Scaffold Report
Scaffold Report
Mohanad Mosaad
Ahmed Zaid
Ammar Essam
Omar Mattar
Introduction:
During next plant major shut down, there will be plenty of scaffolds required to perform the
planned activities (around 6000 mᶟ) which exceeds normal maintenance scaffold materials stock.
As a response to the fact of scaffold materials shortage during plant shut down period ,Maintenance
department tried to deal with a specialized scaffold contractor to cover the required scaffold quantities
before shut down starting date.
Main Parties:
Owner: Egyptian Methanex Methanol Company (EMX)
Contractor: Isotermica Contracting Company
Contract Type:
Lump Sum contract (Purchase order) for scaffold erection with fixed fee distributed along
the required period with ascending order.
Advantages:
Disadvantages:
1- Contract did not specify the required quantity per each working month.
2- Contract did not specify the required entry permits fees responsibility.
3- Contract did not have an incentive fee to motivate contractor achieving targets.
The Egyptian Methanex Methanol Company S.A.E
SECTION: SUB-SECTION:
Maintenance Department General Maintenance
TITLE: DOCUMENT #:
Scaffold Installation & Dismantle SOW
1. Purpose
The main purpose of this document is to help the contractor understand minimum requirements for
Scaffold erection, Modifications & Dismantle during EMethanex next turn around.
2. General
This SOW does not intend to specify all the details or all of the items that may be required fo r the proper
installation of scaffolds.
Deviation from the SOW required prior Emethanex approval.
3. Objective
Installation of access scaffolds as well as modifications & dismantle for the installed scaffolds
according to activities needs as a lump sum.
4. Scope Of Work
The scope of work will be including the following items:
Page 3 of 5
The Egyptian Methanex Methanol Company S.A.E
SECTION: SUB-SECTION:
Maintenance Department General Maintenance
TITLE: DOCUMENT #:
Scaffold Installation & Dismantle SOW
5. Contractor obligations
5.1. Work Construction Program
a) Survey all the required scaffold dimensions and locations to determine the required scaffold
accessories before starting the job by enough time and identifying noncompliance in the
dimensions.
b) Provide a detailed project schedule in compliant with the total required scaffold quantities and
durations.
c) Provide technical support in scaffolding design whenever it’s required.
d) Provide hot dip Galvanized materials according to EN 39:2001 (the Galvanizing Coating
Thickness should be identified).
e) Load certificates should be sent along with material for the couplers, tubes & wooden boards.
f) Barricade the work area according to EMX Tape & Barricade Procedure no. EG2RC0082
(Appendix #01).
g) Installation & Dismantling Scaffolding according to EMX Scaffolding Procedure.
h) Perform Modifications to erected scaffolds based on business needs.
i) Providing all hand tools, Scaffold Spanner Lanyards, tool bags for scaffold couplers &
Scaffolders Belts. Noted that all will be inspected by EMX staff prior to the job for acceptance.
j) Provide and ensure 24-7 of supervision. Noted that every supervisor will be assigned to cover
20 workers
k) Provide competent safety officers to cover 24-7 activities and ensure all will be done in a safe
manner. Noted that every safety officer will be assigned to cover 20 workers
l) Provide all PPEs included FRC Coveralls & special PPEs “Full Body Harness, Retractable
Wheel Fall Arrestor ….etc.”
m) Provide transportation for the task force.
Page 4 of 5
The Egyptian Methanex Methanol Company S.A.E
SECTION: SUB-SECTION:
Maintenance Department General Maintenance
TITLE: DOCUMENT #:
Scaffold Installation & Dismantle SOW
6. EMethanex Obligations
7. Safety
All the activities executed by the contractor must be in accordance with the project safety
regulation. The contractor must assure that all his personnel respect the rules and using the
accident prevention means as per EMethanx’s RC Policy (Appendix# 03).
8. Appendices
9.1. Appendix# 01 Tape & Barricade Procedure.
9.2. Appendix# 02 Scaffold Procedure.
9.3. Appendix# 03 RC Policy.
Page 5 of 5