MUNICIPALITIES AND AGRICULTUYRE
DEPARTMENT
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
(STRUCTURAL SECTION)
SUBMITTAL CHECK LIST
(STRUCTURAL)
March 2007
Abu Dhabi Municipality
BUILDING PERMITS DIRECTORATE
STRUCTURAL SECTION
SUBMISSION CHECK LIST
PROJECT INFORMATION:
PROJECT ……………………………………………………………………
NAME:
……………………………………………………………………
……………………………………………………………………
OWNER : ……………………………………………………………………
CONSULTANT : ……………………………………………………………………
COTRACTOR : ……………………………………………………………………
PROJECT LOCATION : Area : ………………...……………………………
Sector : ………………...……………………………
Plot : ………………...……………………………
SUBMISSIONS :
ENABLING WORK
FOUNDATION / SUBSTRUCTURE
SUPER STRUCTURE
DATE : ……………………………………………………………………
SIGNATURE : ……………………………………………………………………
Abu Dhabi Municipality March 2007
Page 2 of 6
BUILDING PERMITS DIRECTORATE
STRUCTURAL SECTION
SUBMISSION CHECK LIST
A) ENABLING WORK:
Sl.No. Item Submitted Remarks
1) Traffic impact study approved by Road Section, if
applicable for the project.
2) Approved site plan.
3) Service clearance for site. (NOC)
4) Copy of receipt from architectural section of
Building Permit Directorate confirming submittal
of architectural drawings to the Directorate.
5) Soil investigation report.
6) Shoring layout.
7) Shoring sections and details.
8) Detailed calculations for shoring from specialist
and approved by the consultant.
9) Depth of excavation.
Abu Dhabi Municipality March 2007
Page 3 of 6
BUILDING PERMITS DIRECTORATE
STRUCTURAL SECTION
SUBMISSION CHECK LIST
B) SUBSTRUCTURE:
Sl.No. Item Submitted Remarks
1) Completion of requirements for enabling works
as applicable.
2) Design philosophy and design criteria.
3) Foundation / substructure plans with complete
details.
4) Calculations for column loads by tributary area
method and by approved computer software.
5) Columns and shear wall layout showing reactions
from the most critical load combinations. (Design
load)
6) Detailed design calculations for proposed
foundation, including columns and shear walls,
as well as basement retaining walls, at
foundation level.
7) Schedule of columns with reinforcement and
sizes and sections.
8) Structural framing (Schematic design) for all
floors showing the assumed sizes of structural
elements.
9) An electronic copy of the structural 3D model for
the lateral stability analysis. The study should
include all structural elements and all the applied
loads.
10) Wind tunnel study if required.
11) Piling plan as applicable, showing the reactions
from the most critical load combinations (Service
loads).
12) Brief specifications and applicable notes for the
foundation & piles, presented on drawings.
13) Pile design by specialist and approved by the
consultant.
Abu Dhabi Municipality March 2007
Page 4 of 6
BUILDING PERMITS DIRECTORATE
STRUCTURAL SECTION
SUBMISSION CHECK LIST
Sl.No. Item Submitted Remarks
14) Piling details showing pile length, reinforcement
details, pile size and capacity, cut off & toe
levels.
15) Proposed location of tower crane within the
approved plot area
16) This check list should cover the latest Abu Dhabi
Municipality requirements for structural Section
submissions.
Abu Dhabi Municipality March 2007
Page 5 of 6
BUILDING PERMITS DIRECTORATE
STRUCTURAL SECTION
SUBMISSION CHECK LIST
C) SUPER STRUCTURE:
Sl.No. Item Submitted Remarks
1) Final structural drawings.
2) Detailed design calculations.
3) Schedule of columns with reinforcement and
sizes and detailed sections.
4) Detailed sectional plans and elevations for shear
walls showing all dimensions and reinforcement.
5) Schedule of beams, with reinforcement and
sizes, including typical beam elevation and
sections.
6) General notes for structural elements.
7) Plans, sections and details of swimming pools,
reinforced concrete water tanks, and significant
architectural features.
8) Plan & section for staircases showing all
dimensions and steel reinforcement.
NOTE: COMPLETE DESIGN PACKAGE:
The consultant may choose to make a final and complete submittal at one time. However,
the Directorate prefers that he makes preliminary design submittals at various significant
stages, and discusses the design philosophy and design criteria before preparing final
drawings, in order to avoid any dispute in the future.
Abu Dhabi Municipality March 2007
Page 6 of 6