Single-box-culvert-structural-Design 2 X 3 M REVISIiiii
Single-box-culvert-structural-Design 2 X 3 M REVISIiiii
Single-box-culvert-structural-Design 2 X 3 M REVISIiiii
JOB NO :
DESIGNED BY :
DATE :
CULVERT NO. :
INPUT DATA
ASSUMPTIONS
Max.coefficient of lateral
earth pressure = 0.6
Min.coefficient of lateral
earth pressure = 0.2
(BASED ON BS5400:PART 2)
MATERIAL PROPERTIES
fcu = 20 N/mm2
fy = 320 N/mm2
::
377192487.xls 1
BOX CULVERT ANALYSIS
UNFACTORED LOAD
*Note:
Dispersion of wheel load is taken as 2:1 in soil (BS5400 :pt 2)
For depth of fill 6.0m > depth > 1.8m , consider 2 axles only
ANALYSIS OF BOX
(A) CASE 1 : For max.BM and shear on wall & max. hogging
BM at corners, consider max. lateral earth
pressure acting on the wall in empty
condition.
P1 ------> ! A where
! P1, P2 = earth pressure
!
!
P2 ------> ! B
P1 = 25.16 kN/m2
P2 = 90.50 kN/m2
Joints A B
DF
FEM AD
0.42
-56.2
4.0
0.9
0.3
0.1 AB
0.58
46.6
5.6
-2.1
1.2
-0.8
0.5
-0.2
0.1 BA
0.58
-58.4
-4.1
2.8
-1.6
0.6
-0.3
0.2
-0.1 BC
0.42
65.5
-3.0
-1.2
-0.3
-0.1
-50.9 50.9 -61.0 61.0
::
(B) CASE 2 : For max.sagging moment in the top & bottom
slab, consider min.lateral earth pressure
acting on the box.
P1 = 8.39 kN/m2
P2 = 30.17 kN/m2
377192487.xls 2
DESIGN MOMENT ENVELOPE
Hogging moment at bottom corners = 61.00 kNm/m 61.00
REINFORCEMENT DESIGN
Hogging Steel at Bottom Corners :
(i) Slab
K= 0.051 < 0.156
No comp.steel required.
Z= 229.21 < 231.8
As(req)= 956.0 mm2/m
(ii) wall
K= 0.051 < 0.156
No comp.steel required.
Z= 229.21 < 231.8
As(req)= 956 mm2/m
(ii) wall
K= 0.043 < 0.156
No comp.steel required.
Z= 231.80 < 231.8
As(req)= 789 mm2/m
::
Sagging Steel at Top Slab :
K= 0.044 < 0.156
No comp.steel required.
Z= 231.36 < 231.8
As(req)= 817 mm2/m
REINFORCEMENT PROVISION
(A) SUPPORT STEEL
(I) TOP SLAB
use Y 16 spacing 150 c/c
As (req) = 789 mm2/m
As (prov) = 1340 mm2/m
(III) WALL
use Y 16 spacing 150 c/c
As (req) = 956 mm2/m
As (prov) = 1340 mm2/m
377192487.xls 3
(B) MIDSPAN STEEL
(I) TOP SLAB
use Y 12 spacing 100 c/c
As (req) = 817 mm2/m
As (prov) = 1131 mm2/m
::
(II) BOTTOM SLAB
use Y 12 spacing 100 c/c
As (req) = 922 mm2/m
As (prov) = 1131 mm2/m
(III) WALL
use Y 12 spacing 100 c/c
As (req) = 366 .
As (prov) = 1131 mm2/m
SHEAR CHECK
(i) Base
Shear = 76.06 kN
Shear stress v = 0.31 N/mm2
ps = 0.55 %
vc = 0.54 N/mm2 * Shear is OK.
(ii) Wall
Shear = 62.74 kN
Shear stress v = 0.26 N/mm2
ps = 0.55 %
vc = 0.54 N/mm2 * Shear is OK.
D 16 - 150 mm c/c
(III) WALL
(III) WALL
D 12 - 100 mm c/c
377192487.xls 4
mm4
mm4
377192487.xls 5