Contoh S-Curve

This document outlines the schedule and budget for a project to construct a 17,000 cubic meter aviation fuel storage tank over 15 months. It details the engineering, procurement, fabrication, construction and testing work packages. The project preparation phase in the first 3 months accounts for 1.75% of the total budget. Procurement makes up 52% of the budget and will occur between months 4-13. Fabrication and construction will take place between months 7-15, utilizing 40% of the total budget. Testing will be completed in month 15.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
447 views1 page

Contoh S-Curve

This document outlines the schedule and budget for a project to construct a 17,000 cubic meter aviation fuel storage tank over 15 months. It details the engineering, procurement, fabrication, construction and testing work packages. The project preparation phase in the first 3 months accounts for 1.75% of the total budget. Procurement makes up 52% of the budget and will occur between months 4-13. Fabrication and construction will take place between months 7-15, utilizing 40% of the total budget. Testing will be completed in month 15.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROYEK PEMBANGUNAN TANGKI TIMBUN AVTUR KAPASITAS 17.

000 KL DI SHAFTHI
"S CURVE INTERNAL "
MONTH OF
NAMA PEKERJAAN Cost Bobot 1 2 3 4 5 6 7 8 9 10 11 12 13 14
April Mei Juni Juli Agustus September Oktober November Desember Januari Februari Maret April Mei
PEKERJAAN PERSIAPAN 100.00 1.75%
Perijinan 18.00 0.32% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Project Management 18.00 0.32% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Mobilisasi Demobilisasi Material, alat & tenaga kerja 18.00 0.32% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Penyiapan air kerja, listrik kerja, peralatan komunikasi 6.00 0.11% 0.03% 0.03% 0.03% 0.03%
Water Sprayer (Tirai Air) 12.00 0.21% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Penyiapan Akses Jalan Kerja ( Demolish Bundwall) 4.00 0.07% 0.02% 0.02% 0.02%
Direksi keet & Penyimpanan Material 4.00 0.07% 0.02% 0.02% 0.02% 0.02%
Perlengkapan dan peralatan safety selama proyek 6.00 0.11% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
Welder Performance Quality Test (WPQT) 6.00 0.11% 0.03% 0.03% 0.03% 0.03%
Pekerjaan Soil Test 4.00 0.07% 0.02% 0.02% 0.02%
Pembersihan lokasi akibat pelaksanaan pekerjaan 4.00 0.07% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
ENGINEERING 100 2.25%
Engineering Proses 20 0.45% 0.15% 0.15% 0.15%
Engineering Mechanichal 20 0.45% 0.15% 0.15% 0.15%
Engineering Piping 15 0.34% 0.11% 0.11% 0.11%
Engineering Electrical 15 0.34% 0.11% 0.11% 0.11%
Engineering Instrumen 10 0.23% 0.08% 0.08% 0.08%
Engineering Civil 10 0.23% 0.08% 0.08% 0.08%
Asbuilt Drawing 10 0.23% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
PROCUREMENT
Procurement Civil 100.00 52.00%
Procurement Pondasi Tanki 1 x 17000 KL 22.00 11.44% 1.14% 1.14% 1.14% 4.00% 4.00%
Procurement Drain Tank Pit 8.00 4.16% 0.42% 0.42% 0.42% 1.46% 1.46%
Procurement Mechanical & Piping
Procurement Tangki 27.00 14.04% 1.40% 1.40% 1.40% 1.40% 4.21% 4.21%
Procurement Tank Appurtenance 10.00 5.20% 0.52% 0.52% 0.52% 0.52% 1.56% 1.56%
Procurement Drain Tank, Recoverry Vessel & Pompa 10.00 5.20% 0.52% 0.52% 0.52% 0.52% 1.56% 1.56%
Procurement Jalur Pipa BBM dan DRAIN 8.00 4.16% 0.69% 0.69% 0.69% 0.69% 0.69% 0.69%
Procurement Tank Fire System 5.00 2.60% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43%
Procurement Electrical
Procurement Electrical 5.00 2.60% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33%
Procurement Instrument
Procurement Instrument 5.00 2.60% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33%
FABRICATION & CONSTRUCTION
Construction Civil 100.00 40.00%
Construction Pondasi Tanki 1 x 17000 KL 20.00 8.00% 0.80% 0.80% 0.80% 0.80% 2.40% 2.40%
Construction Drain Tank Pit 8.00 3.20% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46% 0.46%
Fabrication & Construction Mekanikal & Piping
Fabrikasi On Workshop Tangki 12.00 4.80% 1.20% 1.20% 1.20% 1.20%
Construction Tangki 20.00 8.00% 1.33% 1.33% 1.33% 1.33% 1.33% 1.33%
Construction Tank Appurtenance 8.00 3.20% 0.64% 0.64% 0.64% 0.64% 0.64%
Construction Drain Tank & Recoverry Vessel 7.00 2.80% 1.40% 1.40%
Construction Pompa 5.00 2.00% 0.40% 0.40% 0.40% 0.40% 0.40%
Construction Jalur Pipa BBM dan Drain 5.00 2.00% 0.50% 0.50% 0.50% 0.50%
Cosntruction Tank Fire System 5.00 2.00% 0.50% 0.50% 0.50% 0.50%
Construction Electrical
Construction Electrical 5.00 2.00% 0.67% 0.67% 0.67%
Construction Instrument
Construction Instrument 5.00 2.00% 0.50% 0.50% 0.50% 0.50%
PEKERJAAN PENGETESAN
Pekerjaan Inspeksi & Tes tangki 100.00 4.00%
Vacum test 8.00 0.32% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Pengujian Coating (Thickness, Holiday Test dan Pull Off Test) 8.00 0.32% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
NDT Test 8.00 0.32% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Hydrostatic Test 20.00 0.80% 0.40% 0.40%
Kalibrasi Tanki 8.00 0.32% 0.32%
PEKERJAAN FINISHING
Commisioning test 28.00 1.12% 0.56% 0.56%
Soak Test 8.00 0.32% 0.16% 0.16%
Pekerjaan sertifikasi (SKPP) 12.00 0.48% 0.24% 0.24%
Planning Progress 30,800,000,000 100.00% 0.89% 0.89% 2.45% 4.97% 7.93% 12.34% 13.67% 17.17% 16.97% 7.00% 6.31% 5.66% 2.09% 1.67%
Acumulative schedule 0.89% 1.77% 4.22% 9.19% 17.12% 29.46% 43.13% 60.30% 77.26% 84.27% 90.58% 96.24% 98.33% 100.00%

April Mei Juni Juli Agustus September Oktober November Desember Januari Februari Maret April Mei

Emmy Yanuar
Manajer Divisi