Hoarding Construction at Arkema Kerteh 2 Project

This document outlines the manpower, equipment, and resources needed for hoarding construction at the Arkema Kerteh 2 project over February and March. It shows that the project management team will consist of 6 people working full time. The execution team will range from 66 to 132 people depending on the week. A variety of equipment such as generators, welding machines, and portable toilets are also scheduled. The total manhours planned are 3060 for project management and 11220 for execution by the end of March.

Uploaded by

Mohd Azrin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
174 views1 page

Hoarding Construction at Arkema Kerteh 2 Project

This document outlines the manpower, equipment, and resources needed for hoarding construction at the Arkema Kerteh 2 project over February and March. It shows that the project management team will consist of 6 people working full time. The execution team will range from 66 to 132 people depending on the week. A variety of equipment such as generators, welding machines, and portable toilets are also scheduled. The total manhours planned are 3060 for project management and 11220 for execution by the end of March.

Uploaded by

Mohd Azrin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

HOARDING CONSTRUCTION AT ARKEMA KERTEH 2

PROJECT
MONTH February March
MANPOWER WEEK 1 2 3 4 5 6 7 8 9
CUT -OFF DATE 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar
PROJECT MANAGEMENT TEAM (PMT)
1 Project Manager 1 1 1 1 1 1 1 1 1
2 Site Manager 1 1 1 1 1 1 1 1 1
3 PTW Coordinator 1 1 1 1 1 1 1 1 1
4 Safety Supervisor 1 1 1 1 1 1 1 1 1
5 Procurement 1 1 1 1 1 1 1 1 1
6 Admin/ HR 1 1 1 1 1 1 1 1 1

Working Hours 60 60 30 60 60 60 60 60 60
Total Man Power 36 36 18 36 36 36 36 36 36
Total Manhour 360 360 180 360 360 360 360 360 360
Acc. ManHour 360 720 900 1260 1620 1980 2340 2700 3060

MONTH February March


MANPOWER WEEK 1 2 3 4 5 6 7 8 9
CUT -OFF DATE 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar
EXECUTION TEAM
1 Supervisor 1 1 1 1 1 1 1 1 1
2 Foreman 2 2 2 2 2 2 2 2 2
3 Welder 4 4 4 4 4 4 4 4 4
4 Fitter 5 5 5 5 5 5 5 5 5
5 Rigger 2 2 2 2 2 2 2 2 2
6 Helper 5 5 5 5 5 5 5 5 5
7 Fire Watch 3 3 3 3 3 3 3 3 3

Working Hours 60 60 30 60 60 60 60 60 60
Total Man Power 132 132 66 132 132 132 132 132 132
Total Manhour 1320 1320 660 1320 1320 1320 1320 1320 1320
Acc. ManHour 1320 2640 3300 4620 5940 7260 8580 9900 11220

MONTH February March


MACHINERY & FACILITY WEEK 1 2 3 4 5 6 7 8 9
CUT -OFF DATE 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar
1 Generator Set (25kva) 1 1 1 1 1 1 1 1 1
2 Generator Set Portable (5kva) 2 2 2 2 2 2 2 2 2
3 JCB Backhoe 0 0 0 1 0 0 0 0 0
3 Panel Box 1 1 1 1 1 1 1 1 1
4 Welding Machine 4 4 4 4 4 4 4 4 4
5 Grinder 6 6 6 6 6 6 6 6 6
6 High Speed Cutting Machine 2 2 2 2 2 2 2 2 2
6 Socket Plug 5 5 5 5 5 5 5 5 5
7 Hand Drill 3 3 3 3 3 3 3 3 3
8 Extension Wire (15m length) 10 10 10 10 10 10 10 10 10
9 Gas Detector 3 3 3 3 3 3 3 3 3
10 Lightning Detector 1 1 1 1 1 1 1 1 1
11 Temporary Office 20Feet 1 1 1 1 1 1 1 1 1
12 Fire Extinguisher 5 5 5 5 5 5 5 5 5
13 Canopy 20' x 20' 2 2 2 2 2 2 2 2 2
14 Portable toilet (200L) 1 1 1 1 1 1 1 1 1
15 Water Dispenser 1 1 1 1 1 1 1 1 1

Total Item 48 48 48 49 48 48 48 48 48
Acc. Total Item 48 96 144 193 241 289 337 385 433