Plumbing Design Cource
Plumbing Design Cource
Plumbing Design Cource
Said Elshayeb
[email protected]
P a g e |1
The purpose of plumbing design system, is to provide clean water supply with a suitable capacity &pressure to
water fixtures and to drain the result outside the building safely without affecting health.
1. Sources of Water.
2. Estimation of Water Demand for a Certain Project.
3. Water Supply Network Component.
The water network of a building/project is being supplied by using one or more of the following sources:
Water filters maybe used before filling tanks, if the municipal water network is contaminated.(or at
Hospitals)
Water demand (Capacity and storage duration) for a project should be well estimated to ensure a
continuous supply of water whenever needed by project occupants or equipment.
The water demands varies from one project to another, also storage duration varies according to project
location and municipal water supply conditions :( 1day storage for a residential building – 2 days for
hospitals etc.)
Amount of stored water should be well estimated to avoid:
To estimate the required water capacity the following factors should be known:
1. Number of project occupants and equipment.
2. Required water demand for occupants according to the application.
3. Water Storage Duration.
The water demand depends basically on the number of project occupants and equipment need to be supplied with
water (if required) such data should be known from one of the following sources:
Estimation of water supply requirements for a hotel building (5 Stars) consists of 150 room
Solution
Number of rooms=150
Required water capacity per room=1500 lpd (liter per day including all services and staff).
OPTION (1):
OPTION (2):
Install an underground tank of 2 compartments each of 200m 3 and a roof top tanks of the remaining
50m3.
Main Network:
Water supply network is being buried at a safe underground level surrounded by clean sand layers to
avoid mechanical loads.
A 15 cm clean sand bedding should be prepared below water pipe, and a minimum of 30 cm bedding
above water pipe should also be prepared.
The water supply network should be routed around the outer area of the project to supply each water
branch line.
Water supply network should be routed away from any electrical rooms or hazardous spaces.
If the water supply and drainage pipes are intersected, water supply pipes should be 30 cm above
drainage pipes.
Water supply pipes should be 2 meters away from drainage pipes.
There are two ways for connecting polypropylene/High Density Polyethylene pipes:
Welding
Socket Welding.
Butt Welding.
Saddle Welding.
Threaded Connectors
Valves are used for water supply network to separate it for ease of maintenance.
Valves should be made of (copper- stainless steel- plastic – bronze) and should be coated by nickel-
chrome.
Valves should be installed at water network through a dismantling joint (Erection Joint).
Types of used valves:
Sectional Valves& valve pit/ house connection.
Air valve.
Drain Valve.
Pressure reducing valve.
Sectional valves/house connection should be installed at each branch line of the water supply network to
separate this branch when needed for maintenance.
Valves should be installed inside an accessible valve pit.
Most common sectional valves are Gate Valves- Butterfly Valves(light weight-less volume).
Sectional valves are installed for:
Each building.
Between water meter gauge.
Each home water inlet.
Each riser and branch.
Used to release the air from water supply network during the filling of network.
Drain valves are installed to drain the network whenever needed for maintenance or any other reason.
Used to decrease the pressure to operate the lines and fixtures below maximum pressure.
Should be installed inside a valve pit.
Maximum operating pressure for plumbing fixtures is 4 Bar.