Appendix G3 Construction Method Statement
Appendix G3 Construction Method Statement
MEMO
TO: Amanda Mileson
FROM: Riaan Bence
SUBJECT: Mushroom Farm – K73: Construction of the K73, a new dual
carriageway - Construction Method Statement for the extension of three
existing culverts under K58 Allandale Road, and the construction of one new
culvert for Water Use License Application
DATE: 19 January 2017
1. INTRODUCTION
The Gauteng Department of Roads and Transport is planning major road upgrades including the
construction of a new dual carriage way road, the K73 and upgrades to the K58 – Allandale Road. The
K73 will link Allandale Road with Woodmead Drive and is located between Barbeque Downs and
Kyalami Hills.
The K73 will cross the Jukskei river and wetland area, by means of a new bridge. The upgrades in
Allandale Road includes road widening in sections of the road with three existing culverts. These
culverts will be extended to suit the wider new road as well as the addition of culverts in the western
section of Allandale Road. The construction of the aforementioned bridge and extension of the existing
culverts is herein further discussed.
2. BACKGROUND
WSP I Parsons Brickerhoff was appointed by the Gauteng Department of Roads and Transport
undertake the engineering services for the upgrading of the roads associated with construction of the
K73.
The following roads were identified and will be upgraded as part of the K73 construction:
à Allandale Road;
à Woodmead Drive
à K73 – proposed dual carriageway
3. SCOPE OF METHODOLOGY
The methodology contained in this report is only applicable to the extension of the existing culverts and
the construction of a new culvert in Allandale Road.
à Laying of pipe and box culverts – to extend existing
à Addition of box culverts to assist with flow of stormwater.
à Demolition of existing inlet and outlet structures and reconstruction thereof.
4. PROPOSED CONSTRUCTION METODOLOGY
4.1 Construction method for permanent roads crossing wetlands
Fill embankments across wetlands are generally constructed on top of rockfill layers which provide
stability and dissipate pore water pressures. It is good practice to construct the fills at least 6 months
before the pavement layers are added on top. This allows for any settlement to take place without
causing any deformation in the new road surface. It also allows for the natural flow in the wetland to be
monitored to ensure that the drainage layers are functioning effectively.
In extreme conditions, it may not be practical, or safe, to excavate in the wetland. The alternative method
of ‘end tipping’ the rockfill to create a solid foundation for the road fill embankment would then be used.
The rock is tipped at the edge of the wetland and gradually pushed in until firm enough footing is
achieved. Subsequent loads can then be laced further into the wetland. Thus the rock fill is gradually
placed across the affected area.
A geo-grid or geotextile, as appropriate, is placed on top of the levelled rock fill, before carrying out
steps 5.1 i to 5.1 iv above.
Page 2 of 4
4.3 CONSTRUCTION METHOD FOR EXTENSION OF EXISTING CULVERTS
AND THE ADDITION OF BOX CULVERTS
i. Surveyor to indicate setting out positions of the various structural elements.
ii. Remove upper layer of wetland soils and stockpile locally. This is done to ensure the area can be
rehabilitated more effectively after construction is completed.
iii. Demolish existing inlet and outlet structures and cart away material.
iv. Excavate and level and compact surface for before placing the new pipe culvert or box culvert floor
slabs.
v. Cast box culvert floor slab with concrete and allow to cure.
vi. Lay pipe culvert in place.
vii. Set up formwork and reinforcement for inlet and outlet structures.
viii. Cast concrete for inlet and outlet structures.
ix. Pack gabions as per design to prevent soil erosion.
x. Reinstate the wetland soils that were removed and stockpiled prior to construction.
xi. Stabilise the soil with a fully biodegradable surface stabiliser such as Fibretex Geojute Slopesaver,
if required.
Page 3 of 4
à Appropriate measures such as the implementation of silt traps, or areas to contain silt before
entering the watercourse, should be devised such as sedimentation basins.
à Soil and spoil must not be stored within 100m of the watercourse.
Page 4 of 4