.522 0.0435
1.018 0.0844
1.500 0.1250

Cement Sand
B m³
4.176 0.348
8.104 0.675
12.000 1.000

20 mm 25 mm
0.360 0.450
0.240 0.300
0.180 0.225
0.150 0.188
0.02 0.025

Sand

0.143
0.135
0.124
0.108

9 10
254 283
452 503
707 785
1017 1131
1809 2011
2827 3142
4418 4909
7237 8042
1131 1257
ARE METER
LABOR ESTIMATE:
1. Concreting of plain flooring: 2 men can pour 1.2 m³ conc./day
2. Concreting of R.C. flooring: 2 men can pour 0.84 m³ conc./day
3. Concreting of column and beam: 2 men can pour 0.50 m³ conc./day
4. Finishing of flooring(rough): 2 men finish 72 m²/day
5. Finishing of CHB joints: 2 men finish 420 pc/day
6. Plastering of CHB: 2 men plasters 8 m²/day
7. Laying of CHB : 2 men lay 100 pc/day
8. Breaking old R.C. flooring: 2 men break 0.30 m³/day
9. Laying of Glazed tiles 6"x6": 2 men lay 72 pc/day
10. Installation of water closet: 2 men install 1-set WC/2 day
11. Installation of lavatory: 2 men install 1-set LAV/1 1/2 days
12. Installation of G.I. sheets 32"x12" on steel frames: 2 men install 10 sheets/day
13. Installation of G.I. pipe 1/2Ǿ x 200́ʹ: 2 men install 20 pc/day
14. Installation of plywood board: 2 men install 15 sheets(4ʹ x 8ʹ)/day
15. Formworks: Beam, Floor slab : 2.8MH/m²
COLUMN FOOTING
L= 1 m
B= 1 m
d= 0.3 m
Ø= 16 mm
No. of Bars = 8 BW
Length of Bar = 0.85 m 7 No. in 6m Bar
NUMBER OF COLUMN FOOTING = 21 pc
Mixture Class = A
Mixture Class = 2
Volume of Concrete = 6.3 m³

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 57 Bag ₱ 230.00 ₱ 13,110.00
2 16 mmØ x 6m Def. Bar 48 pc 335.00 16,080.00
3 Ga. # 16 GI Tie Wire 8 kg 65.00 520.00
4 Sand 4 m³ 450.00 1,800.00
5 Gravel 7 m³ 550.00 3,850.00
6 Water 171 gal 3.00 513.00
Total Material Cost ₱ 35,873.00

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 6 ₱ 750.00 ₱ 4,500.00
2 Steel Man 1 6 300.00 1,800.00
3 Mason 1 6 350.00 2,100.00
4 Unskilled Worker 1 6 200.00 1,200.00
Total Labor Cost ₱ 9,600.00
Total Cost ₱ 45,473.00
Cost per m³ ₱ 7,217.94
CONCRETE COLUMN

NO. OF COLUMNS = 21 pc
COLUMN HEIGHT = 8m
C1 = 0.3 m
C2 = 0.3 m
MAIN BAR DIAMETER = 12 mm
NO. OF BARS = 8 pc
LATERAL TIE DIAMETER = 10 mm
VOLUME OF CONCRETE = 15.12 m³
LENGTH OF LATERAL TIE = 0.94 m NO. OF LATERAL TIE IN A 6m BAR = 6 pc
SPACING OF LATERAL TIES = 0.3 m
TOTAL NO. OF LATERAL TIES = 980
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 137 Bag ₱ 230.00 ₱ 31,510.00
2 12 mmØ x 6m Def. Bar 219 pc 191.00 41,829.00
3 10 mmØ x 6m Def. Bar 164 pc 135.00 22,140.00
4 Ga. # 16 GI Tie Wire 45 kg 65.00 2,925.00
5 1/4" X 4' X 8' Ordinary Plywood 25 pc 290.00 7,250.00
6 2" x 2" x 8' Coco Lumber 672.84 Bd f 14.00 9,419.76
7 Common Wood Nail 11 kg 75.00 825.00
8 Sand 8 m³ 450.00 3,600.00
9 Gravel 16 m³ 550.00 8,800.00
10 Water 411 gal 3.00 1,233.00
Total Material Cost ₱ 129,531.76

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 31 ₱ 750.00 ₱ 23,250.00
2 Steel Man 1 31 300.00 9,300.00
3 Carpenter 1 31 350.00 10,850.00
4 Mason 1 31 350.00 10,850.00
5 Unskilled Worker 1 31 200.00 6,200.00
Total Labor Cost ₱ 60,450.00
Total Cost ₱ 189,981.76
Cost per m³ ₱ 12,564.93
CONCRETE BEAM

TOTAL LENGTH OF BEAM = 303 m


OVERALL DEPTH OF BEAM = 0.45 m
WIDTH OF BEAM = 0.25 m
MAIN BAR DIAMETER = 25 mm
NO. OF MAIN BARS OF THE BEAM = 7 pc
STIRRUP TIE DIAMETER = 10 mm
VOLUME OF CONCRETE = 34.0875 m³
LENGTH OF STIRRUP TIE = 1.14 m
SPACING OF TIES = 0.15 m
NO. OF BEAM - COL. CONNECTIONS = 29 pc
TOTAL NO. OF STIRRUP TIES = 2137 pc
NO. OF TIES IN A 6m BAR = 5 pc

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 307 Bag ₱ 230.00 ₱ 70,610.00
2 25 mmØ x 6m Def. Bar 427 pc 535.00 228,445.00
3 10 mmØ x 6m Def. Bar 428 pc 135.00 57,780.00
4 Ga. # 16 GI Tie Wire 85 kg 65.00 5,525.00
5 1/4" X 4' X 8' Ordinary Plywood 75 pc 290.00 21,750.00
6 2" x 2" x 8' Coco Lumber 2003 Bd f 14.00 28,042.00
7 Common Wood Nail 37.5 kg 75.00 2,812.50
8 Sand 18 m³ 450.00 8,100.00
9 Gravel 35 m³ 550.00 19,250.00
10 Water 921 gal 3.00 2,763.00
Total Material Cost ₱ 445,077.50

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 69 ₱ 750.00 ₱ 51,750.00
2 Steel Man 1 69 300.00 20,700.00
3 Carpenter 1 69 350.00 24,150.00
4 Mason 1 69 350.00 24,150.00
5 Unskilled Worker 1 69 200.00 13,800.00
Total Labor Cost ₱ 134,550.00
Total Cost ₱ 579,627.50
Cost per m³ ₱ 17,004.11
CONCRETE HOLLOW BLOCK WALL

AREA OF THE WALL = 607.27 m²


LENGTH OF WALL FOOTING = 105 m
SIZE OF CHB = 4 X 8 X16
SIZE OF VERTICAL BAR = 12 mm
SPACING OF VERTICAL BAR = 0.6 m
SIZE OF HORIZONTAL BAR = 10 mm
SPACING OF HORIZONTAL BAR = 3 LAYER
WIDTH OF WALL FOOTING = 0.4 m
OVERALL DEPTH OF WALL FOOTING = 0.25 m
SIZE OF MAIN BAR = 10 mm
SPACING OF MAIN BAR = 0.3 m
SIZE OF TEMPERATURE BAR = 12 mm
NO. OF TEMPERATURE BAR = 3 pc
VOLUME OF CONCRETE = 10.5 m³
NO. OF VERTICAL BAR (CHB) = 217 pc
NO. OF HORIZONTAL BAR (CHB)= 218 pc
NO. OF MAIN BAR (WF) = 23.333333 pc NO. OF MAIN BAR IN 6m BAR = 15
TOTAL NO. OF TEMP. BAR (WF) = 63 pc
NO. 16 GI TIE WIRE = 26 Kg

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 908 Bag ₱ 230.00 ₱ 208,840.00
2 CHB (20 X 40 X 60) 7600 pc 9.00 68,400.00
2 12 mmØ x 6m Def. Bar 280 pc 195.00 54,600.00
3 10 mmØ x 6m Def. Bar 241.33333 pc 135.00 32,580.00
4 Ga. # 16 GI Tie Wire 26 kg 65.00 1,690.00
5 Sand 52 m³ 450.00 23,400.00
6 Gravel 15 m³ 550.00 8,250.00
7 Water 2724 gal 3.00 8,172.00
Total Material Cost ₱ 405,932.00

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 121 ₱ 750.00 ₱ 90,375.00
2 Steel Man 1 121 300.00 36,150.00
3 Mason 1 121 350.00 42,175.00
4 Unskilled Worker 1 121 200.00 24,100.00
Total Labor Cost ₱ 192,800.00
Total Cost ₱ 598,732.00
Cost per m² ₱ 985.94
CONCRETE SLAB

FLOOR AREA = 334 m²


THICKNESS OF SLAB = 0.125 m
SIZE OF BAR = 10 mm
SPACING OF BARS = 10 cm
VOLUME OF CONCRETE = 41.75 m³

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 375.75 Bag ₱ 230.00 ₱ 86,422.50
2 10 mmØ x 6m Def. Bar 1076 pc 135.00 145,260.00
3 Ga. # 16 GI Tie Wire 117 kg 65.00 7,605.00
4 1/4" X 4' X 8' Ordinary Plyw 120 pc 290.00 34,800.00
5 2" x 2" x 8' Coco Lumber 5126.4 Bd f 14.00 71,769.60
6 Common Wood Nail 167 kg 75.00 12,525.00
7 Sand 21 m³ 450.00 9,450.00
8 Gravel 42 m³ 550.00 23,100.00
9 Water 1127.25 gal 3.00 3,381.75
Total Material Cost ₱ 394,313.85

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 83.5 ₱ 750.00 ₱ 62,625.00
2 Steel Man 1 83.5 300.00 25,050.00
3 Carpenter 1 83.5 350.00 29,225.00
4 Mason 1 83.5 350.00 29,225.00
5 Unskilled Worker 1 83.5 200.00 16,700.00
Total Labor Cost ₱ 162,825.00
Total Cost ₱ 557,138.85
Cost per m² ₱ 1,668.08
CONCRETE SLAB

FLOOR AREA = 229.5 m²


THICKNESS OF SLAB = 0.10 m
SIZE OF BAR = 10 mm
SPACING OF BARS = 50 cm
VOLUME OF CONCRETE = 22.95 m³

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 206.55 Bag ₱ 230.00 ₱ 47,506.50
2 10 mmØ x 6m Def. Bar 227 pc 135.00 30,645.00
3 Ga. # 16 GI Tie Wire 16.5 kg 65.00 1,072.50
5 Sand 12 m³ 450.00 5,400.00
6 Gravel 23 m³ 550.00 12,650.00
7 Water 619.65 gal 3.00 1,858.95
Total Material Cost ₱ 99,132.95

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 54 ₱ 750.00 ₱ 40,500.00
2 Steel Man 1 54 300.00 16,200.00
4 Mason 1 54 350.00 18,900.00
5 Unskilled Worker 1 54 200.00 10,800.00
Total Labor Cost ₱ 86,400.00
Total Cost ₱ 185,532.95
Cost per m² ₱ 808.42
SCAFFOLDING

FLOOR AREA = 140 m²


FLOOR HEIGHT = 3.20 m
NO. OF COLUMNS = 21.00
LENGTH OF BEAM = 135.00 m
SIZE OF TIMBER = 2" X 3" GOOD LUMBER
NO. OF BD.FT. FOR COLUMN = 3774.62
NO. OF BD.FT. FOR BEAM = 5616.00
NO. OF BD.FT. FOR SLAB = 1274.00

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 2" X 3" GOOD LUMBER 10664.62 Bd f 28.00 298,609.47
2 Common Wood Nail 54 kg 75.00 4,050.00
Total Material Cost ₱ 302,659.47

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 88.9 ₱ 750.00 ₱ 66,653.90
2 Carpenter 1 88.9 350.00 31,105.15
3 Unskilled Worker 1 88.9 200.00 17,774.37
Total Labor Cost ₱ 115,533.43
Total Cost ₱ 418,192.90
Cost per m² ₱ 2,987.09
ROOFING WORKS

LENGTH OF ROOF SURFACE = 13.5 m 2.34 m


WIDTH OF ROOF SURFACE = 17 m 2 m
ROOF SURFACE AREA 468.36 m²
SIZE OF PURLINS = 2" X 3" X 10' GOOD LUMBER
SPACING OF PURLINS = 0.6 m
SIZE GI ROOFING = 32" X 12' Ga. # 26 GI ROOFING
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Ga. # 26 GI ROOFING 32" X 12' 90 pc ₱ 380.00 ₱ 34,200.00
2 2" X 3" X 10' GOOD LUMBER 150 pc 140.00 21,000.00
3 ROOFING NAIL (2⅟2") 10 kg 130.00 1,300.00
5 PRE-FABRICATED GUTTER 43 pc 450.00 19,350.00
6 FASCIA CAP 43 pc 550.00 23,650.00
7 2" X 6" X 12' GOOD LUMBER 150 pc 336.00 50,400.00
8 ⅟2" X 4" X 8" MARINE PLYWOOD 10 pc 920.00 9,200.00
9 Common Wood Nail 13 kg 75.00 975.00
Total Material Cost ₱ 159,100.00

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 26 ₱ 750.00 ₱ 19,500.00
4 Carpenter 1 26 350.00 9,100.00
5 Unskilled Worker 1 26 200.00 5,200.00
Total Labor Cost ₱ 33,800.00
Total Cost ₱ 192,900.00
Cost per m² ₱ 411.86
CONCRETE SLAB

FLOOR AREA = 276.75 m²


THICKNESS OF MORTAR = 0.05 m
SIZE OF GRANITE FLOOR TILE = 0.60 X 0.60 mm
SPACING OF BARS = 50 cm
VOLUME OF CONCRETE = 13.8375 m³

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 50 Bag ₱ 230.00 ₱ 11,500.00
2 GRANITE FLOOR TILE 300 pc 135.00 40,500.00
3 TILE GROUT 3 kg 125.00 375.00
5 Sand 7 m³ 450.00 3,150.00
7 Water 65 gal 3.00 195.00
Total Material Cost ₱ 55,720.00

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 15 ₱ 750.00 ₱ 11,250.00
4 Mason 1 15 350.00 5,250.00
5 Unskilled Worker 1 15 200.00 3,000.00
Total Labor Cost ₱ 19,500.00
Total Cost ₱ 75,220.00
Cost per m² ₱ 271.80
OVERALL BILL OF QUANTITIES
Project Title: Proposed One - Storey Commercial Building

HEALTHY BAKE SHOP

I. EARTHWORK
DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Excavation 14.00 m³ P 150.00 P 2,100.00
2 Backfilling Materials 11.00 m³ 150.00 1,650.00
Sub-total P 3,750.00

II. MASONRY WORKS


DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Concrete Hollow Block #4 120 pc P 9.50 P 1,140.00
2 Sand 11 m³ 450.00 4,950.00
3 Gravel 9 m³ 550.00 4,950.00
4 Portland Cement 51 bag 240.00 12,240.00
5 10mm Ø Deformed Bar 45 pc 145.00 6,525.00
6 12mm Ø Deformed Bar 50 pc 195.00 9,750.00
7 Ga # 16 GI Tie Wire 3 Kg 60.00 150.00
8 Labor 1 lot 25,000.00 25,000.00
Sub-total P 64,705.00

III. CONCRETE WORKS


DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Gravel 25 m³ 550.00 13,750.00
2 Sand 20 m³ 450.00 9,000.00
3 Portland Cement 100 bag 240.00 24,000.00
5 12mm Ø Deformed Bar 99 pc 195.00 19,305.00
6 10mm Ø Deformed Bar 105 pc 145.00 15,225.00
7 1/4" x 4'x8' Ordinary Plywood 40 pc 250.00 10,000.00
8 2"x3"x12' Coco Lumber 48 pc 84.00 4,032.00
9 2"x2"x12' Coco Lumber 56 pc 56.00 3,136.00
10 Common Wood Nails 1 lot 1,100.00 1,100.00
11 Ga # 16 GI Tie Wire 3 Kg 65.00 195.00
12 Labor 1 lot 30,000.00 30,000.00
Sub-total P 129,743.00

IV. STEEL WORKS


DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Fixed Glass (W1) 2 set 1,100.00 P 2,200.00
2 Fixed Glass (W2) 3 set 750.00 2,250.00
3 Steel Casement Window (W3) 4 set 400.00 1,600.00
4 Steel Casement Window (W4) 9 set 270.00 2,430.00
5 Labor 1 lot 8,500.00 8,500.00
Sub-total P 16,980.00
V. ROOFING WORKS
DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Gravel 16 pc 550.00 8,800.00
2 Sand 12 pc 450.00 5,400.00
3 Portland Cement 51 bag 240.00 12,240.00
4 12mm Ø Deformed Bar 68 pc 185.00 12,580.00
5 10mm Ø Deformed Bar 61 pc 135.00 8,235.00
6 1/4" x 4'x8' Ordinary Plywood 18 pc 270.00 4,860.00
7 2"x3"x12' Coco Lumber 25 pc 80.00 2,000.00
8 2"x2"x12' Coco Lumber 27 pc 51.00 1,377.00
9 Ga # 16 GI Tie Wire 3 Kg 60.00 180.00
10 Accessories 1 lot 1,600.00 1,600.00
11 Labor 1 lot 21,000.00 21,000.00
P 78,272.00

VI. CARPENTRY WORKS


DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Fixed Glass Door (D1) 1 pc 1500.00 1500.00
1 Solid Panel Door (D2) 6 pc 1,200.00 7,200.00
2 PVC Door (D3) 5 SET 900.00 4,500.00
3 Accessories 1 lot 1,000.00 1,000.00
4 Labor 1 lot 4,300.00 4,300.00
Sub-total P 18,500.00

VII. TILE WORKS


DESCRIPTION QUANTITY UNIT UNIT COST COST
1 24" X 24" Ceramic Floor Tiles 95 pc 147.00 13,965.00
2 30 cm x 30 cm Ceramic Floor Tiles 78 pc 27.00 2,106.00
3 30 cm x 30 cm Ceramic Glazed Tiles 92 pc 28.00 2,576.00
4 Tile Grout 5 pack 280.00 1,400.00
5 Portland Cement 11 bag 240.00 2,640.00
6 Sand 4 m³ 500.00 2,000.00
7 Accessories 1 lot 1,500.00 1,500.00
8 Labor 1 lot 9,500.00 9,500.00
Sub-total P 35,687.00

VIII. Plumbing 36,386.00


IX. Electrical 55,861.00
X. Painting 15,000.00
XI. Other Expenses 10,000.00

Total Cost P 464,884.00


Project Title: Proposed One - Storey Commercial Building

HEALTHY BAKE SHOP

SUMMARY OF ALL COST

I. EARTHWORKS P 3,750.00
II. MASONRY WORKS 64,705.00
III. CONCRETE WORKS 129,743.00
IV. STEEL WORKS 16,980.00
V. ROOFING WORKS 78,272.00
VI. CARPENTRY WORKS 18,500.00
VII. TILE WORKS 35,687.00
VIII. Plumbing 36,386.00
IX Electrical 55,861.00
XII. Painting 15,000.00
XI. Other Expenses 10,000.00
P 464,884.00
BILL OF QUANTITIES
PLUMBING

Description Quantity Unit Unit Cost Cost


1 Water Closet 5 Set P 1,600.00 P 8,000.00
2 Lavatory 2 set 800.00 1,600.00
5 Floor Drain #4 5 pc 25.00 125.00
6 100 mm Ø PVC Sanitary Pipe 13 pc 250.00 3,250.00
7 50 mm Ø PVC Sanitary Pipe 11 pc 130.00 1,430.00
8 12 mm Ø uPVC Pipe 26 pc 105.00 2,730.00
9 12 mm Faucet 9 pc 75.00 675.00
10 Concrete Hollow Block # 4 30 pc 8.50 255.00
11 10mm Ø Deformed Bar 9 pc 154.00 1,386.00
12 Gravel 1.5 m3 650.00 975.00
13 Sand 1m 3
600.00 600.00
14 Porland Cement 9 bag 240.00 2,160.00
15 Fittings 1 lot 800.00 800.00
16 Accessories 1 lot 400.00 400.00
17 Labor 1 lot 12,000.00 12,000.00
Sub-total P 36,386.00
BILL QUANTITIES
ELECTRICAL

ITEM DESCRIPTION QUANTITYUNIT UNIT COST COST


1 # 06 AWG DUPLEX WIRE 15 m P 30.00 P 450.00
2 # 2.0 mm² THHN / COPPER WIRE 2 ROLL 2,160.00 4,320.00
3 # 3.5 mm² THHN / COPPER WIRE 2 ROLL 2,560.00 5,120.00
4 # 5.5 mm² THHN / COPPER WIRE 1 ROLL 2,900.00 2,900.00
5 # 8.0 mm² THHN / COPPER WIRE 15 m 185.00 2,775.00
6 # 30.0 mm² THHN / COPPER WIRE 10 m 695.00 6,950.00
8 PIN LIGHT 16 SET 150.00 2,400.00
9 FLUORESCENT LAMP 3 SET 700.00 2,100.00
11 16 BRANCHES PANEL BOARD 1 SET 1,400.00 1,400.00
12 2P, 250V, 15 AT CIRCUIT BREAKER 2 PC 250.00 500.00
13 2P, 250V, 20 AT CIRCUIT BREAKER 2 PC 350.00 700.00
14 2P, 250V, 30 AT CIRCUIT BREAKER 6 PC 480.00 2,880.00
15 2P, 250V, 40 AT CIRCUIT BREAKER 2 PC 462.00 924.00
16 2P, 250V, 150 AT CIRCUIT BREAKER 1 PC 756.00 756.00
17 K-22 / K-10 WIRE HOLDER 1 PC 110.00 110.00
18 2- GANG, 250V, CONVENIENCE OUTLET 12 PC 160.00 1,920.00
19 250V, ACU OUTLET 3 PC 165.00 495.00
20 250V, 30A, SWITCH (SINGLE) 13 PC 110.00 1,430.00
21 250V, 30A, SWITCH (DOUBLE) 1 PC 120.00 120.00
23 2" X 4" UTILITY BOX 8 PC 19.00 152.00
24 JUNCTION BOX 16 PC 28.00 448.00
25 12 mm Ø PVC PIPE 13 PC 62.00 806.00
26 18 mm Ø PVC PIPE 7 PC 95.00 665.00
27 25 mm Ø PVC PIPE 1 PC 120.00 120.00
28 12 mm Ø MOLDFLEX 1 ROLL 420.00 420.00
29 Labor 1 LOT 15,000.00 15,000.00
TOTAL P 55,861.00
CEILING WORKS

CEILING AREA = 210 m²


SIZE OF CEILING JOIST= 2" X 2"
SPACING OF CEILING JOIST = 0.60 X 0.60
CEILING BOARD = 1/4" MARINE PLYWOOD

MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 1/4" MARINE PLYWOOD 90 pc 380.00 34,200.00
2 Common Wood Nail 3 kg 75.00 225.00
3 2" X 2" X 10' GOOD LUMBER 939.54 bd.f. 28.00 26,307.12
Total Material Cost ₱ 60,732.12

LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 14 ₱ 750.00 ₱ 10,500.00
2 Carpenter 1 14 350.00 4,900.00
3 Unskilled Worker 1 14 200.00 2,800.00
Total Labor Cost ₱ 18,200.00
Total Cost ₱ 78,932.12
Cost per m² ₱ 375.87

You might also like