Bridge Protective Ship Collision
Bridge Protective Ship Collision
Bridge Protective Ship Collision
JOHAN FORSGRAN
ANDREAS LAMTON
Cover:
Deformation figure of the FE-model representing the protective pier, created in FE-
software Abaqus/CAE 6.13-3.
Chalmers Reproservice. Göteborg, Sweden, 2015
I
Non-linear analysis of bridge protective piers exposed to ship collision
Energy absorbing capacity of the protective piers at Hisingsbron
Master’s thesis in the Master’s Programme Structural Engineering and Building
Technology
JOHAN FORSGRAN
ANDREAS LAMTON
Department of Civil and Environmental Engineering
Division of Structural Engineering
Concrete Structures
Chalmers University of Technology
ABSTRACT
Series of historical ship-bridge collisions exposed the need for protective measures.
One of these is protective piers that are sacrificial structures and defend the bridge
supports against ship collisions. The purpose of this report was to study the non-linear
structural response of these piers, which are to be built at Hisingsbron in Gothenburg,
during collision progress. This was done by setting up a non-linear finite element
model of the protective piers in the software Abaqus and analyse deformation pattern,
critical events and resisting capacity.
It was found hard to model the ship load in a representable way and so the incoming
kinetic energy from the design ship was compared to the protective piers' energy
resisting capacity. The analysis gave an indication of how the structure would deform
and computations proved that the energy absorbing capacity was insufficient.
However, as the defined clay springs could not be verified, the results are not
completely valid and cannot be used in design process of the protective piers. A
powerful model, from which interesting data can be extracted, is obtained by
correcting the springs and redefine the boundary conditions to resemble the reality
better.
Key words: FE-modelling, FEM, Finite element model, Non-linear, Ship collision,
Energy absorption, Protective pier, Hisingsbron, Concrete Damaged
Plasticity, Structural response, Displacement control, Abaqus, Clay
springs, Concrete, Steel, Reinforcement, Beam, Pile
I
Icke-linjär analys av påsegling utav ledverk
Energiabsorberande kapacitet för ledverket vid Hisingsbron
Examensarbete inom masterprogrammet Structural Engineering and Building
Technology
JOHAN FORSGRAN
ANDREAS LAMTON
Institutionen för bygg- och miljöteknik
Avdelningen för Konstruktionsteknik
Betongbyggnad
Chalmers tekniska högskola
SAMMANFATTNING
Flera historiska kollisioner mellan fartyg och bro har påvisat ett behov av skyddande
åtgärder. En sådan är ledverk vilka är offerkonstruktioner och hindrar fartyg från att
köra in i brostöd. Syftet med denna rapport var att studera den icke-linjära responsen
för Hisingsbrons ledverk under kollisionsförloppet. Detta gjordes genom att bygga en
finit-element modell av ledverket i mjukvaran Abaqus och därefter analysera
deformation, kritiska händelser och mothållande kapacitet.
Då det visade sig vara komplicerat att modellera fartygslasten på ett representativt sätt
jämfördes istället dimensionerande fartygs inkommande energi med ledverkets
energiabsorberande förmåga. Analysen gav en indikation på hur ledverket skulle ha
deformerats och beräkningar visade att den energiabsorberande kapaciteten var
otillräcklig. Eftersom lerfjädrarnas korrekta funktion inte kunde säkerställas så är
resultaten inte pålitliga och borde därmed inte användas i ledverkets projektering. En
bra modell, utifrån vilken man kan hämta intressanta data, erhålls om fjädrarna
korrigeras och randvillkoren ändras för att bättre efterlikna verkligheten.
Nyckelord: FE-modellering, FEM, Finit element modell, Icke-linjär,
Skeppskollision, Energi absorbering, Ledverk, Hisingsbron, Concrete
Damaged Plasticity, Strukturell respons, Förskriven deformation,
Abaqus, Lerfjädrar, Betong, Stål, Armering, Balk, Påle
II
Contents
ABSTRACT I
SAMMANFATTNING II
CONTENTS III
PREFACE VI
NOTATIONS VII
1 INTRODUCTION 1
1.1 Background 1
1.2 Purpose and objectives 1
1.3 Limitations 2
1.4 Method 2
2 PROTECTIVE MEASURES 3
2.1 Different types of protective methods 3
2.1.1 Out of reach 4
2.1.2 Strong piers 4
2.1.3 Guide structures 5
2.2 Risk assessment 5
2.3 Protective piers design 8
2.3.1 General concepts 8
2.3.2 Loads on piers 10
2.3.3 Energy absorption 11
2.4 Mathematical interpretation of load 13
2.4.1 Equivalent static force 15
2.4.2 Dynamic force 15
2.4.3 Load application techniques 16
5 RESULTS 54
5.1 Structural response 54
5.1.1 Overall structural response 54
5.1.2 Beam 60
5.1.3 Piles 66
5.1.4 Reinforcement 71
5.1.5 Clay springs 73
6 DISCUSSION 83
6.1 Modelling 83
6.2 Structural response 84
6.2.1 Overall structural response 85
6.2.2 Structural response in individual parts 85
7 CONCLUSION 88
7.1 Modelling 88
7.2 Structural response 88
8 FURTHER INVESTIGATIONS 89
9 REFERENCES 90
9.1 Oral sources 92
1.1 Background
In the year 2010 a series of investments in roads, railroads and public transportation
called West Swedish Agreement (Västsvenska paketet) were launched. The Swedish
Road Administration’s (Trafikverkets) goal is to create a modernized society which
can grow and be more attractive but at the same time be sustainable
(Trafikverket, 2014).
One of the larger investments is to build a new bridge over Göta älv in Gothenburg,
replacing the current bridge named Göta älvbron which was erected in the years 1936-
1939 (Göteborgs stad, 2015). Due to the degradation of the steel in this construction
action must take place in 2020 at the latest because of the calculated risk of failure. A
great need of transportation over the river has kick-started the plans for the new
bridge Hisingsbron and are currently in the making.
Included in the new bridge concept is the design of protective piers which is executed
by the consulting company COWI AB. Protective piers are barriers that are erected in
the river to guide the ships in the channel or to protect structures from collision. At
Hisingsbron these piers will lead the ships through the bridge opening and prevent
impact with the foundations. A study made by Trafikverket shows that the waterway
traffic is predicted to increase (Trafikverket, 2013). The unused capacity of Göta älv
cannot be utilized unless, for example, the protective piers along the fairway meet the
requirements for the new traffic. The construction of Hisingsbron is planned to start in
the beginning of year 2016.
It is of importance that the piers absorb the energy from the collision in an accurate
way so that a catastrophe can be averted. This is done by deformation, both globally
by the whole structure and also locally in the different parts. The behaviour of this
collision should therefore be analysed so that the piers can be designed to withstand a
collision. The response of the protective piers at impact is hard to predict with regular
linear-elastic model and is for that reason proposed to be executed with a non-linear
FE-setup (Finite Element-setup).
1.4 Method
The project is divided into three sections. The first part is a literature study on
protective piers and how this problem has been handled before. A case study will also
be performed on the protective piers at the planned Hisingsbron to facilitate the
behavioural study on the piers. The case study will provide dimensions for modelling
of the protective piers. In addition to this a literature study will be made on FE-
modelling to support understanding for how the model and loads will be set up in the
software Abaqus. This is done by looking at previous reports, articles and Chalmers
lectures containing FE-modelling of similar problem and contact with cunning people
in the area.
In the second part simplified hand-calculations in 2D will verify the model and show
approximate results to be expected from later analyses. The FE-model will be simple
to start with but extended by the time by including more parts of the total guide
structure into 3D.
Last part will be designated to model the final structure and run analyses to interpret
the structural behaviour in the finite element program Abaqus/CAE 6.13-3.
Evaluation whether the global response is reasonable or not along with refinement of
model takes place.
c) d)
Figure 2.1 Different protective measures for bridge supports.
𝑅 =𝑃∙𝐶 (2.1)
Where:
𝑅 is the risk
𝑃 is the probability
𝐶 is the consequence
Figure 2.2 Risk assessment of a collision between ship and protective pier
adapted from SSPA (SSPA, 2009).Moving from a) to b) is a
consequence reducing measure while moving from a) to c) reduces the
probability.
Where:
𝑁 = 𝑛𝜆𝑇(1 − 𝑝𝑎 ) is the total number of incidents in the period of consideration
Figure 2.3 Scenario of ship collision, showing a vessel A steering away from its
planned course X towards structure B (Eurocode, 2010).
𝐴𝐹 = (𝑁)(𝑃𝐴)(𝑃𝐺)(𝑃𝐶) (2.3)
Where:
𝑁 is the annual number of bridge passages for the vessel type under
consideration
𝑃𝐴 is the probability of the vessel being aberrant per bridge passage, and
successful evasive action not being taken
𝑃𝐺 is the geometric probability of a collision between an aberrant vessel and a
bridge pier or span
𝑃𝐶 is the probability of bridge collapse due to a collision by an aberrant vessel
Figure 2.4 Risk diagram for selected engineering projects and the lines
separating "accepted" and "marginally accepted" areas
(Larsen, 1993).
A large scale pier has a main longitudinal beam favourably made in a heavy material,
such as concrete, to withstand a heavy collision. The stiffer construction that a
concrete beam implies has its advantages since forces are better distributed within the
structure, allowing more connecting members to contribute to the bracing.
The main purpose of the protective pier is to transfer the load from a ship-collision
into the ground, essentially creating a load carrying system.
The first part of the system that will receive the ship load is responsible for taking
care of the service state loads. This is advantageously done by some kind of energy
absorbing parts, referred to as fenders, which are mounted on the face of the
longitudinal beam. Fenders are typically made out of rubber or possibly foam
elastomer that have high energy absorption capacity. The fenders can either be
connected via external longitudinal beams that distribute the loads to several units, see
Figure 2.6 [a], or be mounted with panels for distribution to a single or to a group of
fenders, see Figure 2.6 [b].
a) b)
Figure 2.6 Different fender systems. a) Shows fenders with load distributing
beams. b) Shows panel like fenders.
In the case of an accidental load the first part of the system will only manage to take
up a very small portion of the total load. Instead the second part of the system a main
b)
c)
Figure 2.8 Three graphics showing a ship to pier collision at different scenarios.
a) Right before impact, b) hard impact and c) soft impact.
The ship collision progress for protective piers is likely to be on-going on the scale of
seconds thus placing it somewhere in between the two extremes. The interaction is
dynamic but it is common to translate the forces into equivalent static forces as a
conservative simplification (Eurocode, 2010). This will be further developed in the
following section. An advanced design of structures exposed to an impact could
however include dynamic effects and/or non-linear material behaviour. Figure 2.10
below shows how an impact to an arbitrary structure can be represented in different
ways.
𝑣 (2.4)
𝐹 = 1.11 ∙ 0.88√𝐷𝑊𝑇 ∙
8
according to AASHTO
𝐹 = 𝑣√𝑘 ∙ 𝑚 (2.5)
according to Eurocode
𝐷𝑊𝑇 is the dead weight tonnage of the ship [metric ton]
𝑣 is the ship velocity [m/s]
𝑘 is the equivalent elastic stiffness of the ship [N/m]
𝑚 is the mass of the ship [kg]
The highly estimated forces according to Eurocode and AASHTO can be seen in an
example, Figure 2.11, by Tongji University, as mentioned in Section 2.3.3, in the case
of a collision between a bridge pier and ship.
Water
Clay
Passage at the bridge opening has been simplified and made less risky in the new
bridge concept by increasing the fairway width from 20 to 30 meters. Free sailing
height varies between 12.5 m when the bridge is closed and 29m when the bridge is
fully opened.
To inland
Göta älv
Hisingsbron
To ocean
A structure on piles is favourable due to the weak clay bottom whilst the alternative
with padding around the foundations would take up too much space in the narrow
fairway to be a viable option. Flexible protective piers (soft impact) on piles will
allow some deflections to take place if a collision occurs. A great advantage of this is
that a strong structure would cause the ship to absorb all of the energy, potentially
resulting in a rip in its hull. The risk of fire, leakage from cargo and disrupt in traffic
below or on top of bridge could be the consequence and is not acceptable at
Hisingsbron as both types of traffic are highly prioritized. Concerns like these have
indeed been decisive in the evaluation of other projects were upgrades of protective
piers got motivated (SSPA, 2014). Altogether, it is concluded that protective piers are
appropriate for Hisingsbron.
Göta älv
Hisingsbron
To ocean
Figure 3.5 Two scenarios describing the collision of the protective piers. One
scenario is when ship A collides with the 150 meters long pier.
Scenario B is when the ship collides with the 50 m long pier.
As concluded earlier, scenario B is the worst case scenario. This is when a fully
loaded, 89 meters long, Vänermax-ship is approaching the 50 meter protective pier at
an angle of 20° with a speed of 8 knots (SSPA, 2014). These results were obtained
through analysis of simulations made in SEAMAN software. Canal geometry,
statistics and predictions were some of the variables leading to the case stated above.
Figure 3.6 Colliding ship with its total force, force components and incoming
angle.
Mathematical model
Governed by differential equations
Assumptions on
Geometry Improve
Kinematics mathematical
Material law model
Loading
Boundary conditions
Etc.
Refine
Interpretation of results
analysis
Design improvements
Structural optimization
Figure 4.1 An adapted systematic scheme showing the process of finite element
analysis (Bathe, 1996).
A Static General analysis was used in Abaqus to analyse the model at first. Warning
messages were generated, pointing at the system matrix not being positive definite,
and so the analysis type was changed to Static Riks instead. This option is favourable
in cases of negative stiffness response in load-displacement, as in some buckling or
collapse behaviour (SIMULIA, 2012). It also has its benefits for ill-conditioned
problems treating unstable problems or limit loads.
Figure 4.3 Piles supporting the protective piers are attached to the bridge
foundation at the opening, giving a stiffer response of the piers.
Figure 4.5 Behaviour of a spring representing clay with a linear stiffness K until
the yielding point Py.
Cohesion forces along the pile could probably be modelled by springs as well.
Vertical clay carrying capacity is however not considered in this model and thus the
reaction forces at the bottom boundary need to be checked and discussed whether
these are sufficient or not. The clay-pile modelling is advanced as there might be
several unknown parameters which could affect the global behaviour in any direction
(Matlock, 1970).
Figure 4.6 Location of the springs represented on two piles. The same
distribution is for every pile.
Figure 4.7 Different setups of connections between main beam and piles in
Abaqus. 1) Tie constraints between surfaces. 2) Tie constraints
between node regions. 3) Tie constraints involving a fictive rigid beam.
The third setup is the most appropriate one as it gives the desired structural response
namely a beam and piles that follow each other, see Figure 4.8 [2]. The tie constraint
models, in Figure 4.7 [1] and Figure 4.7 [2], do connect the parts but not in a real
way, see Figure 4.8 [1]. Because of this the connection involving a fictive rigid beam
depicted in Figure 4.7 [3] is the one used in the model.
Both the hand calculation models and the Abaqus models described below use the
load controlled approach. The data compared in these verifications is the maximum
deflection in the centreline of the lower edge of the beam. In this approach a 10m long
simply supported beam is loaded with a point load at the centre of the beam with an
arbitrary magnitude of 3200 kN. For the Abaqus model, the point load is modified to
a line load with the same resulting magnitude, see Figure 4.10. This is done to best
represent the 2D point load in the 3D Abaqus model and also to get rid of the local
abnormities under the concentrated load. Only longitudinal reinforcement at short
ends of the beam is included in the models accounting for this.
The second model uses the same non-reinforced concrete cross-section as model 1 but
is modelled with beam elements that include shear deformations. As can be seen in
Table 4.1, this change in element property increases the deflection of the Abaqus
model with 22.1 %. This increase can be attributed to influence of shear deflections in
the global response.
Model 3) also has the same non-reinforced concrete cross-section as model 1 though
this model is modelled with tetrahedral 3D solid elements instead. The deflection of
this beam increases with 25.5 % which shows that the solid elements also include
shear deformation as for the shear flexible beam elements.
In model 4) reinforcement is added to the rectangular concrete cross-section but is
apart from that same as model 3). The deflection is lowered for both hand calculations
and Abaqus compared to model 3) which is expected due to the increased stiffness,
see Appendix D. Even though the results are lowered the difference between hand
calculations and Abaqus keeps relatively constant. The difference is 26.9 % which is
close to the difference in model three.
The model 5) has the same cross-section as the beam used for the protective pier but
is without reinforcement and is modelled with tetrahedral 3D solid elements, see
Figure 4.9. This setup increases the difference to 47.8 % compared to hand
calculations. Two more tests, 6a) and 6b), are required to see if the cross-section
shape is the influencing factor.
In model 6a) a rectangular cross-section with the same area moment of inertia as for
model 5), thus resulting in a lower depth, is analysed. Because of the same area
moment of inertia, the result of the hand calculations will remain constant but as can
be seen in Table 4.1 the deflection in Abaqus is lowered to 1.401 mm. This equates to
a margin of error of 23.2 % which is in the same magnitude as for the other models
with rectangular shapes. This indicates that the odd shape of model 5) influences the
deflection in Abaqus a great deal and that shear deformations are evident.
In model 6b) the shape of model 5) is kept constant but the depth is lowered to 1.8 m
from ordinary 2.8 m. This is done to see how much influence the depth has on the
deflection. The difference is lowered in this case to 14.04 %, see Table 4.1. This
decrease can be contributed to the reduced influence from shear deflection. As
So though the hand calculations and the final model differs as much as 52.4 % the
model can be verified by the reasoning about influence of odd cross-section and shear
deformation done in the previous sections about Timoshenko beam theory.
The beam's dynamic behaviour is harder to validate as there are many parameters in
Abaqus and assumptions in hand calculations that could give rise to the difference. It
is also found that the load setup is classified as pressure load rather than a
Figure 4.12 Principled sketch of stress distribution in steel tubes. Negative and
positive stress on each side of the neutral line.
Secondly the tie constraints lock nodes to each other in the interface between the
materials and introduce more stiffness to the pile. An alternative method to connect
the materials would be to set up a contact interaction with friction that uses a specified
behaviour in the normal and tangential directions (Johansson & Gylltoft, 2002).
Friction models do however require much computational resources, can be hard to get
to converge and can give rise to critical points (Flansbjer, 2015). Since the pile is
probable to have a large deformation, a tie constraint is motivated as the concrete will
be squeezed stuck inside the steel sheet when bending occurs and hence reflect a tie
constraint well. When local concrete response and cracks are of interest, a friction
model is more suitable. To get a good overview of how well a tie constraint resembles
the reality, the two extremes are compared namely a tie constraint model and a
frictionless contact model. Tests show that the difference in deflection for the chosen
pile setup is less than 1% and so the tie constraint is good to use, see Appendix C.
The total number of elements for each mesh size is then plotted against the maximum
deflection to see if convergence is reached. The maximum deflection is measured on
the bottom edge of the beam see Figure 4.13.
As can be seen in Figure 4.14 convergence is reached at about 13000 elements which
corresponds roughly to an element size of about 0.35 meters, see Table 4.2.
The decrease in element size will after this point only increase the computational time
as can be seen in Figure 4.15. From this the conclusion is that no larger elements than
0.35 meters have to be used for the beam.
0:50:24
[h:mm:ss]
0:43:12
0:36:00
0:28:48
0:21:36
0:14:24
0:07:12
0:00:00
0 5000 10000 15000 20000 25000 30000
Figure 4.15 The increase in computational time with increase in total number of
elements for the beam convergence study.
4.4.3.2 Piles
The convergence study for the piles is done on a single pile with the length of about
60 meters. The pile is modelled with two different elements, 3D solids for the
concrete and shell elements for the steel tube. The pile was the fixed at one end and
loaded with a 20 kN point load at the other end where deflection also was measured.
When the number of elements are calculated they are plotted against the maximum
deflections, see Figure 4.16.
Convergence
Displacement of pile [m]
7,40
7,20
7,00
6,80
6,60
6,40
6,20
6,00
0 20000 40000 60000 80000 100000 120000
As can be seen in Figure 4.16, the convergence is not fully developed. Choosing a
mesh size of 0.15m results in a less accurate deflection of pile but saves a vast amount
of computation time, see Figure 4.17, which weighs more in this case.
2:24:00
[h:mm:ss]
1:55:12
1:26:24
0:57:36
0:28:48
0:00:00
0 20000 40000 60000 80000 100000 120000
Figure 4.17 The increase in computational time with an increase in total number of
elements for the pile convergence study.
𝑚𝑣 2
𝐸𝑎 = (4.1)
2
Where:
𝐸𝑎 is the total available kinetic energy [J]
𝑚 is the mass of the object [kg]
𝑣 is the velocity of the object [m/s]
Where:
𝐸𝑑𝑒𝑓 is the deformation energy [J]
𝐸𝑎 is the total available kinetic energy [J]
𝛼 is the incoming angle of the ship [°]
The resistance of the structure will be calculated as the work done by displacing the
structure, see Equation (4.3).
𝑊 =𝐹∙𝛿 (4.3)
Where:
𝑊 is the work done on the structure [Nm]
𝐹 is the force that displaces the structure [N]
𝛿 is the displacement of the structure [m]
The work is measured by energy with the unit Joule [J] and is the same as Newton
times meter [Nm]. By the law of energy conservation, it can be stated that the total
energy of an isolated system remains constant. In other words, a collision becomes a
transformation of ship's kinetic energy into work done by the pier, 𝑊(𝑠ℎ𝑖𝑝) =
𝑊(𝑝𝑟𝑜𝑡𝑒𝑐𝑡𝑖𝑣𝑒 𝑝𝑖𝑒𝑟). This is not fully true as some energy will be absorbed by the
processes stated in Section 2.3.3.
The energy for the designing Värnermax ship used in this report is calculated to 18.9
MNm according to Equation (4.2). For the complete calculations see Appendix B.
Collision progress starts at time zero and goes on until the kinetic energy from the
incoming vessel has been absorbed. The Figure 4.18 shows a simplified expected
relation between the objects which in reality would vary non-linearly.
The sequence can also be visualized by an energy-time diagram, see Figure 4.20
which summarizes the collision progress. It is clear to see that collision end takes
place when the structure has consumed all of the ship's kinetic energy.
4.6.1 Concrete
The chosen model in Abaqus for describing the non-linear behaviour of concrete is
called “Concrete Damaged Plasticity”. For this model to work properly some general
plastic parameters and the non-linear stress-strain relationship for concrete is
described and entered into the model. For a material like concrete that is behaving
differently in compression and tension, the parameters describing these states have to
be obtained separately. An accurate way to do this is to perform tests of the chosen
concrete, however, there are codes and regulations to gain useful values of the sought
stress-strain relationships. Because of the absence of tested data in this project a code
of principles produced by a collaboration from Lund Tekniska Högskola (LTH),
Chalmers Tekniska Högskola (CTH) and Kungliga Tekniska Högskolan (KTH) by
(Carlsson, et al., 2008) called “Säkerhetsprinciper för bärighetsanalys av broar med
icke-linjära metoder” (Security principles for carrying capacity analysis of bridges
with non-linear methods) is used to obtain the non-linear data of the concrete.
4.6.1.1 Compression
In highly compressed parts of the concrete it is important that the internal forces are
able to redistribute from the crushed concrete to the reinforcement. It is essential that
the model being used is able to exhibit this behaviour in a reasonable way so that non-
linear compressive stress-strain curve gets a reasonable shape that describes its
behaviour (Carlsson, et al., 2008). The mentioned report by (Carlsson, et al., 2008)
has modelled a compressive stress-strain relationship according to the International
Federation of Concrete (fib) report from 1990 and is described by Equation (4.4) that
is able to do this in a reasonable way.
Where:
𝜀𝑢2 (𝑘 − 2) + 2𝜀𝑢 − 𝑘
𝜍=4 (4.5)
(𝜀𝑢 (𝑘 − 2) + 1)2
To make the two parts of the function fit together the value of the strain at the top of
the curve 𝜀𝑐1 is adjusted (Carlsson, et al., 2008). Using Equation (4.4) this is proved
difficult. The first part of the function is defined as Equation (4.6)
(The International Federation for Structural Concrete (fib), 2012).
𝜀𝑐 𝜀𝑐
𝜀𝑐1 (𝑘 − 𝜀𝑐1 )
𝜀 𝑓𝑐𝑐 (4.6)
1 + 𝜀 𝑐 (𝑘 − 2)
𝑐1
So to be able to make the curves to fit together Equation (4.4) and (4.6) are combined
to Equation (4.7).
𝜀𝑐 𝜀𝑐
𝜀𝑐1 (𝑘 − 𝜀𝑐1 )
𝜀 𝑓𝑐𝑐 , 0 ≤ 𝜀𝑐 ≤ 𝜀𝑢
1 + 𝜀 𝑐 (𝑘 − 2)
𝑐1
𝜎𝑐 (𝜀𝑐 ) = 𝑓𝑐𝑐 (4.7)
, 𝜀𝑐 ≥ 𝜀𝑢
𝜀𝑐 2 𝜀𝑐
𝜀 𝜀
(𝜍𝜀𝑢 − 2) ( 𝑐1 ) + (4 − 𝜍) 𝑐1
𝜀𝑢 𝜀𝑢
{
The result is a reasonable curve shape that captures the compressed concrete's non-
linear behaviour in a good way, see Figure 4.21.
𝜎𝑐
𝜀𝑐,𝑒𝑙 = (4.8)
𝐸𝑐
The limit of elasticity is set to 0.4 ∙ 𝑓𝑐𝑐 (Carlsson, et al., 2008). The input-data is
presented in Table 4.4 and the complete calculations in Appendix E.
4.6.1.2 Tension
The approach to calculate the non-linear tensile behaviour is rather different than for
the compressive part. One way to decide it is to have a curve that gives reasonable
fracture energy (Carlsson, et al., 2008). This is done by calculating the start and end
point of the plastic part of the curve. The start point is calculated by Equation (4.9)
and the end point by Equation (4.10).
𝑓𝑐𝑡
𝜀𝑡,𝑒𝑙 = (4.9)
𝐸𝑐
10 ∙ 𝜀𝑡,𝑒𝑙 (4.10)
Figure 4.22 Non-linear tensile stress-strain behaviour for concrete used in Abaqus.
As for the compressive part the input-data needed is the stress and the inelastic strain,
these values are chosen so that the curve gets the previously mentioned hang, see
Table 4.5. Calculations are found in Appendix E.
Where:
𝜎𝑏0 is the initial equibiaxial compressive yield stress [Pa]
𝜎𝑐0 is the initial uniaxial compressive yield stress [Pa]
K determines how the yield surface is described in the deviatoric plane. When K
changes, the yield surface also changes, see Figure 4.24.
Figure 4.24 Typical yield surfaces on the deviatoric plane (SIMULIA, 2012).
𝐸𝑠 𝜀, 𝜀 < 𝜀𝑦
𝑓𝑦 , 𝜀𝑦 < 𝜀 ≤ 𝜀ℎ
𝜎= (4.12)
𝜀 − 𝜀ℎ
𝑓𝑦 + 𝐸ℎ (𝜀 − 𝜀ℎ ) (1 − 𝐸ℎ ), 𝜀 > 𝜀ℎ
{ 4(𝑓𝑢 − 𝑓𝑦 )
Equation (4.12) is used to create the input-data for the stresses into the non-linear
material model for steel in Abaqus, see Figure 4.25.
As for the concrete, the strain entered into the model is not the total strain but rather
the plastic strain. This strain is calculated as the total strain 𝜀 minus the yield strain 𝜀𝑦 .
The input-data used for this model is presented in Table 4.7 and the complete
calculations in Appendix E.
Figure 5.1 Deformed and undeformed shape of the protective pier in the same
figure for comparison.
The force needed to create this deformation and move the protective pier was
calculated by measuring the reaction force at the reference point where the
displacement of the beam was applied since this force equals the total reaction force
of the protective pier. These two where then plotted against each other to be able to
calculate the total internal energy of the structure and this was done by calculating the
area under the graph, see Figure 5.2.
Energy-Arc length
1,2E+07
1,0E+07
Energy [Nm]
8,0E+06
6,0E+06
At Reference Point
4,0E+06 Whole Model
2,0E+06
0,0E+00
0 0,5 1 1,5 2 2,5
Arc length
Figure 5.3 Comparison of the hand calculated energy absorption at the reference
point and whole models internal energy calculated with ALLIE in
Abaqus.
Figure 5.4 Elements in tensile plastic strain i.e. cracked concrete elements
(light grey)
The second point was at arc length 0.2023 and this was when the first pile yields see
Figure 5.5.
The third point was at arc length 0.7363 when the yielding of the Reinforcement
starts.
The fourth point was at arc length 1.954, this was the point when the first clay spring
yields and at the fifth point is at the end of the analysis at arc length 2.232. The
reaction force and the applied displacement of these structural events are presented in
Table 5.1 and shown in Figure 5.7. Complete data regarding the force-displacement
curve are appended in Appendix F.
Force-displacement
3,5E+06
At Reference
3,0E+06 Point
Reaction force [N]
Point 1
2,5E+06
Point 2
2,0E+06
Point 3
1,5E+06
Point 4
1,0E+06
Point 5
5,0E+05
0,0E+00
0 1 2 3 4
Displacement [m]
Figure 5.7 Force-displacement curve showing different important structural
events. Point 1) First crack of concrete in span, Point 2) First pile
yields, Point 3) Reinforcement yields, Point 4) First clay spring yields,
Point 5) End of analysis.
A summary of the structural response data at the mentioned structural events is shown
in Table 5.1 to get an overview of the structural response of the whole structure. More
detailed data on the structural response of the individual parts of the protective pier is
presented later in this chapter.
5.1.2.1 Displacements
Figure 5.8 shows the displacement along the centreline at the top of beam in the
direction of the collision. The maximum deflection along this line can be found at the
end of the beam and was calculated to 4.037 meters.
-1
Displacement [m]
-1
-2
-2
-3
-3
-4
-4
-5
True distanse [m]
Figure 5.8 Displacement along the beam in the direction of the collision.
The maximum displacements of the beam was also calculated. This was done in
Abaqus for all the important arc lengths that was mentioned in Section 5.1.1 and are
presented in Table 5.2 along with their location in the model. This was done to see
when large displacements occur during the analysis. The locations of theses
displacements on the beam are also presented in Figure 5.9.
Figure 5.9 Location of maximum beam displacement. 1) Arc length 0.0528, 2) Arc
length 0.2023, 3) Arc length 0.7363, 4) Arc length 1.954, 5) Arc length
2.232.
Figure 5.10 Location of maximum beam stress. 1) Arc length 0.0528, 2) Arc length
0.2023, 3) Arc length 0.7363, 4) Arc length 1.954, 5) Arc length 2.232.
Figure 5.11 Location of nodes 27835 and 32684 on opposite sides of the beam.
Picture taken at arc length 0.0528 when the first crack in the concrete
appears.
These nodes are deemed to be of interest as they are lying in an area where the
curvature of the beam is high. The results of the tensile behaviour is presented in
Figure 5.12 and can be compared with the tensile strength of the concrete which was
3.21 MPa. Whereas the results of the compressive behaviour is presented in Figure
5.13 and can be compared with the compressive strength which was 43 MPa. As can
be seen in Figure 5.13 the compressive stress exceeds the compressive strength.
3,0E+06
Stress-arc length
behaviour
2,5E+06 Point 1
Stress [Pa]
2,0E+06 Point 2
Point 3
1,5E+06
Point 4
1,0E+06
Point 5
5,0E+05
0,0E+00
0 0,5 1 1,5 2 2,5
Arc-length [-]
Figure 5.12 Tensile stresses in node 27835 during the analysis. Also showing the
structural events, Point 1) First crack of concrete in span, Point 2)
First pile yields, Point 3) Reinforcement yields, Point 4) First clay
spring yields, Point 5) End of analysis.
Stress-arc length
5,0E+07 behaviour
Point 1
4,0E+07
Stress [Pa]
Point 2
3,0E+07 Point 3
2,0E+07 Point 4
Point 5
1,0E+07
0,0E+00
0 0,5 1 1,5 2 2,5
Arc-length [-]
Figure 5.13 Compressive stresses in node 32684 during the analysis. Also showing
the structural events, Point 1) First crack of concrete in span, Point 2)
First pile yields, Point 3) Reinforcement yields, Point 4) First clay
spring yields, Point 5) End of analysis.
Figure 5.14 Compression zone at the fixed end of the beam where the light grey
parts are in compression and the dark grey in tension. 1) Arc length
0.0528, 2) Arc length 0.2023 3) Arc length 0.7362 4) Arc length 1.954
5) Arc length 2.232
Figure 5.16 Location of maximum pile deflection. 1) Arc length 0.0528, 2) Arc
length 0.2023, 3) Arc length 0.7363, 4) Arc length 1.954, 5) Arc length
2.232.
Figure 5.17 Location of maximum pile stress. 1) Arc length 0.0528, 2) Arc length
0.2023, 3) Arc length 0.7363, 4) Arc length 1.954, 5) Arc length 2.232.
Table 5.6 Reaction forces in the piles in point 1, arc length 0.0528
Piles Reaction force in
pile [kN]
Back row
Pile 1 174.9
Pile 2 120.2
Pile 3 63.26
Pile 4 19.84
Pile 5 -0.513
Front row
Pile 6 -538.5
Pile 7 -391.2
Pile 8 -239.1
Pile 9 -112.3
Pile 10 -30.6
Table 5.7 Reaction forces in the piles in point 2, arc length 0.2023
Piles Reaction force in
pile [kN]
Back row
Pile 1 -368.2
Pile 2 -90.53
Pile 3 25.49
Pile 4 5.264
Pile 5 -8.529
Front row
Pile 6 -1112
Pile 7 -886.2
Pile 8 -561.1
Pile 9 -254.4
Pile 10 -60.40
Table 5.9 Reaction forces in the piles in point 4, arc length 1.954
Piles Reaction force in
pile [kN]
Back row
Pile 1 -1891
Pile 2 -1783
Pile 3 -1594
Pile 4 -1157
Pile 5 276.8
Front row
Pile 6 -2397
Pile 7 -1986
Pile 8 -1654
Pile 9 -1261
Pile 10 -596.5
5.1.4 Reinforcement
Since the displacement of the reinforcement coincides with the displacement of the
beam, because of the full interaction between the two, the main focus in this section
will be on the stresses of the reinforcement.
5.1.4.1 Stresses
The maximum stresses of the reinforcement at the critical events where obtained from
Abaqus and are presented in Table 5.11 along with the location in the model. For
comparison the stress-strain behaviour of the reinforcement is presented in
Appendix E. These locations are also presented in Figure 5.18.
The springs that are chosen are located on pile 1 according to Figure 5.19. Spring-0 is
the first spring located near the river bottom, Spring-20 is the spring located nearest to
the maximum deflection of the pile and Spring-50 is located in the bottom end of the
pile.
Spring-0
2500
2000
Stress [Pa]
1500
1000
500
0
0 0,0002 0,0004 0,0006 0,0008 0,001 0,0012 0,0014
Strain [-]
Spring-0
35000
30000
25000
Stress [Pa]
20000
15000
10000
5000
0
0 0,005 0,01 0,015 0,02
Strain [-]
50000
Stress [Pa]
40000
30000
20000
10000
0
0 0,02 0,04 0,06 0,08 0,1
Strain [-]
Figure 5.23 to Figure 5.25 shows the stress-strain relationship for Spring-20. The
yield pressure for Spring-20 was 164.7 kN/m and the displacement of the spring at the
time of yielding should be 0.02745 m.
Spring-20
0
-0,000005 -0,000004 -0,000003 -0,000002 -0,000001 0
-5
Stress [Pa]
-10
-15
-20
-25
-30
Strain [-]
-200
-300
-400
-500
-600
Strain [-]
Spring-20
1400
1200
1000
800
Stress [Pa]
600
400
200
0
-0,0001 -0,00005-200 0 0,00005 0,0001 0,00015 0,0002 0,00025
-400
-600
Strain [-]
Spring-50
20
18
16
Stress [Pa]
14
12
10
8
6
4
2
0
0 0,0000005 0,000001 0,0000015 0,000002
Strain [-]
Spring-50
1600
1400
1200
Stress [Pa]
1000
800
600
400
200
0
0 0,00002 0,00004 0,00006 0,00008 0,0001 0,00012 0,00014 0,00016
Strain [-]
1200
1000
800
600
400
200
0
0 0,00005 0,0001 0,00015 0,0002
Strain [-]
Figure 5.29 to Figure 5.31 shows the strain-arc length relationship for Spring-0.
Spring-0
0,0014
0,0012
0,001
Strain [-]
0,0008
0,0006
0,0004
0,0002
0
0 0,01 0,02 0,03 0,04 0,05 0,06
Figure 5.29 Strain-Arc length relationship for Spring-0 at Arc length 0.0528.
0,01
0,008
0,006
0,004
0,002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
Figure 5.30 Strain-Arc length relationship for Spring-0 at Arc length 0.7363.
Spring-0
0,09
0,08
0,07
0,06
Strain [-]
0,05
0,04
0,03
0,02
0,01
0
0 0,5 1 1,5 2 2,5
Figure 5.31 Strain-Arc length relationship for Spring-0 at Arc length 2.232.
Spring-20
0
-5E-07 0 0,01 0,02 0,03 0,04 0,05 0,06
-0,000001
-1,5E-06
Strain [-]
-0,000002
-2,5E-06
-0,000003
-3,5E-06
-0,000004
-4,5E-06
-0,000005
Arc length [-]
Figure 5.32 Strain-Arc length relationship for Spring-20 at Arc length 0.053.
Spring-20
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
-0,00001
-0,00002
-0,00003
Strain [-]
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
-0,00009
Arc length [-]
Figure 5.33 Strain-Arc length relationship for Spring-20 at Arc length 0.7363.
0,0002
0,00015
Strain [-]
0,0001
0,00005
0
0 0,5 1 1,5 2 2,5
-0,00005
-0,0001
Arc length [-]
Figure 5.34 Strain-Arc length relationship for Spring-20 at Arc length 2.232.
Figure 5.35 to Figure 5.37 shows the strain-arc length relationship for Spring-50.
Spring-50
0,000002
0,0000018
0,0000016
0,0000014
Strain [-]
0,0000012
0,000001
0,0000008
0,0000006
0,0000004
0,0000002
0
0 0,01 0,02 0,03 0,04 0,05 0,06
Figure 5.35 Strain-Arc length relationship for Spring-50 at Arc length 0.053.
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
Figure 5.36 Strain-Arc length relationship for Spring-50 at Arc length 0.7363.
Spring-50
0,00018
0,00016
0,00014
0,00012
Strain [-]
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,5 1 1,5 2 2,5
Figure 5.37 Strain-Arc length relationship for Spring-50 at Arc length 2.232.
To be able to investigate that the deformation in the pile was transferred to the spring,
the displacement of the nodes where the spring were connected was examined.
Table 5.12 Displacement of the nodes in the pile where the springs were
connected.
Arc length [-] Displacement in Displacement in Displacement in
pile 1 at Spring-0 pile 1 at Spring-20 pile 1 at Spring-50
[m] [m] [m]
0.0528 -0.1445 -0.1655 -0.0044
0.7363 -1.904 -3.401 -0.1542
2.232 -5.695 -8.333 -0.3810
6.1 Modelling
The focus in this report was to model a large part of the structure and allow long
computation times to capture the structural response well. An analysis time of 44
hours on a cluster is considered accepted for this thesis work, which is a type of
research. This might not be an efficient solution for a design company as increased
labour time could increase the project costs. As the mesh convergence study showed,
increased mesh accuracy can let the analysis time increase vastly for larger models.
The non-linear material properties are probably the governing factor influencing the
analysis time negatively in this case study.
There are many assumptions regarding the load and its application that could change
the outcome of the analysis. The report treats a load that is constantly acting in the
same global direction that is a component of the actual inclined force resultant. A
closer prediction discloses an interesting phenomenon which takes place when the
protective pier bends back at collision. The transversal force acting on the pier has a
potential to increase as the normal to the face of the pier turns towards the incoming
ship and hence increases the transversal component of the force, see Figure 6.1.
Nevertheless, the ship might be pushed in the right direction during the collision and
then the transversal force component decreases.
Figure 6.1 Displacement of protective pier due to ship impact with increased
transversal force component.
Another aspect is that the ship could be sliding along the pier while the load was
resisted and so the structure would behave differently than described in Chapter 5. It
is conservative to absorb the load the way it was done in this report, at the end of the
pier. If the point of impact was closer to the bridge, more pile groups would work
together and also the influence of the fixed support would be greater, resulting in a
greater capacity of the pier at that point.
An assumption was made when modelling the I- and T-beam as totally rigid. These
parts could in reality move independently and interact through contact and friction. It
is not considered as very possible but this still means that the main beam and the pile
groups would not necessarily have the same deformation behaviour. The very
complex global behaviour of the protective pier makes it hard to predict what could
have occurred if these parts were modelled as in reality. Worth mentioning is that
stresses were found to be high in the piles right below the rigid beams which could
give rise to these actions.
The chosen method of comparing energies has its limitations in validity as a crucial
assumption was made. Protective piers are not necessarily in their original shape
when the design collision occurs. If the impact happens after several years it is very
probable that several minor hits have taken place (SSPA, 2014). Many small
imperfections from these hits could have reduced the capacity of the protective pier
that later on would result in more damage at lower loads.
7.1 Modelling
Despite a profound literature study there was not many papers found in the field of
protective piers. There are in general little knowledge of these types of structures
since there have not been many full scale tests to use as reference. Historical accidents
have created the need for protective structures in waterways and thereby driven the
engineering knowledge forward to the level so that it is now incorporated in design
process of bridges and other exposed constructions from the very beginning. Despite
this, the codes are not fully developed to treat this type of structure in detail. The part
of Eurocode that was used in the report was an informative annex with no clear
information of the impact phenomena. The report clearly states that there are a lot of
parameters, which are not treated in the codes. This concludes that a lot of
development in this research area ought to be done. It is however not impossible that
documentation is kept inside companies.
tryck)
Clay yield pressure
Beam bed module
(Balkbäddmodul)
(Lerans flyttryck)
Displacement of
spring Ku at py
(Bäddmodul)
Corrected cu
Bed module
Depth
Level
ku Ku py δ
3
m kPa kN/m kN/m² kN/m m kN kN
-20
Depth (from top of clay)
-30
-40
-50
-60
-70
-80
Clay yield pressure, py
Force-Displacement
At Reference
3500000 Point
3000000
Point 1
Reaction force [N]
2500000 Point 2
2000000 Point 3
1500000
Point 4
1000000
Point 5
500000
0
0 1 2 3 4
Displacement [m]
Figure F.1
10000000
8000000
Energy [MNm]
6000000
At Reference Point
4000000
Whole Model
2000000
0
0 0,5 1 1,5 2 2,5
Arc length
Figure F.2 The absorbed energy by the protective pier calculated with ALLIE (solid
line) and by hand (dashed line).
Spring-0
2500
2000
Stress [Pa]
1500
1000
500
0
0 0,0002 0,0004 0,0006 0,0008 0,001 0,0012 0,0014
Strain [-]
Figure G.1 Stress-strain relationship for Spring-0 at Arc length 0.0528.
Spring-6
500
450
400
350
Stress [Pa]
300
250
200
150
100
50
0
0 0,00002 0,00004 0,00006 0,00008 0,0001 0,00012 0,00014 0,00016
Strain [-]
Figure G.2 Stress-strain relationship for Spring-6 at Arc length 0.0528.
-50
Stress [Pa]
-100
-150
-200
-250
Strain [-]
Figure G.3 Stress-strain relationship for Spring-10 at Arc length 0.0528.
Spring-12
0
-0,00008 -0,00007 -0,00006 -0,00005 -0,00004 -0,00003 -0,00002 -0,00001 0
-50
-100
Stress [Pa]
-150
-200
-250
-300
-350
Strain [-]
Figure G.4 Stress-strain relationship for Spring-12 at Arc length 0.0528.
-10
-15
-20
-25
-30
Strain [-]
Figure G.5 Stress-strain relationship for Spring-20 at Arc length 0.0528.
Spring-30
5
4,5
4
3,5
Stress [Pa]
3
2,5
2
1,5
1
0,5
0
0 0,0000001 0,0000002 0,0000003 0,0000004 0,0000005 0,0000006
Strain [-]
Figure G.6 Stress-strain relationship for Spring-30 at Arc length 0.0528.
-1
Stress [Pa]
-1,5
-2
-2,5
-3
-3,5
Strain [-]
Figure G.7 Stress-strain relationship for Spring-40 at Arc length 0.0528.
Spring-50
20
18
16
14
Stress [Pa]
12
10
8
6
4
2
0
0 0,0000005 0,000001 0,0000015 0,000002
Strain [-]
Figure G.8 Stress-strain relationship for Spring-50 at Arc length 0.0528.‘
Spring-0
8000
7000
6000
Stress [Pa]
5000
4000
3000
2000
1000
0
0 0,0005 0,001 0,0015 0,002 0,0025 0,003 0,0035 0,004
Strain [-]
Figure G.9 Stress-strain relationship for Spring-0 at Arc length 0.2023.
Spring-6
1800
1600
1400
Stress [Pa]
1200
1000
800
600
400
200
0
0 0,0001 0,0002 0,0003 0,0004 0,0005 0,0006
Strain [-]
Figure G.10 Stress-strain relationship for Spring-6 at Arc length 0.2023.
-200
Stress [Pa]
-300
-400
-500
-600
-700
-800
Strain [-]
Figure G.11 Stress-strain relationship for Spring-10 at Arc length 0.2023.
Spring-12
0
-0,00025 -0,0002 -0,00015 -0,0001 -0,00005 0
-200
Stress [Pa]
-400
-600
-800
-1000
-1200
Strain [-]
Figure G.12 Stress-strain relationship for Spring-12 at Arc length 0.2023.
-20
-30
Stress [Pa]
-40
-50
-60
-70
-80
-90
-100
Strain [-]
Figure G.13 Stress-strain relationship for Spring-20 at Arc length 0.2023.
Spring-30
9
8
7
Stress [Pa]
6
5
4
3
2
1
0
0 0,0000002 0,0000004 0,0000006 0,0000008 0,000001 0,0000012
Strain [-]
Figure G.14 Stress-strain relationship for Spring-30 at Arc length 0.2023.
-4
Stress [Pa]
-6
-8
-10
-12
-14
Strain [-]
Figure G.15 Stress-strain relationship for Spring-40 at Arc length 0.2023.
Spring-50
70
60
50
Stress [Pa]
40
30
20
10
0
0 0,000001 0,000002 0,000003 0,000004 0,000005 0,000006 0,000007
Strain [-]
Figure G.16 Stress-strain relationship for Spring-50 at Arc length 0.2023.
Spring-0
35000
30000
25000
Stress [Pa]
20000
15000
10000
5000
0
0 0,005 0,01 0,015 0,02
Strain [-]
Figure G.17 Stress-strain relationship for Spring-0 at Arc length 0.7363.
Spring-6
7000
6000
5000
Stress [Pa]
4000
3000
2000
1000
0
0 0,0005 0,001 0,0015 0,002
Strain [-]
Figure G.18 Stress-strain relationship for Spring-6 at Arc length 0.7363.
-1000
Stress [Pa]
-1500
-2000
-2500
-3000
-3500
-4000
Strain [-]
Figure G.19 Stress-strain relationship for Spring-10 at Arc length 0.7363.
Spring-12
0
-0,0012 -0,001 -0,0008 -0,0006 -0,0004 -0,0002 -500 0
-1000
-1500
Stress [Pa]
-2000
-2500
-3000
-3500
-4000
-4500
-5000
Strain [-]
Figure G.20 Stress-strain relationship for Spring-12 at Arc length 0.7363.
-200
-300
-400
-500
-600
Strain [-]
Figure G.21 Stress-strain relationship for Spring-20 at Arc length 0.7363.
Spring-30
70
60
50
Stress [Pa]
40
30
20
10
0
-0,000004 -0,000002 0 0,000002 0,000004 0,000006 0,000008 0,00001
-10
-20
Strain [-]
Figure G.22 Stress-strain relationship for Spring-30 at Arc length 0.7363.
-80
-100
-120
-140
-160
-180
-200
Strain [-]
Figure G.23 Stress-strain relationship for Spring-30 at Arc length 0.7363.
Spring-50
1600
1400
1200
Stress [Pa]
1000
800
600
400
200
0
0 0,00002 0,00004 0,00006 0,00008 0,0001 0,00012 0,00014 0,00016
Strain [-]
Figure G.24 Stress-strain relationship for Spring-50 at Arc length 0.7363.
Spring-0
60000
50000
Stress [Pa]
40000
30000
20000
10000
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07
Strain [-]
Figure G.25 Stress-strain relationship for Spring-0 at Arc length 1.954.
Spring-6
14000
12000
10000
Stress [Pa]
8000
6000
4000
2000
0
0 0,001 0,002 0,003 0,004 0,005
Strain [-]
Figure G.26 Stress-strain relationship for Spring-6 at Arc length 1.954.
-6000
-8000
-10000
-12000
-14000
-16000
-18000
Strain [-]
Figure G.27 Stress-strain relationship for Spring-10 at Arc length 1.954.
Spring-12
0
-0,005 -0,004 -0,003 -0,002 -0,001 -2000 0
-4000
-6000
Stress [Pa]
-8000
-10000
-12000
-14000
-16000
-18000
-20000
Strain [-]
Figure G.28 Stress-strain relationship for Spring-12 at Arc length 1.954.
800
600
Stress [Pa]
400
200
0
-0,0001 -0,00005 0 0,00005 0,0001 0,00015 0,0002
-200
-400
-600
Strain [-]
Figure G.29 Stress-strain relationship for Spring-20 at Arc length 1.954.
Spring-30
200
100
0
Stress [Pa]
-200
-300
-400
-500
-600
Strain [-]
Figure G.30 Stress-strain relationship for Spring-30 at Arc length 1.954.
-200
Stress [Pa]
-300
-400
-500
-600
-700
-800
Strain [-]
Figure G.31 Stress-strain relationship for Spring-40 at Arc length 1.954.
Spring-50
1800
1600
1400
Stress [Pa]
1200
1000
800
600
400
200
0
0 0,00005 0,0001 0,00015 0,0002
Strain [-]
Figure G.32 Stress-strain relationship for Spring-50 at Arc length 1.954.
Spring-0
60000
50000
Stress [Pa]
40000
30000
20000
10000
0
0 0,02 0,04 0,06 0,08 0,1
Strain [-]
Figure G.33 Stress-strain relationship for Spring-0 at Arc length 2.232.
Spring-6
25000
20000
Stress [Pa]
15000
10000
5000
0
0 0,001 0,002 0,003 0,004 0,005 0,006 0,007
Strain [-]
Figure G.34 Stress-strain relationship for Spring-6 at Arc length 2.232.
-5000
Stress [Pa]
-10000
-15000
-20000
-25000
Strain [-]
Figure G.35 Stress-strain relationship for Spring-10 at Arc length 2.232.
Spring-12
0
-0,006 -0,005 -0,004 -0,003 -0,002 -0,001 0
-5000
Stress [Pa]
-10000
-15000
-20000
-25000
Strain [-]
Figure G.36 Stress-strain relationship for Spring-12 at Arc length 2.232.
600
400
200
0
-0,0001 -0,00005-200 0 0,00005 0,0001 0,00015 0,0002 0,00025
-400
-600
Strain [-]
Figure G.37 Stress-strain relationship for Spring-20 at Arc length 2.232.
Spring-30
200
100
0
-0,00012 -0,0001 -0,00008 -0,00006 -0,00004 -0,00002-100 0 0,00002
Stress [Pa]
-200
-300
-400
-500
-600
-700
-800
-900
Strain [-]
Figure G.38 Stress-strain relationship for Spring-30 at Arc length 2.232.
-200
Stress [Pa]
-300
-400
-500
-600
-700
-800
Strain [-]
Figure G.39 Stress-strain relationship for Spring-40 at Arc length 2.232.
Spring-50
1800
1600
1400
Stress [Pa]
1200
1000
800
600
400
200
0
0 0,00005 0,0001 0,00015 0,0002
Strain [-]
Figure G.40 Stress-strain relationship for Spring-50 at Arc length 2.232.
Spring-0
0,0014
0,0012
0,001
Strain [-]
0,0008
0,0006
0,0004
0,0002
0
0 0,01 0,02 0,03 0,04 0,05 0,06
Spring-6
0,00016
0,00014
0,00012
Strain [-]
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,01 0,02 0,03 0,04 0,05 0,06
-0,00002
Strain [-]
-0,00003
-0,00004
-0,00005
-0,00006
Arc length [-]
Figure G.43 Strain-arc length relationship for Spring-10 at Arc length 0.0528.
Spring-12
0
0 0,01 0,02 0,03 0,04 0,05 0,06
-0,00001
-0,00002
Strain [-]
-0,00003
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
Arc length [-]
Figure G.44 Strain-arc length relationship for Spring-12 at Arc length 0.0528.
-0,000001
-1,5E-06
Strain [-]
-0,000002
-2,5E-06
-0,000003
-3,5E-06
-0,000004
-4,5E-06
-0,000005
Arc length [-]
Figure G.45 Strain-arc length relationship for Spring-20 at Arc length 0.0528.
Spring-30
0,0000006
0,0000005
0,0000004
Strain [-]
0,0000003
0,0000002
0,0000001
0
0 0,01 0,02 0,03 0,04 0,05 0,06
-1E-07
Strain [-]
-1,5E-07
-2E-07
-2,5E-07
-3E-07
-3,5E-07
Arc length [-]
Figure G.47 Strain-arc length relationship for Spring-40 at Arc length 0.0528.
Spring-50
0,000002
0,0000018
0,0000016
0,0000014
Strain [-]
0,0000012
0,000001
0,0000008
0,0000006
0,0000004
0,0000002
0
0 0,01 0,02 0,03 0,04 0,05 0,06
Spring-0
0,004
0,0035
0,003
Strain [-]
0,0025
0,002
0,0015
0,001
0,0005
0
0 0,05 0,1 0,15 0,2 0,25
Spring-6
0,0006
0,0005
0,0004
Strain [-]
0,0003
0,0002
0,0001
0
0 0,05 0,1 0,15 0,2 0,25
-0,00008
-0,0001
-0,00012
-0,00014
-0,00016
-0,00018
Arc length [-]
Figure G.51 Strain-arc length relationship for Spring-10 at Arc length 0.2023.
Spring-12
0
0 0,05 0,1 0,15 0,2 0,25
-0,00005
Strain [-]
-0,0001
-0,00015
-0,0002
-0,00025
Arc length [-]
Figure G.52 Strain-arc length relationship for Spring-12 at Arc length 0.2023.
-0,000004
Strain [-]
-0,000006
-0,000008
-0,00001
-0,000012
-0,000014
-0,000016
Arc length [-]
Figure G.53 Strain-arc length relationship for Spring-20 at Arc length 0.2023.
Spring-30
0,0000012
0,000001
0,0000008
Strain [-]
0,0000006
0,0000004
0,0000002
0
0 0,05 0,1 0,15 0,2 0,25
-4E-07
Strain [-]
-6E-07
-8E-07
-0,000001
-1,2E-06
-1,4E-06
Arc length [-]
Figure G.55 Strain-arc length relationship for Spring-40 at Arc length 0.2023.
Spring-50
0,000007
0,000006
0,000005
Strain [-]
0,000004
0,000003
0,000002
0,000001
0
0 0,05 0,1 0,15 0,2 0,25
Spring-0
0,018
0,016
0,014
0,012
Strain [-]
0,01
0,008
0,006
0,004
0,002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
Spring-6
0,002
0,0018
0,0016
0,0014
Strain [-]
0,0012
0,001
0,0008
0,0006
0,0004
0,0002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
-0,0002
-0,0003
Strain [-]
-0,0004
-0,0005
-0,0006
-0,0007
-0,0008
-0,0009
-0,001
Arc length [-]
Figure G.59 Strain-arc length relationship for Spring-10 at Arc length 0.7363.
Spring-12
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
-0,0002
-0,0004
Strain [-]
-0,0006
-0,0008
-0,001
-0,0012
Arc length [-]
Figure G.60 Strain-arc length relationship for Spring-12 at Arc length 0.7363.
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
-0,00009
Arc length [-]
Figure G.61 Strain-arc length relationship for Spring-20 at Arc length 0.7363.
Spring-30
0,00001
0,000008
0,000006
Strain [-]
0,000004
0,000002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
-0,000002
-0,000004
Arc length [-]
Figure G.62 Strain-arc length relationship for Spring-30 at Arc length 0.7363.
-0,000004
-0,000006
Strain [-]
-0,000008
-0,00001
-0,000012
-0,000014
-0,000016
-0,000018
-0,00002
Arc length [-]
Figure G.63 Strain-arc length relationship for Spring-40 at Arc length 0.7363.
Spring-50
0,00016
0,00014
0,00012
Strain [-]
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8
Spring-0
0,07
0,06
0,05
Strain [-]
0,04
0,03
0,02
0,01
0
0 0,5 1 1,5 2 2,5
Spring-6
0,0045
0,004
0,0035
0,003
Strain [-]
0,0025
0,002
0,0015
0,001
0,0005
0
0 0,5 1 1,5 2 2,5
-0,002
-0,0025
-0,003
-0,0035
-0,004
-0,0045
Arc length [-]
Figure G.67 Strain-arc length relationship for Spring-10 at Arc length 1.954.
Spring-12
0
0 0,5 1 1,5 2 2,5
-0,0005
-0,001
-0,0015
Strain [-]
-0,002
-0,0025
-0,003
-0,0035
-0,004
-0,0045
Arc length [-]
Figure G.68 Strain-arc length relationship for Spring-12 at Arc length 1.954.
0,00015
0,0001
Strain [-]
0,00005
0
0 0,5 1 1,5 2 2,5
-0,00005
-0,0001
Arc length [-]
Figure G.69 Strain-arc length relationship for Spring-20 at Arc length 1.954.
Spring-30
0,00002
0,00001
0
-0,00001 0 0,5 1 1,5 2 2,5
Strain [-]
-0,00002
-0,00003
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
Arc length [-]
Figure G.70 Strain-arc length relationship for Spring-30 at Arc length 1.954.
-0,00002
Strain [-]
-0,00003
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
Arc length [-]
Figure G.71 Strain-arc length relationship for Spring-40 at Arc length 1.954.
Spring-50
0,00018
0,00016
0,00014
0,00012
Strain [-]
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,5 1 1,5 2 2,5
Spring-0
0,09
0,08
0,07
0,06
Strain [-]
0,05
0,04
0,03
0,02
0,01
0
0 0,5 1 1,5 2 2,5
Spring-6
0,007
0,006
0,005
Strain [-]
0,004
0,003
0,002
0,001
0
0 0,5 1 1,5 2 2,5
-0,002
Strain [-]
-0,003
-0,004
-0,005
-0,006
Arc length [-]
Figure G.75 Strain-arc length relationship for Spring-10 at Arc length 2.232.
Spring-12
0
0 0,5 1 1,5 2 2,5
-0,001
-0,002
Strain [-]
-0,003
-0,004
-0,005
-0,006
Arc length [-]
Figure G.76 Strain-arc length relationship for Spring-12 at Arc length 2.232.
0,0002
0,00015
Strain [-]
0,0001
0,00005
0
0 0,5 1 1,5 2 2,5
-0,00005
-0,0001
Arc length [-]
Figure G.77 Strain-arc length relationship for Spring-20 at Arc length 2.232.
Spring-30
0,00002
0
0 0,5 1 1,5 2 2,5
-0,00002
Strain [-]
-0,00004
-0,00006
-0,00008
-0,0001
-0,00012
Arc length [-]
Figure G.78 Strain-arc length relationship for Spring-30 at Arc length 2.232.
-0,00002
Strain [-]
-0,00003
-0,00004
-0,00005
-0,00006
-0,00007
-0,00008
Arc length [-]
Figure G.79 Strain-arc length relationship for Spring-40 at Arc length 2.232.
Spring-50
0,00018
0,00016
0,00014
0,00012
Strain [-]
0,0001
0,00008
0,00006
0,00004
0,00002
0
0 0,5 1 1,5 2 2,5