Flowchart of NCR Via Aconex

The NCR flowchart outlines the process for issuing and resolving nonconformance reports (NCRs) between a quality control engineer (QCE) and contractor. It involves 5 parts: 1) the QCE issues the NCR describing the defect and cause, 2) the contractor proposes a remedy, 3) the QCE accepts or rejects the proposal, 4) the contractor completes the work, and 5) the QCE verifies the issue is resolved before closing out the NCR. Each part has a designated duration for completion.

Uploaded by

Cristian Giurgea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Flowchart of NCR Via Aconex

The NCR flowchart outlines the process for issuing and resolving nonconformance reports (NCRs) between a quality control engineer (QCE) and contractor. It involves 5 parts: 1) the QCE issues the NCR describing the defect and cause, 2) the contractor proposes a remedy, 3) the QCE accepts or rejects the proposal, 4) the contractor completes the work, and 5) the QCE verifies the issue is resolved before closing out the NCR. Each part has a designated duration for completion.

Uploaded by

Cristian Giurgea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

NCR FLOWCHART

QCE NCR issuance


CONTRACTOR
PART A: Details Of Nonconformance:

ACONEX PART B: Proposed Remedial


QCE Classify defects (Critical, Major, Minor, Corrective Action :
Unknown) and the Cause of
Nonconformance (Material, Process, Contractor submit a Remedy Plan.
Workmanship, Documentation) with the
associated reference specifications Duration= 3 days

QCE
Part C: Engineers Acceptance of Contractors
Proposals In Part B:

Contractor's proposals are unacceptable for the ACONEX


following reasons. (Contractor should revise &
resubmit):

Contractors proposals are acceptable and remedial


work may proceed. ACONEX

Duration =1 Day

CONTRACTOR
ACONEX PART D: Remedial Works, Corrective
action proposed In Part B are complete
& ready for Inspection :

Duration= 7 days
QCE
PART E: FOLLOW UP & CLOSE-OUT:

Remedial Works / Corrective Action undertaken by the


Contractor are not acceptable for the following reasons
and this NCR may not be closed out. (Contractor must ACONEX
address these issues)

Remedial Works/Corrective Action have been


undertaken and are acceptable. This NCR may be closed ACONEX
out.
Duration =2 Days

ACONEX

SUPERCONSULTANT
COMPLIANCE CHECK
Duration =1 day