Rusty Estimates
Rusty Estimates
Concrete Proportion
Class Cement in Bag
Proportion
Mixture 40 kg
AA 1 1 1⅟2 3 12
A 2 1 2 4 9
B 3 1 2⅟2 5 7.5
C 4 1 3 6 6
Table 2 - 4. Quantity of Cement and Sand for Plaster per Square Meter
Mixture Cement in Bags
Class 8 mm 12 mm 16 mm 20 mm
A 0.144 0.216 0.288 0.360
B 0.096 0.144 0.192 0.240
C 0.072 0.108 0.144 0.180
D 0.060 0.090 0.120 0.150
SAND (m³) 0.008 0.012 0.016 0.02
Table 2 - 12. Quantity of Cement and Sand on a Stone Rip - Rap per Cubic Meter
Cement in Bags
Stone Sand
Class Grout Mixture m³
A B C
Class A 2.574 1.716 1.287 0.143
Class B 2.448 1.620 1.214 0.135
Class C 2.232 1.488 1.116 0.124
Class D 1.944 1.296 0.972 0.108
TABLE 3-10 QUANTITY OF REINFORCING STEEL BARS IN A ONE-WAY REINFORCED CONCRETE SLAB
Bar Spacing Number of Steel Bars per Square Meter
cm 6.00 m 7.50 m 9.00 m 12.00 m
10.0 3.764 2.937 2.421 1.769
12.5 3.062 2.381 1.934 1.427
15.0 2.584 2.004 1.636 1.197
17.5 2.232 1.726 1.407 1.033
20.0 1.980 1.528 1.258 0.194
22.5 1.786 1.369 1.109 0.810
25.0 1.627 1.250 1.014 0.736
TABLE 3-11 QUANTITY OF TIE WIRE ON A ONE WAY REINFORCED CONCRETE SLAB IN KGS. PER SQUARE METER
STUDS
Board Foot of Studs and Ceiling Joist per Square Meter
Spacing
Dimension
Dimension 0.40 x 0.40 0.40 x 0.60 0.60 x 0.60
(16" x 16") (16" x 24") (24" x 24")
2" x 2" 6.417 5.445 4.474
2" x 3" 9.625 8.312 6.711
2" x 4" 12.833 10.891 8.948
SCAFFOLDING
Column (Board Foot) Beam (Board Foot) Slab
Gravel
m³
0.018
0.022
0.037
0.050
0.072
0.088
0.196
0.252
0.282
0.314
0.346
0.498
0.612
Cement Sand
B m³
0.522 0.0435
1.018 0.0844
1.500 0.1250
Cement Sand
B m³
4.176 0.348
8.104 0.675
12.000 1.000
20 mm 25 mm
0.360 0.450
0.240 0.300
0.180 0.225
0.150 0.188
0.02 0.025
Sand
m³
0.143
0.135
0.124
0.108
9 10
254 283
452 503
707 785
1017 1131
1809 2011
2827 3142
4418 4909
7237 8042
1131 1257
ARE METER
LABOR ESTIMATE:
1. Concreting of plain flooring: 2 men can pour 1.2 m³ conc./day
2. Concreting of R.C. flooring: 2 men can pour 0.84 m³ conc./day
3. Concreting of column and beam: 2 men can pour 0.50 m³ conc./day
4. Finishing of flooring(rough): 2 men finish 72 m²/day
5. Finishing of CHB joints: 2 men finish 420 pc/day
6. Plastering of CHB: 2 men plasters 8 m²/day
7. Laying of CHB : 2 men lay 100 pc/day
8. Breaking old R.C. flooring: 2 men break 0.30 m³/day
9. Laying of Glazed tiles 6"x6": 2 men lay 72 pc/day
10. Installation of water closet: 2 men install 1-set WC/2 day
11. Installation of lavatory: 2 men install 1-set LAV/1 1/2 days
12. Installation of G.I. sheets 32"x12" on steel frames: 2 men install 10 sheets/day
13. Installation of G.I. pipe 1/2Ǿ x 200́ʹ: 2 men install 20 pc/day
14. Installation of plywood board: 2 men install 15 sheets(4ʹ x 8ʹ)/day
15. Formworks: Beam, Floor slab : 2.8MH/m²
COLUMN FOOTING
L= 1 m
B= 1 m
d= 0.3 m
Ø= 16 mm
No. of Bars = 8 BW
Length of Bar = 0.85 m 7 No. in 6m Bar
NUMBER OF COLUMN FOOTING = 21 pc
Mixture Class = A
Mixture Class = 2
Volume of Concrete = 6.3 m³
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 57 Bag ₱ 230.00 ₱ 13,110.00
2 16 mmØ x 6m Def. Bar 48 pc 335.00 16,080.00
3 Ga. # 16 GI Tie Wire 8 kg 65.00 520.00
4 Sand 4 m³ 450.00 1,800.00
5 Gravel 7 m³ 550.00 3,850.00
6 Water 171 gal 3.00 513.00
Total Material Cost ₱ 35,873.00
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 6 ₱ 750.00 ₱ 4,500.00
2 Steel Man 1 6 300.00 1,800.00
3 Mason 1 6 350.00 2,100.00
4 Unskilled Worker 1 6 200.00 1,200.00
Total Labor Cost ₱ 9,600.00
Total Cost ₱ 45,473.00
Cost per m³ ₱ 7,217.94
CONCRETE COLUMN
NO. OF COLUMNS = 21 pc
COLUMN HEIGHT = 8m
C1 = 0.3 m
C2 = 0.3 m
MAIN BAR DIAMETER = 12 mm
NO. OF BARS = 8 pc
LATERAL TIE DIAMETER = 10 mm
VOLUME OF CONCRETE = 15.12 m³
LENGTH OF LATERAL TIE = 0.94 m NO. OF LATERAL TIE IN A 6m BAR = 6 pc
SPACING OF LATERAL TIES = 0.3 m
TOTAL NO. OF LATERAL TIES = 980
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 137 Bag ₱ 230.00 ₱ 31,510.00
2 12 mmØ x 6m Def. Bar 219 pc 191.00 41,829.00
3 10 mmØ x 6m Def. Bar 164 pc 135.00 22,140.00
4 Ga. # 16 GI Tie Wire 45 kg 65.00 2,925.00
5 1/4" X 4' X 8' Ordinary Plywood 25 pc 290.00 7,250.00
6 2" x 2" x 8' Coco Lumber 672.84 Bd f 14.00 9,419.76
7 Common Wood Nail 11 kg 75.00 825.00
8 Sand 8 m³ 450.00 3,600.00
9 Gravel 16 m³ 550.00 8,800.00
10 Water 411 gal 3.00 1,233.00
Total Material Cost ₱ 129,531.76
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 31 ₱ 750.00 ₱ 23,250.00
2 Steel Man 1 31 300.00 9,300.00
3 Carpenter 1 31 350.00 10,850.00
4 Mason 1 31 350.00 10,850.00
5 Unskilled Worker 1 31 200.00 6,200.00
Total Labor Cost ₱ 60,450.00
Total Cost ₱ 189,981.76
Cost per m³ ₱ 12,564.93
CONCRETE BEAM
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 307 Bag ₱ 230.00 ₱ 70,610.00
2 25 mmØ x 6m Def. Bar 427 pc 535.00 228,445.00
3 10 mmØ x 6m Def. Bar 428 pc 135.00 57,780.00
4 Ga. # 16 GI Tie Wire 85 kg 65.00 5,525.00
5 1/4" X 4' X 8' Ordinary Plywood 75 pc 290.00 21,750.00
6 2" x 2" x 8' Coco Lumber 2003 Bd f 14.00 28,042.00
7 Common Wood Nail 37.5 kg 75.00 2,812.50
8 Sand 18 m³ 450.00 8,100.00
9 Gravel 35 m³ 550.00 19,250.00
10 Water 921 gal 3.00 2,763.00
Total Material Cost ₱ 445,077.50
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 69 ₱ 750.00 ₱ 51,750.00
2 Steel Man 1 69 300.00 20,700.00
3 Carpenter 1 69 350.00 24,150.00
4 Mason 1 69 350.00 24,150.00
5 Unskilled Worker 1 69 200.00 13,800.00
Total Labor Cost ₱ 134,550.00
Total Cost ₱ 579,627.50
Cost per m³ ₱ 17,004.11
CONCRETE HOLLOW BLOCK WALL
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 908 Bag ₱ 230.00 ₱ 208,840.00
2 CHB (20 X 40 X 60) 7600 pc 9.00 68,400.00
2 12 mmØ x 6m Def. Bar 280 pc 195.00 54,600.00
3 10 mmØ x 6m Def. Bar 241.33333 pc 135.00 32,580.00
4 Ga. # 16 GI Tie Wire 26 kg 65.00 1,690.00
5 Sand 52 m³ 450.00 23,400.00
6 Gravel 15 m³ 550.00 8,250.00
7 Water 2724 gal 3.00 8,172.00
Total Material Cost ₱ 405,932.00
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 121 ₱ 750.00 ₱ 90,375.00
2 Steel Man 1 121 300.00 36,150.00
3 Mason 1 121 350.00 42,175.00
4 Unskilled Worker 1 121 200.00 24,100.00
Total Labor Cost ₱ 192,800.00
Total Cost ₱ 598,732.00
Cost per m² ₱ 985.94
CONCRETE SLAB
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 375.75 Bag ₱ 230.00 ₱ 86,422.50
2 10 mmØ x 6m Def. Bar 1076 pc 135.00 145,260.00
3 Ga. # 16 GI Tie Wire 117 kg 65.00 7,605.00
4 1/4" X 4' X 8' Ordinary Plyw 120 pc 290.00 34,800.00
5 2" x 2" x 8' Coco Lumber 5126.4 Bd f 14.00 71,769.60
6 Common Wood Nail 167 kg 75.00 12,525.00
7 Sand 21 m³ 450.00 9,450.00
8 Gravel 42 m³ 550.00 23,100.00
9 Water 1127.25 gal 3.00 3,381.75
Total Material Cost ₱ 394,313.85
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 83.5 ₱ 750.00 ₱ 62,625.00
2 Steel Man 1 83.5 300.00 25,050.00
3 Carpenter 1 83.5 350.00 29,225.00
4 Mason 1 83.5 350.00 29,225.00
5 Unskilled Worker 1 83.5 200.00 16,700.00
Total Labor Cost ₱ 162,825.00
Total Cost ₱ 557,138.85
Cost per m² ₱ 1,668.08
CONCRETE SLAB
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 206.55 Bag ₱ 230.00 ₱ 47,506.50
2 10 mmØ x 6m Def. Bar 227 pc 135.00 30,645.00
3 Ga. # 16 GI Tie Wire 16.5 kg 65.00 1,072.50
5 Sand 12 m³ 450.00 5,400.00
6 Gravel 23 m³ 550.00 12,650.00
7 Water 619.65 gal 3.00 1,858.95
Total Material Cost ₱ 99,132.95
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 54 ₱ 750.00 ₱ 40,500.00
2 Steel Man 1 54 300.00 16,200.00
4 Mason 1 54 350.00 18,900.00
5 Unskilled Worker 1 54 200.00 10,800.00
Total Labor Cost ₱ 86,400.00
Total Cost ₱ 185,532.95
Cost per m² ₱ 808.42
SCAFFOLDING
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 2" X 3" GOOD LUMBER 10664.62 Bd f 28.00 298,609.47
2 Common Wood Nail 54 kg 75.00 4,050.00
Total Material Cost ₱ 302,659.47
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 88.9 ₱ 750.00 ₱ 66,653.90
2 Carpenter 1 88.9 350.00 31,105.15
3 Unskilled Worker 1 88.9 200.00 17,774.37
Total Labor Cost ₱ 115,533.43
Total Cost ₱ 418,192.90
Cost per m² ₱ 2,987.09
ROOFING WORKS
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 26 ₱ 750.00 ₱ 19,500.00
4 Carpenter 1 26 350.00 9,100.00
5 Unskilled Worker 1 26 200.00 5,200.00
Total Labor Cost ₱ 33,800.00
Total Cost ₱ 192,900.00
Cost per m² ₱ 411.86
CONCRETE SLAB
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Portland Cement (40 kg) 50 Bag ₱ 230.00 ₱ 11,500.00
2 GRANITE FLOOR TILE 300 pc 135.00 40,500.00
3 TILE GROUT 3 kg 125.00 375.00
5 Sand 7 m³ 450.00 3,150.00
7 Water 65 gal 3.00 195.00
Total Material Cost ₱ 55,720.00
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 15 ₱ 750.00 ₱ 11,250.00
4 Mason 1 15 350.00 5,250.00
5 Unskilled Worker 1 15 200.00 3,000.00
Total Labor Cost ₱ 19,500.00
Total Cost ₱ 75,220.00
Cost per m² ₱ 271.80
OVERALL BILL OF QUANTITIES
Project Title: Proposed One - Storey Commercial Building
I. EARTHWORK
DESCRIPTION QUANTITY UNIT UNIT COST COST
1 Excavation 14.00 m³ P 150.00 P 2,100.00
2 Backfilling Materials 11.00 m³ 150.00 1,650.00
Sub-total P 3,750.00
I. EARTHWORKS P 3,750.00
II. MASONRY WORKS 64,705.00
III. CONCRETE WORKS 129,743.00
IV. STEEL WORKS 16,980.00
V. ROOFING WORKS 78,272.00
VI. CARPENTRY WORKS 18,500.00
VII. TILE WORKS 35,687.00
VIII. Plumbing 36,386.00
IX Electrical 55,861.00
XII. Painting 15,000.00
XI. Other Expenses 10,000.00
P 464,884.00
BILL OF QUANTITIES
PLUMBING
MATERIALS
ITEM DESCRIPTION QUANTITY UNIT UNIT COST COST
1 1/4" MARINE PLYWOOD 90 pc 380.00 34,200.00
2 Common Wood Nail 3 kg 75.00 225.00
3 2" X 2" X 10' GOOD LUMBER 939.54 bd.f. 28.00 26,307.12
Total Material Cost ₱ 60,732.12
LABOR
ITEM DESCRIPTION QUANTITY DAY RATE PER DAY COST
1 Civil Engineer 1 14 ₱ 750.00 ₱ 10,500.00
2 Carpenter 1 14 350.00 4,900.00
3 Unskilled Worker 1 14 200.00 2,800.00
Total Labor Cost ₱ 18,200.00
Total Cost ₱ 78,932.12
Cost per m² ₱ 375.87