PLDT GROUP NETWORK BUILD
FIXED NETWORK BUILD ACCESS ACCEPTANCE CHEC
ACCEPTANCE CHECKLIST Report
To be filled up, mark x at category, network
elements and activities Date : ______
SWBS Installation of
Project Description
(Specifics OF Network Element) at _(Site Location/Address, Town, Province, Zone
Contract Details Cross Functional Team
Start PM
Completion Zone
Contract Completion Operation/FxATOp
Contract Cost Contractor
Scope of Work Activities
1 General requirement
RTA requirement: approved applied
provide "√ " mark JPA requirement: approved applied
applicable and "X" MECO COOP
1.1 Permits mark if not applicable
inside the box...
DPWH CEO HOA BRGY
DOH MAYORS GOVERNOR
Instrusion to private property
2 OLT Equipment (Optical Line Terminal)
Homing OLT
2.1 OLT Cards
Cards installed
Type of cards
Number of cards
SFP installed
2.2 SFP Type of SFP installed
No. of SFP installed
Existing ODF
80% utilized Yes No
2.3 OLT ODF requirements Provisioning of New ODF
ODF properly mounted
ODF properly mounted/labelled
Type of patch cord Simplex Duplex
LC-LC SC-LC FC-LC FC-SC FC- SC
No. of patchcord
Patchcord Installation
2.4 OLT Patchcords requirements
Patchcord labelling
Tie cable 80% utilized
2.5 Tie cable requirements
New tie cable requirement
3 ODN INSTALLATION
Maintenance loop
Enclosure: Aerial Underground
3.1 Feeder / Sub-feeder requirements
FOC Span: Regular Short Long
Creosoted pole : 25 ft 30 ft 35 ft
3.2 Poles
Concrete pole : 25 ft 30 ft 35 ft
Pole Clamp: Type: CA TCA DEG
Guy Grip
Guying: Head guy Pole-to-pole side guy
3.3 Guying and Pole Dressing
Side guy Sidewalk guy Pole-to-pole guy
Anchorage: Log Concrete
Extension arms 10 pin 26 pin 44 pin
Pull-off installation
Aerial Support on-pole
Cross over
Riser cable guards
Grounding wire
3.4 Grounding
Grounding Rod
4 ODN Materials
LCP : Fiberhome Sunsea Fibercom
TYCO Fujikura
LCP installation: 18 feet above below
No. of LCP Splitter: 1:8 1:16
Inside LCP Box
4.1 LCP (Local Covergence Point)
LCP Stencilling
Future or Expansion LCP
Power budget LCP (1:8) to OLT
NAP : Fiberhome Sunsea Fibercom
TYCO Fujikura
NAP installation: 18 feet above below
No. of NAP Splitter: 1:8 1:16
Inside NAP Box
NAP Stencilling
Hook with Nut on pole with NAP
4.2 NAP (Network Access Point)
Bridle ring
Figure 8 FOC Routing at NAP
Future or Expansion NAP
Power budget NAP (1:8) to OLT
5 Fiber Optic Cable (FOC)
Figure 8 - 24 Fiber 48 Fiber 72 Fiber
5.1 Fiber Optic Cable (FOC) type Traditional - 24 Fiber 48 Fiber 72 Fiber
Jacketed Fiber Optic Cable
Armoured Fiber Optic Cable
5.2 FOC protection (Touched to Electrical Figure 8 - 24 Fiber 48 Fiber 72 Fiber
power cable)
Traditional FOC
5.3 FOC typical installation
Figure 8 FOC
6 Testing and Pre-test
Is personnel who will do the test/pre-test is skilled/
experienced and has a proper tools , equipments and
materials
Power meter available
OTDR available
Splicing machine available
Fluke/ Grounding tester
Pre Testing prior to acceptance
Pre Testing/Actual testing during
6.1 Acceptance
Test protocol available
Plan on site
Boom truck/ Vehicle with basket
service vehicle available
extension ladder available
use of 99% alcohol/kimwipes tissue during splicing
Is core assignment correct
Necessary Tools/special tools available
7 Safety Practices
is personnel has proper tools, equipments and
materials
is personnel safety conscious
proper uniform
use of cone & signages
7.1 Safety Practices vehicle use with signages
uses of hard hat, gloves and safety shoes
uses of body belt and strap
personnel who manage traffics
proper lighting (evening works)
proper ladder
8 House keeping
Recovery of equipment migrated to new equipment
installed
Recovery of equipment (legacy) which are already not
used and already power-off status and still installed at
cabinet/rack
Recovery of equipment (legacy) which are already not
used and already power-off status and dismantled
8.1 Equipment
Recovery of power and equipment cables of the
migrated equipment that will not re-used
Recovery of power and equipment cables of the
equipment (legacy)that are already power-off and will
not re-used
Recovery of power and equipment cables of the
equipment (legacy) that are already dismantled and
will not re-used
Disposal/Recovery of patchcord of the replaced
8.2 Patchcord ,migrated, dismantled, powered-off equipment
Disposal/Recovery of excess patchcord
Disposal/Recovery of excess power cable
Disposal/Recovery excess equipment cable
8.3 Cables
Disposal/Recovery excess FOC cable
Disposal of excess grounding cables
Disposal of excess bolts, screw, bars, plates woods,
etc.
8.4 Excess Materials
Disposal of equipments boxes, frame, papers, plastic,
foam, rags, cables peel, dust, etc.
Vacuum cleaner
Broom and dustfan
9.5 Equipments needed
Clean Cloth
5 S (site must be clean before and after)
OTHERS/COMMENTS:
additionals queries, comments, agreement, action needed etc. to accomplished PLDT
Quality/Technical standard requirements of the project ..
Attested by: (PM) Attested by: (ZONE) Attested by: (FxATOp)
Should be signed by all atttendees present during acceptance... If personnel concern is not present during Acceptance activities, in
personnel/ Division on the actual day of the Acceptance(by Phone) and continued the Acceptance activities. (Sample: Advice: Na
Name Name Name
Date Date Date
NETWORK BUILD
CCESS ACCEPTANCE CHECKLIST
ACCEPTANCE CHECKLIST Report
Date : ______
Category
In Building
IPCore
Solution
Backbone CusNet
X Access Outside plant
te Location/Address, Town, Province, Zone NPIP Support
onal Team Network Elements
AG IPBB/Core
OLT BRAS/Brains/N4I
AS X FTTH
CEN X FOC/FITL/Feeder
PLDT Quality &Technical Standard Complied Remarks
YES NO
specify your queries, deficiencies,
agreement, action needed etc..on
the said activities during accetance
RTA/JPA and permits requirement should be secured to accomplished PLDT
by PLDT/Contractor before any implementation will Quality/Technical standard
start requirements ..
provide "√ " mark if YES and "X" mark
if NO, complied with PLDT Technical
standard... NA if not applicable
YES NO
FTTH homing port should me requested thru
NFCSM Division. Issued PON Port assignment should
be strictly followed… No changing of issued PON
port assignment is allowed without prior approval
by NFCSM.
Cards properly inserted. No. of cards should be
properly audited/ turn-over to the End-user/ Owner
Proper SFP should be used/inserted based on the
requirements (short haul/long haul)… No. of SFP
should be properly audited/ turn-over to the End-
user/ Owner
Utilization of existing ODF or location of new ODF
should be with approval via WARPP ESR. Properly
mounted and labelled- white Font. Calibri 24 (ODF
NAME/TAG)
Type of patchcord to be used are based on the
requirements. 5 mm- yellow simplex.TYPE
Patchcord installed shall be in exact length or on the
available nearest standard length. Connector is not
allowable if patching is within same room. For
FTTH projects, Patching of patchcord will be done by
FxCTOp. Correct patchcord requirements will be
provided by PM.
Patchcord properly labelled. Brother: Color : white, 8
inches from connector; Font size Calibri 11.. Label
should be stated the "from" (where it from (CSZ) ,
what equipment/ODF; port assignment and "To"
(where it To (CSZ) , what equipment/ODF; port
assignment or OLT SITE NAME
Existing tie cable should not be more than 80%
utilization. New tie cable will be provided if attained.
PM SHALL ENDORSE TO BIBOT OFINA
YES NO
For feeder, provide 30 m maintenance loop to place
at the riser pole or 1st manhole. For Sub-feeder,
30m maintenance loop will be place before the splice
enclosure. No maintenance loops on succeeding
LCP's and NAP's. Maintenance loops should be
placed on PLDT pole only, never on Meralco poles.
Used proper loop holder to properly secure the
maintenance loop.
Use proper enclosure. For aerial & UG FOC, use
dome or butt type. For all FTTH construction,
install splice enclosure before 1st LCP. It should be
located at main road or outside (before entry) the
subdivision or village.
Regular FOC span - 50 meters pole-to-pole
Short FOC span - > 50 meters pole-to-pole
Long FOC span - < 50 meters pole-to-pole.
For Long span, if sagging is probable, maximum
sag - 2 feet. Catenary construction is advisable
(should be lashed) or may required additional pole.
For Provinces, the typical height of sag from Ground
Level to the midspan is 15’ (for along the road),
while for road crossing is at 18’ . Implement S
method for road crossing
Poles to be used is dependent to the availability and
soil condition. It should have pole tag(aluminum) or
incripted with PLDT and date/number. Depth of
excavation: 1.2 meter NGL if soil is rocky and and 1.5
to 1.8 meters NGL if ordinary. Clear excavation site
of surplus soil/materials and restore affected
pavement to original condition.
Pole clamp height:
22/20 feet height across the road >
22 ft height upto 18m height along the road
Use proper guy grip base on FOC cable used. It
should be preformed and with guy grip spacer. Used
yellow cable tie to add support to the FOC cable on
the guy grip. Once cable tie is secured, remove or cut
any excess. For Figure 8 24F/48F/72F (with 1.2mm
wire strand messenger) – use 1/7” Guy Grip
For Figure 8 144F/216F (with 1.6mm wire strand
messenger) – use 3/16” Guy Grip
Proper guying with correct pole clamp, guy wire
with complete accessories (insulator strain,
protector guy wire) will be used for every site
condition. Head guy - CA 2A Pole-to-pole - CA 2A
Side guy - GCA 1B Sidewalk guy - GCA 1B Pole-to-
pole Side guy - com CA 2A & GCA 1B
Use 6 feet anchor rod for side walk guy installation.
Clean excavation site of surplus soil and materials
and restore affected pavement to original condition.
Proper material will be used based on site condition
and location of pole
Pipe : GI ( 4" x 10') Strap : Stainless 3/4" wide GA
22 Metal U Gard : 4 3/16" x 8' Base : Concreted
Messenger wire No. 6 (5/16"). Should be properly
strapped to pole using metal strap stainless 3/4 "
wide 22GA, with PVC moulding (1"x1" x 8') and
surely bonded to FOC messenger wire and ground
rod using proper clamp. Complete grounding should
be provide every LCP and end of aerial NAP.. DO NOT
strip or take away cable sheath... Excess grounding
wire should be cut.
Grounding Rod: 1/2" x 8'. Should be properly
implaced in ground… Grounding should not be
greater than 25 ohms. Additional grouding rod is
required if grounding is still 25 ohms.
YES NO
LCP should be pre and approved by TechStand
LCP 's pole mount closure position should be fixed
facing the main road. It will be installed 1' - 2'
below center bolt of C1 pole clamp (22/20 feet or
18 feet). But not less than 12 feet. LCP should not be
installed at pole with power transformer.
LCP should be fused-in/ fused-out (modular). In-put
and out-put of the splitter will be fused to the fiber
core
With shrinkable sleeve/ protection tube / fix
with cable tie / spiral tube protection?
LCP Stencilling naming convention should be:
MUNICIPAL CODE - MKT LCP
Number Sample - LP3 NO SPACE
Provide 5m -7M loop at the identified locations
where they will be installed. Expansion loop should
be placed on the side of the future LCP facing the
central office.
SC Patchcord Connector : 0.30 db
Field installable connector : 0.5 db
Fusion splice : 0.03 db
LCP (1:8) : 10.5 db Power
budget limit (OLT to LCP) : 105 DBm Power
budget limit (OLT to ONU) : 28 DBm
NAP should be pre-approved / approved by
TechStand
NAP should be pre-approved / approved by
TechStand
NAP 's pole mount closure position should be fixed
facing the main road. It will be installed 1' - 2'
below center bolt of C1 pole clamp, but not less than
12 feet. NAP should not be installed at pole with
power transformer.
NAP should be:
In-put side - Fused
Out-put side - Connectorized
With shrinkable sleeve/ protection tube / fix
with cable tie / spiral tube protection?
NAP Stencilling naming convention should be:
MUNICIPAL CODE Sample - MKT
LCP Number Sample - LP3
NAP Number Sample homing - NP8 no space left
alligned
Install hooks with nut together with pole clamps on
every pole where NAP is installed
Install two (2) hooks, one (1) facing left and the
other facing the right side of the street
For end poles with NAP, meaning poles installed at
dead-ends or road-ends
Install only one (1) hook and should be installed
facing the open section of the street
5 pcs Bridle ring are required at NAP only. 2 bridle
ring at both side of NAP and 1 at the bottom 5" to 6
" directly under the drop cable ports. Bridle ring are
dedicated for drop cable use only
Route the 24F Fig. 8 FOC opposite the drop cable
ports side of the NAP going to the main cable ports.
"Do Not" route the cable on the same side where the
drop cables are so as not to disturb the drops
Provide 5m - 7m loop at the identified locations
where they will be installed. Expansion loop should
be placed on the side of the future NAP facing the
central office.
SC Patchcord Connector : 0.30 db
Field installable connector : 0.5 db
Fusion splice : 0.03 db
LCP (1:8) : 10 db Power
budget limit (OLT to NAP) : - 22 DBm Power
budget limit (OLT to ONU) : -28 DBm
YES NO
If insertion point is aerial, use figure 8 FOC. If
underground, use traditional (round lashed) FOC…
For ODN distribution, use Fig. 8 ( 8 core, 3
buffer)FOC. For Sub Feeder requirement: use Fig. 8
fiber. For Feeder requirements: use Traditional
fiber
Fiber Optic Cables that were used before in Direct
Buried Applications.
Fiber Optic Cables that are used primarily in many
applications
Wrap the 24F Figure 8 FOC with a ½ HDPE pipe, to
protect and insulate it from electrical contacts
Length of HDPE pipe should be 16”
Secure both ends of the HDPE pipe with electrical
tape
Install the messenger wire to the pole clamp. Lay-
out the traditional FOC to the messenger wire. Lash
the traditional FOC to the messenger wire using the
lashing machine with spinner wire. Install the
grounding system. Install loop holder if needed.
Provide PLDT standard tie wire 2 for every 10
meters.
Install the Fig 8 FOC to the pole clamp. Install the
grounding system. Install loop holder if needed.
Provide PLDT standard tie wire 2 for every 10
meters.
YES NO
Equipment/testing apparatus to be used should be
calibrated with complete accessories. Person who w
ill used the said equipment should be skilled and
experienced..
must available if needed
must available if needed
must available if needed
must available if needed
Pre test should be conducted by Contractor prior to
acceptance. Pre testing result should be submitted to
PM or available during Acceptance . No acceptance
will be conducted without pre testing
Test protocol of every equipment should be available
(triple copy) before any testing/Pre test is
conducted. No testing will be done without TPF.
always available if needed
must available if needed
always available if needed
must available if needed
must available if needed
always validated correct
must available if needed
YES NO
must available
personnel must be safety conscious
must available
must available
must available
must available
must available
must available
must available
must available
YES NO
Legacy equipment migrated to new equipment will
be removed by Contractor. This will be itemized by
PM (picture possible) and turn-over to MigSupp
Division for uploading to WARPP and proper
disposition
Legacy equipment already power-off status but still
installed at cabinet/rack and which are already
dismantled will be reported by PM to equipment
owner/end-user for proper disposition
Power and equipment cables of legacy equipment
migrated to new equipment will be removed by
Contractor. This will be itemized by PM (picture
possible) and turn-over to MigSupp Division for
uploading to WARPP and proper disposition
Power and equipment cables Legacy equipment
already power-off status but still installed at
cabinet/rack and which are already dismantled will
be reported by PM to equipment owner/end-user for
proper disposition
Disposal/Recovery of all replaced patchcord,
dismantled power and equipments cables including
the excess cables, metal, plastic, paper materials,
foam, rags, cables peel, dust etc.. will be done by
Contractor. Project area/sites must be clean, free
from foreign object before and after
implementation/ works.
must available if needed
must available if needed
must available if needed
must know the 5 S program of PLDT
needed etc. to accomplished PLDT
oject ..
xATOp) Attested by: (Contractor) Attested by: (Others)
ncern is not present during Acceptance activities, indicate that PM already informed/advised the said
ued the Acceptance activities. (Sample: Advice: Name of Personnel - Date)
e Name Name
e Date Date