EX-0035 Drilling - English API Formula Sheet TH
EX-0035 Drilling - English API Formula Sheet TH
EX-0035 Drilling - English API Formula Sheet TH
Gauge Problem Exercises are constructed from a completed kill sheet ‘filled-in’ with all relevant
volume and pressure calculations.
Each question is based on the strokes, pump rate, drill pipe and casing gauge readings at a
specific point in time during a well kill operation. Any one or a combination of these readings could
indicate the action required. Options are shown in the multiple-choice answers.
The casing and/or drill pipe pressures will only be relevant to the action if –
• The casing and/or drill pipe pressures given in the question are below the expected pressures,
or
• The casing and/or drill pipe pressures given in the question are 70 psi or more above the
expected pressures.
or
Pressure (psi)
TVD (ft) x 0.052
[Annular Pressure Loss (psi) ÷ TVD (ft) ÷ 0.052] + Mud Density (ppg)
Or
Or
10. NEW PUMP PRESSURE (psi) WITH NEW MUD DENSITY approximate
[Surface LOT pressure (psi) ÷ Shoe TVD (ft) ÷ 0.052] + LOT Mud Density (ppg)
or
Surface LOT Pressure (psi)
Shoe TVD (ft )× 0.052
+ LOT Mud Density (ppg)
February 2017 EX-0035 Version 2.0 Page 2 of 4
Printed copies are UNCONTROLLED: It is the user’s responsibility to verify printed material against the controlled document
Drilling - English API Formula Sheet
[Maximum Allowable Mud Density (ppg) – Current Mud Density (ppg)] x 0.052 x Shoe TVD (ft)
or
SIDPP (psi)
+ Original Mud Density (ppg)
TVD (ft )× 0.052
Rate of Increase in Surface Pressure (psi/hr) ÷ Drilling Mud Density (ppg) ÷ 0.052
or
21. LEVEL DROP PULLING REMAINING COLLARS OUT OF HOLE DRY (ft)
22. LEVEL DROP PULLING REMAINING COLLARS OUT OF HOLE WET (ft)
Overbalance (psi)× [Riser or Casing Capacity (bbl/ft)- Closed End Displacement (bbl/ft)]
Mud Gradient (psi/ft) × Closed End Displacement (bbl/ft)
Length of Dry Pipe (ft ) × Pipe Capacity (bbl/ft) × Drilling Mud Density (ppg)
Slug Density (ppg) - Drilling Mud Density (ppg)
[Air Gap (ft) + Water Depth (ft)] × Mud Density (ppg) − [Water Depth (ft) × Sea Water Density (ppg)]
TVD (ft) − Air Gap (ft) − Water Depth (ft)
Mud Density (ppg) × 0.052 × Casing Capacity (bbl/ft) × Unfilled Casing Height (ft)
Casing Capacity (bbl/ft) + Annular Capacity (bbl/ft)