Voltage Stability Constrained Available Transfer Capability Calculation Using Matlab
Voltage Stability Constrained Available Transfer Capability Calculation Using Matlab
Voltage Stability Constrained Available Transfer Capability Calculation Using Matlab
ABSTRACT
The Available Transfer Capability (ATC) of a transmission system is a measure
of unutilized capability of the system at a given time and depends on a number
of factors such as the system generation dispatch, system load level, load
distribution in the network, power transfers between areas, network topology,
and the limits imposed on the transmission network due to thermal, voltage and
stability considerations. This paper describes a method for determining the
ATC between any two areas in a transmission system (multiarea) under a given
set of system operating conditions. The method used here provides ATC between
the two areas in a transmission system on the basis of voltage magnitude limits
at the buses and static voltage stability limits. In addition, the method can be
used to compute ATC between two areas based on including thermal limits
also. The proposed method is illustrated using two IEEE test systems.
Index Terms: Available Transfer Capability (ATC), Total Transfer Capability
(TTC), Tie Lines.
1. INTRODUCTION
The computation of ATC is very important in the deregulated power system
because Electric utilities would be required to post information on ATC’s of
their transmission networks so that such information will help power marketers,
sellers and buyers in planning, operation and reserving the transmission services
[1]. Utilities would have to determine adequately their ATC’s to ensure that
system reliability is maintained while serving a wide range of transmission
transactions. ATC between and within areas of the interconnected power system
and ATC for critical transmission paths between these areas would be
continuously updated and changes in scheduled power transfers between the
areas are posted.
1,2,3,4 Department of Electrical and Electronics, The National Institute of Engineering - Mysore.
E-mail: [email protected], [email protected], [email protected],
4
[email protected]
28 T. ANANTHAPADMANABHA, H. PRADEEPA, R. CHIDANANDAPPA AND…
Power system transfer capability indicates how much inter area power
transfers can be increased without compromising system security. Transfer
capability computations play a role in both the planning and operation of the
power system with regard to system security. One benefit of interconnected
power systems is the potential for increased reliability.
In an interconnected system, the loss of generation in one area can be
replaced by generation from other areas. Thus, several systems interconnected
can survive contingencies that the individual systems could not. Transfer
capability computations are useful for evaluating the ability of the interconnected
system to remain secure following generation and transmission outages.
Determining the adequacy of the transmission system in allowing external
generation to replace internal generation is a typical application for transfer
capability computations. For this purpose, a model of the network reflecting
the anticipated conditions is assumed. Several generators within one area are
selected as sinks. The power injected to the network at these locations is
systematically reduced or eliminated to reflect the planned or unplanned loss
of the units. For each generation outage scenario, several external generators
are selected as potential sources.
The choice of sources and the participation of each source depend upon
the assumption concerning the time frame of the response. The purpose of the
transfer capability computation is to determine the quantity of lost generation
that can be replaced by the potential reserves and the limiting constraints in
each circumstance. In addition to varying the assumptions regarding the
generation sources and sinks to reflect different outages and reserve locations,
the computations are often repeated assuming different loading conditions or
increasing loads and coincident branch element outages.
Transfer capability is the measure of the ability of interconnected electric
systems to reliably move or transfer power from one area to another over all
transmission lines (or paths) between those areas under specified system
conditions [3]. The units of transfer capability are in terms of electric power,
generally expressed in megawatts (MW). In this context, “area” may be an
individual electric system, power pool, control area, sub region, or NERC
Region, or a portion of any of these. Transfer capability is also directional in
nature. That is, the transfer capability from Area A to Area B is not generally
equal to the transfer capability from Area B to Area A [3].
Available Transfer Capability (ATC) is a measure of the transfer capability
remaining in the physical transmission network for further commercial activity
over and above already committed uses [3]. Total Transfer Capability (TTC) is
defined as the amount of electric power that can be transferred over the
interconnected transmission network in a reliable manner while meeting all of
a specific set of defined pre and post-contingency system conditions [3].
The system-limiting factors that limit a power system’s ATC are many.
Among them are the line current limits, voltage magnitude limit, generator
reactive power limit, and voltage collapse limit, etc.
VOLTAGE STABILITY CONSTRAINED AVAILABLE TRANSFER CAPABILITY CALCULATION… 29
The line current limit usually is a line’s thermal limit. Too much current
flow in a line may cause a line to droop or damage nearby connected
equipments. DC power flow has been widely used to calculate thermal limit
with great speed.
But DC power flow can not deal with other limiting factors. The bus voltage
magnitudes also need to be kept within reasonable limits. Voltage over-limit
may cause damage to system equipments, and reduce the power quality to the
customers. Low voltage sometimes is also an indication that the system is near
a voltage collapse. Both high voltage and low voltage are regulated by system
circuit breakers and pose limits to the power transfer.
Generators have reactive power output limits. After a limit is reached, a
generator will not be able to regulate its bus voltage. It is degraded from a PV
bus into a PQ bus. This may cause voltage collapse or system instability [6].
The voltage collapse is the upper physical limit that a power system can
function properly. Beyond this point, no mathematical solution exists. This
situation usually happens after a bus voltage has a significant drop or when a
generator’s var limit is reached.
The limitations on power system performance that we consider in this paper
are transmission voltage magnitudes and voltage collapse. All these limits can
be handled in an AC load flow power system model.
The simulation process used in this paper is illustrated using the flow chart
given below. The ATC is limited by the voltage magnitude at the buses and the
static voltage stability limit. Thermal limit checking is not accounted in this
ATC computation and is assumed to be infinity.
As the flowchart shows, a transfer case is selected first. The variables,
which are going to be used for the simulation, are chosen. For example, after
identifying the tie lines connecting the two areas, the power of the generator of
an area and the load of another area is increased so that power is transferred
from an area to another. The branch flow of the line or lines connecting the
two areas will then be recorded. If the power flow solution of the transfer case
cannot be converged, the simulation will be stopped, go back a few steps, and
continue running again with smaller steps, just to increase the accuracy of the
simulation. The reason for running the simulation in a bigger step comparing
to the second stage is to reduce the time consumption. The ATC is then the
total power flow increased between the two areas before the system plunge
into instability.
For a given system state, the ATC from one area (Area 1) to another area
(Area 2) and ATC’s for selected transmission paths between them will be
calculated using following procedure:
1. Establish a base case power flow using AC power flow in which the
system load is supplied without violating any transmission limits.
2. Identify the tie lines between the two areas.
3. Obtain from the base case, power flows in these selected tie lines or
transmission paths between the two areas.
4. Check for presence of loads at the receiving ends of these tie lines.
5. If so, increase the load in larger steps.
6. Again obtain the power flows in these tie lines between the two areas by
running AC power flow.
7. Repeat step 5 until system conditions are violated.
8. Now go back one step and decrease the load by one step.
9. Now by increasing the load in smaller steps run the power flow until
system conditions are violated and obtain the power flows in tie lines.
10. The difference between the flows computed in steps 9 and 3 on a
particular transmission path or tie line would give the required ATC for
that path or tie line.
11. The sum of ATC’s computed for tie lines between two areas will give the
ATC between those two areas.
32 T. ANANTHAPADMANABHA, H. PRADEEPA, R. CHIDANANDAPPA AND…
Check if Bus
Yes
voltages are stable
No
Step back and increase
variables in smaller steps
No
ATC
End
Fig. 1: Flow Chart for The Simulation
Fig. 1: Flow chart for the simulation
The above procedure can he used to compute ATC’s of multiple-area
systems as a function of time. Hourly or daily ATC’s can be calculated as the
power system goes through its moment by moment changes.
Table I
23 18 19 4.33
24 19 20 4.30
25 10 20 7.87
26 10 17 8.04
27 10 21 2.23
28 10 22 3.46
29 21 22 2.20
30 15 23 2.23
31 22 24 3.46
32 23 24 2.20
33 24 25 –6.59
34 25 26 0.00
35 25 27 –6.78
36 28 27 6.86
37 27 29 0.00
38 27 30 0.00
39 29 30 0.00
40 8 28 1.38
41 6 28 5.48
Table II
Area No. to Area No. ATC (MW)
1 2 23.15
1 3 38.52
2 3 –13.71
Table III
Area No. to Area No. ATC (MW)
1 2 19.09
1 3 –21.97
2 3 –345.29
5. CONCLUSION
In this paper a simple, efficient and practical method for determining the ATC
between any two areas in the transmission system has been proposed and the
ATC’s for transmission paths between two buses and ATC’s between two areas
interconnected by tie lines are calculated. The results obtained from the
application of the above method of ATC assessment to the two IEEE test systems
demonstrated that ATC was limited mainly due to the violation of voltage
magnitudes at the buses.
REFERENCES
[1] G. Hamoud, “Assessment of Available Transfer Capability of Transmission Systems”, IEEE
Transactions on Power System, 15, No. 1, February 2000.
[2] Ian Dobson, Hans Glavitsch, Chen-Ching Liu, Uasio Tamura and Khoi Vu, “Voltage Collapse in
Power Systems”, 8755-3996/92 1992 IEEE.
[3] North American Electric Reliability Council, “Available Transfer Capability Definitions and
Determination”, NERC June 1996.
VOLTAGE STABILITY CONSTRAINED AVAILABLE TRANSFER CAPABILITY CALCULATION… 37
[4] G.C. Ejebe, J. Tong, J.G. Waight, J.G. Frame, X. Wang, W.F. Tinney, “Available Transfer
Capability Calculations”, IEEE Transactions on Power Systems, 13, No. 4, November 1998.
[5] Dr. Nigel T. Hawkins, “Voltage Collapse and its Avoidance”, IEE, Savoy Place, London WC2R
0BL, UK.
[6] Ronghai Wang, Robert H. Lasseter, Jiangping Meng, Fernando L. Alvarado, “Fast Determination
of Simultaneous Available Transfer Capability (ATC)”.
[7] P. Kundur, Power System Stability and Control, McGrawHil, 1994.
[8] Arthit Sode-Yome and N. Mithulananthan, “Static Voltage Stability Study Using MATLAB
Symbolic and Optimization Toolboxes”.
[9] Ian Dobson, Scott Greene, Rajesh Rajaraman, Christopher L. DeMarco, Fernando L. Alvarado,
Mevludin Glavic, Jianfeng Zhang, Ray Zimmerman, “Electric Power Tansfer Capability: Concepts,
Applications, Sensitivity and Uncertainty,” PSERC Publication 01-34 November 2001.
[10] www.ee.washington.edu/research/pstca.
[11] www.pserc.cornell.edu/matpower.