Sewerage Project of Barmer Town

The document provides a bar chart showing the implementation schedule for a sewerage project in Barmer Town over 36 months. Key activities include tendering and contract award in months 0-2, site survey and mobilization in months 2-3, laying of sewer lines from months 3-18, construction of manholes from months 6-24, and construction of a waste stabilization pond from months 12-18. The project aims to be completed within 36 months with testing and commissioning occurring in the final months from 30-36.

Uploaded by

sombans
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
195 views1 page

Sewerage Project of Barmer Town

The document provides a bar chart showing the implementation schedule for a sewerage project in Barmer Town over 36 months. Key activities include tendering and contract award in months 0-2, site survey and mobilization in months 2-3, laying of sewer lines from months 3-18, construction of manholes from months 6-24, and construction of a waste stabilization pond from months 12-18. The project aims to be completed within 36 months with testing and commissioning occurring in the final months from 30-36.

Uploaded by

sombans
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Sewerage Project of Barmer Town

Bar Chart showing Project Implemantation Schedule

Duration in Months
S.No. Activity Start End
Month Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Tendering and award of
1 0 2
contract

Site Survey and


2 Demarcation and 2 3
mobilisation

Road cutting Earth work and


3 3 18
laying of Swer line

4 Construction of Manhole 6 24

Construction of Waste
5 12 18
Stabilisation Pond

6 Repairing of existing road 18 24

Railway line crossing of


7 6 7
Sewer pipe line

Construction of Intercepting
Chambers and Laying of
8 PVC connection pipe 18 24

Issue of sewer connection to


9 24 30
Houses

Testing and Commissioning


10 30 36