Assignment 2
Assignment 2
Construct an activity on arrow network based on the activity described below. Show all your
work, label activities in the network by their activity letters and node numbers. Remove any
redundant dependencies and label dummy activities.
Calculations
Start of the project (ES) Early finish activity T1 (EF)= Early finish activityR2
0 ES+d EF=ES+d
0+3=3 0+4 = 4
3+0 = 3
Early finish activity H Early finish activity D2 Early finish activity W
EF=ES+d EF=ES+d EF=ES+d
0+2 = 2 3+6 =9 3+9 =12
12+0 = 12
Early finish activity S & E1 Early finish activityP1 &T2 Early finish activity O2 & X
EF=ES+d EF=ES+d EF=ES+d
3+10 = 13 12+6 = 18 9+ 18 = 27
8+4= 12 13+3 = 16 2+ 6 = 8
2+0 = 2
Early finish activity L Early finish activity F Early finish activity P2
EF=ES+d EF=ES+d EF=ES+d
27 + 11 = 38 5+ 12 = 17 17+ 0= 17
12+7 = 19
Early finish activity Dummy Early finish activity R1, G, E
5 and 6 19 + 10 = 29
EF=ES+d 38 + 5 = 43
19 + 0= 19 7 + 19 = 26
18 + 0 = 18
Backward path
Project late finish (LF) Late start activity G Late start activity E
43 (LS)= LF - d (LS)= LF - d
43-5=38 43 -10 = 33
Late start activity R1 Late start activity F& P2 Late start activity L
(LS)= LF - d (LS)= LF - d (LS)= LF - d
43 - 7 = 36 33-5 = 28 38- 11 = 27
33 - 0 = 33 33 – 7 = 26
Late start activity X , Late start activity O2 Late start activity P1
(LS)= LF - d (LS)= LF - d (LS)= LF - d
27- 6 =21 27 - 9= 18 18- 6 = 12
15- 0 = 15 33 - 0 = 33 26- 0 = 26
Late start activity T2 Late start activity E1 Late start activity
(LS)= LF - d (LS)= LF - d D2,S,W,dummy 2
18 – 3 = 15 15 – 8 = 7 26- 6 = 20
12- 9= 3
15 - 10 = 5
7-0= 7
Late start activity T1,R2,H
(LS)= LF - d
3-3 = 0
7- 4= 3
15 – 2= 13
Float Calculations