10 Loss of Mains Protection
10 Loss of Mains Protection
10 Loss of Mains Protection
Loss-Of-Mains – LOM
Interconnected Psys
If LOM is not detected, then system
Qsys
the generator could remain Pload
connected, causing a safety Qload
hazard within the network.
G
Pgen
Qgen
Generator
network
Loss-Of-Mains – LOM
OPEN
System can become unearthed
Utility network
Interconnected 30
generation
system
profile
feeder Pload 20
Qload
~ } non-detection zone
10
LOM
feeder Pload
Qload
~
LOM
G
Pgen
Qgen
Generator performance during islanding
dr
H=2s
H=4s
Tm Te
deviation from synchronous speed [rad/s]
4
J
3
dt
2
where:
J – inertia constant [kg m2]
r – rotor speed [rad/s]
1
Tm – mechanical torque [N m]
0
0 0.5 1 t 1.5 2 2.5 Te – electromagnetic torque [N m]
-1
time [s]
1
Jr20
kinetic energy at synchronous speed 2 H – inertia constant [s]
H
machine nominal power Sn
Generator performance during islanding
f
Taking into account that r 2 f r and fr initial rate of change
p
of frequency during islanding can be calculated as follows:
1
dr Jr20
T 2 H Sn
(1) J (2) H2 J
dt Sn r20
2 H S n dr 2 H S n df r 2 H S n 2 df
2 T
(3)
r 0
2
dt r 0
2
dt 2 f p dt
r0
p
2 H S n df 2 H S n df
(4) Tr 0 P
f dt f dt
df P f
dt 2 S n H
Generator performance during islanding
Exiter Islanded
Exiter system
2 5
Generator with Governor H=2s
Generator without Governor H=4s
deviation from synchronous speed [rad/s]
3
1
0.5
1
0
0
0 0.5 1 1.5 2 2.5
0 0.5 1 1.5 2 2.5
-0.5 -1
time [s] time [s]
LOM detection methods
Rate-Of-Change-Of-Frequency (ROCOF)
Direct Intertrip
Active methods
Rate-Of-Change-Of-Frequency (ROCOF) Method
The ROCOF method is based on the local measurement of the
generator voltage and estimation of the rate of change of frequency.
Interconnected
Power System
Loss of grid connection
~
Operation
50.05
50
trip
frequency [Hz]
49.95
Load
49.9
DG
ROCOF
49.85
f
Relay
49.8
f t
ROCOF 49.75
t 49.7
0 0.5 1 1.5 2 2.5 3
time [s]
ROCOF stability
Assume typical ROCOF setting of 0.125Hz/s
Interconnected
Power System
System fault
~
Fault clearance
False ROCOF
50.1
Operation
50.05
50
trip
frequency [Hz]
Load 49.95
DG 49.9
ROCOF
Relay 49.85 f
49.8
f
ROCOF 49.75
t
t 49.7
0 0.5 1 1.5 2 2.5 3
time [s]
ROCOF – summary
LOM
G
Pgen
Solution
Qgen
Voltage Vector Shift (VS) LOM Method
The relay measures voltage phase changes in consecutive
cycles (or half cycles) and compares the value with the preset
threshold.
R IL2 R
IL1
Ed2 VT2
Ed1 Ed1’ Ed1” VT1 Ed2’ Ed2”
Connected Islanded
"
” d1
d”
d1 = E
E
IL1 X
"
E d2
”
Xd
IL2
VT1
j2 IL2
j1 VT2 R
IL1 R
IL1 IL2
Voltage Vector Shift (VS) LOM Method
Ed2 VT2
Ed1 Ed1’ Ed1” VT1 Ed2’ Ed2”
Connected Islanded
"
” d1
d”
d1 = E
E
IL1 X
"
E d2
”
Xd
IL2
VT1
j2 IL2
j1 VT2 R
IL1 R
IL1 IL2
Example
Vector Shift is used to protect an Embedded Generator. Calculate the
voltage angle change if the generator output increased from 15MW to
25MW as a result of an LOM event. Before islanding the generator
operated at unity power factor pf1=1 and after loss of grid connection
power factor changed to pf2=0.85 (lagging load). Assume that at the
time of islanding the generator terminal voltage was VT1 = 1/0°pu.
Generator: Sn = 30 MVA Vn = 33 kV
Xd” = 0.23 pu Ra = 0.05 pu
Xd
Xd’
X d”
IL R
Ed E d’ E d” VT
Solution
Reverse VAR LOM Method
Reverse VAR relay measures the generator reactive power
flow Qgen and operates when it exceeds a fixed threshold.
LOM LOM
G G
Pgen Pgen
Qgen»0
Connected Qgen Islanded
Reverse VAR LOM Method
The amount of reactive power from the generator Qgen may become
insufficient to activate the relay if the total capacitance of the
connecting cables is high delivering reactive power to the loads.
Interconnected Psys=0
system
LOM Qc
G Qc
Pgen Qc
Qgen
Reverse VAR LOM Method
Intertrip
G
Direct Intertripping
Intertripping must be transmitted from every point of
disconnection where the viable island could be formed.
Cost of intertripping is comparatively high (£15k-£100k).
Communication media has to be reliable. Commonly used
techniques include: leased land line, radio (10km), microwave
(20km), PLC (100km), fibre optic cable (20-50km), copper
cable (10km).
Intertrip
G
Direct Intertripping
Intertripping must be transmitted from every point of
disconnection where the viable island could be formed.
Cost of intertripping is comparatively high (£15k-£100k).
Communication media has to be reliable. Commonly used
techniques include: leased land line, radio (10km), microwave
(20km), PLC (100km), fibre optic cable (20-50km), copper
cable (10km).
Intertrip
G
Direct Intertripping
Intertripping must be transmitted from every point of
disconnection where the viable island could be formed.
Cost of intertripping is comparatively high (£15k-£100k).
Communication media has to be reliable. Commonly used
techniques include: leased land line, radio (10km), microwave
(20km), PLC (100km), fibre optic cable (20-50km), copper
cable (10km).
Intertrip
G
Intertripping of Open Ring Feeders
Signal send
Signal block
G G
Signal receive Open point
Signal receive
Signal block
Signal send
G
Signal receive
Intertripping of Open Ring Feeders
Signal send
Signal block
G G
Signal receive Open point Signal receive
Signal block
Signal send
G
Signal receive
Satellite based LOM protection
Transmission
The LOM protection algorithm System
uses the difference between
the received signal and the ~
locally measured frequency to
estimate the voltage angle trip
n – calculated angle
fn – frequency measured locally
fnref – reference frequency received from the satellite
t – angle calculation time step
ffnnrefest
f
fn-30 fn-25
fn
t time
The method is less sensitive to system faults while preserving
good sensitivity to genuine LOM events