Electric Primary Metering: 1.0 Index
Electric Primary Metering: 1.0 Index
Electric Primary Metering: 1.0 Index
2.0 PURPOSE
This standard provides information on the construction of metering for customers who receive primary
voltages (2.4kV to 24.9kV).
6.2 Two types of primary metering enclosures are approved: 1) Preassembled High Voltage
switchboard Metering and 2) Vault-mounted Metal Enclosures. The vault to mount the enclosure
will be provided by the customer. Refer to NVE's Volume 5, section PPM for details. For the
switchboard type metering, the potential transformer disconnect shall be of the gang-operated type
operated by a swing handle. This enclosure must meet the latest version of the "Electric Utility
Service Equipment Requirements Committee" (EUSERC) requirements. The metering
components, PTs, CTs, etc. will be furnished by NVE.
6.3 Wireways in the high voltage switchboard service termination space designed for terminating the
utility service shall be clearly identified for such use. Utility terminations are dead front universal
bushing wells, and no live front bolted terminations will be accepted. Service termination shall be
made in the service termination enclosure or in a specially designated space of the meter panel
which has a separate removable and sealable access plate.
The layout or design of the service termination enclosure, which requires bending the utility
service conductors, should provide space to permit a minimum cable bending radius equal to 10-12
times the overall outside diameter of the cable. The following table is a list of conductors found in
NVE distribution system and their associated minimum bending radius:
6.4 Knockouts in cable wireways should be positioned to minimize service cable bending.
6.5 The service termination enclosure, socket enclosure, and test by-pass block section shall be
sealable and isolated or have barriers provided from other integral enclosure sections which are
accessible to the customer in order to effectively prevent the attachment of unauthorized connections to
unmetered conductors or terminals.
6.6 The manufacturer's rating label, or other markings used in lieu of a label, shall show among other
things:
A) Whether the socket and socket enclosure is designed for overhead service entry, underground
service entry, or both;
B) That the terminating lugs are designed for both aluminum and copper conductors; and
C) The wire size range of the termination lugs.
For each primary metering installation, two sets of drawings must be submitted to NVE: Electric
Metering Department, P.O. Box 10100 (R90EM), Reno, NV 89520. These drawings must detail the
interface between NVE and the Customer. The lead time to obtain the necessary hardware has been
up to 8-10 weeks; therefore, the drawings should be submitted in advance of construction by 10 weeks
minimum. This will assure that the proper metering equipment is available upon construction.
8.0 REFERENCES
EUSERC: Electric Utility Service Equipment Requirements Committee Specifications.
NEC 110-33: Entrance and Access to Work Space
NEC Article 490, Systems over 600 Volts.
NVE: Specification UCD01X, "Cross-Linked Polyethylene Primary Cable", Volume 21.
NVE: Section PPM, Volume 5.