Hoarding Construction at Arkema Kerteh 2 Project
Hoarding Construction at Arkema Kerteh 2 Project
PROJECT
MONTH February March
MANPOWER WEEK 1 2 3 4 5 6 7 8 9
CUT -OFF DATE 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar
PROJECT MANAGEMENT TEAM (PMT)
1 Project Manager 1 1 1 1 1 1 1 1 1
2 Site Manager 1 1 1 1 1 1 1 1 1
3 PTW Coordinator 1 1 1 1 1 1 1 1 1
4 Safety Supervisor 1 1 1 1 1 1 1 1 1
5 Procurement 1 1 1 1 1 1 1 1 1
6 Admin/ HR 1 1 1 1 1 1 1 1 1
Working Hours 60 60 30 60 60 60 60 60 60
Total Man Power 36 36 18 36 36 36 36 36 36
Total Manhour 360 360 180 360 360 360 360 360 360
Acc. ManHour 360 720 900 1260 1620 1980 2340 2700 3060
Working Hours 60 60 30 60 60 60 60 60 60
Total Man Power 132 132 66 132 132 132 132 132 132
Total Manhour 1320 1320 660 1320 1320 1320 1320 1320 1320
Acc. ManHour 1320 2640 3300 4620 5940 7260 8580 9900 11220
Total Item 48 48 48 49 48 48 48 48 48
Acc. Total Item 48 96 144 193 241 289 337 385 433