Standard Commissioning Procedure For Exhaust Air Heat Recovery Systems
Standard Commissioning Procedure For Exhaust Air Heat Recovery Systems
Standard Commissioning Procedure For Exhaust Air Heat Recovery Systems
General Notes:
1. This is a generic test procedure for exhaust air heat recovery systems. If the complexity, configuration, or
other aspects of a specific project require substitute tests or additional tests, explain on the comments sheets, and
attach the additional test procedures and field data. Due to the many possible types of heat recovery systems and
their controls, it is likely that this will be necessary. Note also that not all questions or tests apply to all types of
systems. Attach all relevant functional performance verification sheets, and always attach the final signed and dated
procedure certification page.
2. In all test sections, circle or otherwise highlight any responses that indicate deficiencies (i.e. responses that
don’t meet the criteria for acceptance). Acceptance requires correction and retest of all deficiencies, as defined in
each test section under “Criteria for Acceptance” or “Acceptance”. Attach all retest data sheets. Complete the
Deficiency Report Form for all deficiencies.
3. This Commissioning Procedure does not address fire and life safety or basic equipment safety controls.
4. To ensure that this Commissioning Procedure will not damage any equipment or affect any equipment
warranties, have the equipment manufacturer’s representative review all test procedures prior to execution.
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 1
April 1999
Building Name:
INSTALLED CHARACTERISTICS:
Enter answers from field inspection. Note under response if the feature as installed differs in any way from the design
documents. If an item does not apply, write “NA”j for not applicable.
Criteria for Acceptance: Installed characteristics must be in accordance with design intent documentation and/or
approved submittals.
DESCRIPTION RESPONSE
(add sheets as necessary to adequately describe)
9.
10.
COMMENTS ON INSTALLED CHARACTERISTICS ITEMS (item #, unit #, comment). Add more sheets as needed:
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 2
April 1999
Building Name:
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 3
April 1999
Building Name:
SYSTEM COMPONENT NAMEPLATE DATA (From equipment nameplates, as recorded in field. Attach other sheets
as necessary.):
Criteria for Acceptance: Nameplate data must be in accordance with submittals as approved by Designer.
EQUIPMENT TYPE UNIT # MANUFACTURER MODEL # CAPACITY * COMMENTS
6.Fan, exhaust
7.Booster fan, exhaust
8.Booster fan, exhaust
9.Booster fan, exhaust
10. Booster fan, exhaust
24.
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 4
April 1999
Building Name:
25.
* Include all relevant capacity parameters, and units. For example, for coils in a run-around system, include air-side CFM and delta P
and water-side GPM and delta P. For heat pipes, heat wheels, and plate heat exchangers include both exhaust and supply CFM and
delta P. For expansion tanks, note ft3. For pumps, note GPM , TDH, and FLA. For fans, note CFM, static pressure, and FLA.
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 5
April 1999
Building Name:
INSTALLATION VERIFICATION:
Instructions: Under each unit write "Y" for yes, "N" for no, "NA" for not applicable, or a number to refer to any needed
comments. If other information is requested such as temperature, write the appropriate values. If a motor is driven by
a VFD, complete also the Standard Commissioning Procedure for VFDs. If the motor is VFD-driven, make all supply
fan electrical measurements upstream of the VFD, unless directed otherwise, and use a true RMS multimeter for all
supply fan motor and drive electrical measurements.
Current and voltage imbalance is defined as the greatest difference between the measurement for any of the 3 phases
and the average of the 3 phases, that quantity divided by the average of the 3 phases. As an example, if the voltage
measurements are 451, 461, and 463, then the average is 458.3 volts. The greatest difference between any
measurement and the average is 451-458.3, or 7.3 volts. Then, the voltage imbalance is 7.3 volts / 458.3 volts, or
0.016. As a percentage, this is 1.6%, and would be acceptable by the criteria below.
Criteria for Acceptance: All items in this section require answers of “Y” (or “NA”, where relevant) except where other
criteria are noted.
COILS / HEAT EXCHANGERS UNIT #
INSPECTION ITEM
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 6
April 1999
Building Name:
27.
FANS UNIT #
INSPECTION ITEM
PUMPS UNIT #
INSPECTION ITEM
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 7
April 1999
Building Name:
UNIT #
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 8
April 1999
Building Name:
28.
29.
30.
Basic performance tests: With the system in the full recovery mode, record the following. The design line in each test set refers to
the design condition as reflected in catalog data, drawings, design intent document, etc. The measured line refers to your test
results.
Criteria for Acceptance: The measured value for tests marked with an ““ must be within 15% of the design value as noted on
each previous line. Measured fan currents (tests # 85 and 95) must be less than or equal to the design value.
UNIT #
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 9
April 1999
Building Name:
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 10
April 1999
Building Name:
Start/Stop Control (include interlocks, time-of-day control, outside temperature lockout, etc.):
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
Capacity Control (e.g. heat pipe tilt as a function of discharge air temperature, 3-way valve modulation, heat wheel
speed, etc.):
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 11
April 1999
Building Name:
Describe the tests that were done to verify the control sequence:
Conclusions:
Other Control:
Describe the control sequence:
Describe the tests that were done to verify the control sequence:
Conclusions:
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 12
April 1999
Building Name:
I certify that the data and test results as recorded herein are accurate.
file:\msoffice\winword\docs\scl/cxproc\htrecqas.pro
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page 13
April 1999
Building Name:
Start/Stop Control (include interlocks, time-of-day control, outside temperature lockout, etc.):
Describe the control sequence:
Exhaust fans are interlocked with respective supply fans. Loop circulation pump starts when any supply fan
in heat recovery system starts. Circulation pumps (P1 & P2) are lead/lag with lead pump alternating on
each start cycle. Circulation pumps are locked out when the outdoor air temperature (T2) is between 55F
and 80F (adjustable at EMCS). 3-way valve closed to respective supply coil on start-up. Valve modulates
open per capacity control sequence (below) after 5 minute delay. Note that only supply fans 2 and 4 are
equipped with heat recovery systems. SF1, 3, 5, and 6 do not have heat recovery.
Describe the tests that were done to verify the control sequence:
We monitored the outdoor air temperature (OSAT), the circulation pump (P1 & P2) currents, exhaust fan #2
and #4 currents, and supply fan #2 and #4 currents concurrently for two days. [This could also be recorded
field observations.] During this time the OSAT varied between 45 and 65F, so we reset the upper lockout
limit setpoint to 62F to test the circ pump lockout. (We reset it again to 80F after the test.) We also
observed the operation of the 3-way valve for systems 2 & 4 during system start-up.
Conclusions:
The monitored data show that one of P1 or P2 cycled on when either SF2 or SF4 started. The respective
EF2 or EF4 also cycled on at that time. P1 and P2 alternated as lead pump on every pump start. We
observed the circ. pumps to be off when the OSAT was between 57 and 65F. After resetting the upper lock-
out setpoint, the pump cycled on above 63F. The system #2 & #4 3-way valves modulated open after the
5 minute start-up delay. See attached data graphs. Operation is per the control sequence.
Capacity Control (e.g. heat pipe tilt as a function of discharge air temperature, 3-way valve modulation, heat wheel
speed, etc.):
Describe the control sequence:
The 3-way valve for each respective supply coil modulates to maintain the discharge temperature (T2-4
and T4-4) at setpoint. Backup heat (P6 and V2-4 and V4-4) operate as 2nd stage if the discharge temperature
falls 2 degrees below setpoint. Backup mechanical cooling (P7, and V2-5 and V4-5) operate as 2nd stage
cooling if the discharge temperature rises 2 degrees above setpoint.
Describe the tests that were done to verify the control sequence:
We monitored the temperatures immediately upstream and downstream of the supply side heat recovery
coils as well as the discharge temperature for SF 2 and 4. We also monitored P6 and P7 current to verify
proper staging of backup heating and cooling. Since there was no call for backup cooling during the 24 hour
monitoring period, we reset the discharge air setpoint to simulate a call for backup cooling.
Conclusions:
The data show that there was no backup heat or cooling except when we reset the discharge air temperature
5 degrees above the actual temperature, at which time P7 started and V2-5 & 4-5 modulated open. The data
show delta temperatures across the supply side heat recovery coils of between 4 and 8 degrees F. These
were adequate to maintain the discharge air temperatures at setpoint at all times. See attached graphs.
Operation is per the control sequence.
Seattle City Light Exhaust Air Heat Recovery Commissioning Procedure, page
April 1999