SUMMARY OF LOAD FOR DEMAND LESS THAN

100KVA(~140A)
MAP A
Application Number : PRJ-000-004-0329
A.BASIC INFORMATION
1. Address of Installation 1 - 12,LOT PT6293,JALAN BALING-GERIK,09200 BALING,KEDAH
2. Site Location(Lot & Mk Number) LOT PT6293
3. Premise Category Multi Premise
4. Type of Premise
5. Total Gross Built-in Floor Area
6. Total Land Area
7. Architect
Name JAMIL ARCHITECT
NO 21, JALAN PERDANA HEIGHTS 1/1, PERDANA HEIGHT,
Address 08000 SUNGAI PETANI, KEDAH
Telephone No
04-4218767
Fax No
E-Mail Address [email protected]
8. Surveyor
Name
Address
Telephone No
Fax No
E-Mail Address
9. Owner/Developer
Name LEMBAGA KEMAJUAN WILAYAH KEDAH (KEDA)
IC/Company No 580920-10-5723
Address 1 - 12,LOT PT6293,JALAN BALING-GERIK,09100 BALING,KEDAH
Telephone No 047205300
Fax No
E-Mail Address [email protected]
10. Consultant Engineer
Name SEJATI ENGINEERS SDN BHD
Company No 847269-V
Address NO 7,JALAN PERMATANG GEDONG,TAMAN SEJATI INDAH,08000
SUNGAI PETANI,KEDAH
Telephone No 044304778
Fax No 044304779
E-Mail Address [email protected]

Page1/2
SUMMARY OF LOAD FOR DEMAND LESS THAN
100KVA(~140A)
MAP A
11. Electrical Contractor
Name WAHI MAKMUR ENTERPRISE
Contractor No AS 0275955-M
NO 41, JALAN VISTANA INDAH 1,TAMAN VISTANA INDAH,
Address JALAN LANGGAR,06500 ALOR SETAR,KEDAH DARUL AMAN.
Telephone No
04-7876387
Fax No
E-Mail Address [email protected]
12. Requirement For Temporary Supply MD(kW): Date Supply Required:
Voltage(V):
13. Date Supply Required - ORIGINAL MD(kW):80.00 Date Supply Required:21-Jan-2018
- FINAL MD(kW): Date Supply Required:
14 PLANS-CERTIFIED BY PROFESIONAL ENGINEER
3 SETS-Please specify Plan no & date below
14a. Master Development/Layout plan Plan No : Date :
(Approve by JPB&D)

14b. Site Plan/Proposed Sub-station Sites Plan No : Date :

14c. Layout Plan of Sub-station Building Plan No : Date :


(Stand-Alone/Compartment)

14d. Layout Plan of Main Switch Rooms Plan No : Date :

14e. Single Line Diagram/Schematic of Installation Plan No : Date :

15. Front elevation of building requiring supply

NOTES:
I The Master Development/ Layout Plans (14a) are approved by Local Authority/ Jabatan Perancangan Bandar & Desa/ Jabatan Tanah &
Galian. These plans should already contain TNB preliminary comments on sub-station and right of way/wayleave requirement, as the case
may be.
II The Site Plans/ Proposed Sub-stations Sites (14b) indicate the locations of sub-station sites for the overall development area.
III The Layout Plans of sub-station building (14c) must show the cable entry locations, trencing and ducting details according to TNB
specifications.
IV Layout Plans of Main Switch-room (14d) must indicate the location of MSB, trenching/ ducting details for cable entry.
V The wiring diagrams should indicate incoming switches, metering location and devices, protection schemes and devices, bus-bar and
switchgear rating
IV All drawings and plans are to be submitted in three (3) complete sets. Soft copies in ACAD are also preferable.