0% found this document useful (0 votes)
463 views4 pages

Transformer DS

This document provides the technical specifications for a 1600 KVA transformer. It includes details on the transformer's ratings, components, dimensions, tests, and standard fittings. The transformer will be used for a sewage treatment plant project in Nellore Municipal Corporation that involves constructing decentralized plants, sewer networks, manholes, and house connections along with 5 years of operation and maintenance.

Uploaded by

juliyet v
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
463 views4 pages

Transformer DS

This document provides the technical specifications for a 1600 KVA transformer. It includes details on the transformer's ratings, components, dimensions, tests, and standard fittings. The transformer will be used for a sewage treatment plant project in Nellore Municipal Corporation that involves constructing decentralized plants, sewer networks, manholes, and house connections along with 5 years of operation and maintenance.

Uploaded by

juliyet v
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

L&T CONSTRUCTION Public Health and Municipal

Water and Effluent Treatment IC – Wastewater BU Engineering Department

Construction of Decentralized Sewage Treatment Plants with REV


any proven Technology including receiving sumps cum pumping
stations, Providing Sewer Network System in entire city DOCUMENT NO
PROJECT: including construction of Conventional Manholes & Precast .
0
Manholes, House Sewer Connections and Allied Works, O&M LE160315-E-WW-SW-DD-4418
for a period of 5 years complete, in Nellore Municipal
Corporation.
PREPARED CHECKED APPROVED SHEET
TITLE: Technical Datasheet for Transformer _55MLD Allipuram
PM BGV CC

TRANSFORMER
A. TECHNICAL SPECIFICATIONS
1. MAKE ESENNAR TRANSFORMERS (P) LTD.
TRANSFORMER - IS : 1180- (Part I) : 2014 &
2. REFERENCE STANDARD IS : 2026 – 2011
OIL – IS : 335 : 1993
RATED KVA HV 1600 KVA
3.
LV 1600 KVA
4. PHASES 3
5. SERVICE OUTDOOR
6. MOUNTING PLINTH
7. WOUND DOUBLE
8. TEMP. RISE IN OIL (⁰C) 40
9. BY RESISTANCE (⁰C) 45
10. AMBIENT TEMPERATURE (⁰C) 50
11. WINDING MATERIAL COPPER
12. TYPE OF COOLING ONAN
13. CORE MATERIAL, GRADE CRGO, M4 GRADE
14. CLASS OF INSULATION CLASS “A”
15. VECTOR GROUP Dyn 11
16. FREQUENCY (Hz.) 50
17. PHASE 3
INSULATION LEVEL (kV / kvp) .
18. H.V. 28 /75
L.V. 3/---
19. PRIMARY CONNECTION (HV) DELTA
20. PRIMARY VOLTS 11000 V
21. PRIMARY WIRES 3
22. PRIMARY RATED CURRENT 83.98 A
23. SECONDARY CONNECTION (LV) STAR
24. SECONDARY VOLTS 433 V
25. SECONDARY WIRES 4
26. SECONDARY RATED CURRENT 2133.40 A
27. SYSTEM FAULT LEVEL MVA AS PER IS 2026
L&T CONSTRUCTION Public Health and Municipal
Water and Effluent Treatment IC – Wastewater BU Engineering Department

Construction of Decentralized Sewage Treatment Plants with REV


any proven Technology including receiving sumps cum pumping
stations, Providing Sewer Network System in entire city DOCUMENT NO
PROJECT: including construction of Conventional Manholes & Precast .
0
Manholes, House Sewer Connections and Allied Works, O&M LE160315-E-WW-SW-DD-4418
for a period of 5 years complete, in Nellore Municipal
Corporation.
PREPARED CHECKED APPROVED SHEET
TITLE: Technical Datasheet for Transformer _55MLD Allipuram
PM BGV CC

TYPE ON PRIMARY WINDING FOR +5% TO -15% IN STEPS OF 2.5% ON LOAD


28.
PRIMARY VOLTAGE VARIATION TAP CHANGER
29. NO. OF SWITCH POSITIONS 9
AT 112.5%,COMBINED VOLTAGE &
30. FREQUENCY VARIATION FROM SHALL NOT EXCEED 1.9 TESLA
RATED VOLTAGE AND FREQUENCY
TERMINAL ARRANGEMENT H.V. CABLE BOX
31.
L.V. BUS DUCT
LOSSES
32. AT 50% LOADING 4500 W (Max.)
AT 100% LOADING 13500 W (Max.)
33. IMPEDENCE (Z) (%) HV - LV 6.25%
NO LOAD CURRENT (% OF RATED
34. LESS THAN 1.5%
CURRENT)
35. TOLERANCE IS:2026
B. WEIGHT DETAIL
CORE & WINDINGS WITH CLAMPS
36. 3050 Kgs. (Approx.)
(UNTAKING WEIGHT)
37. TANK & FITTINGS 1904 Kgs. (Approx.)
38. OIL 1760 Ltrs. (1496 Kgs.)
39. TOTAL WEIGHT 6450 Kgs. (Approx.)
C. DIMENSION DETAIL
TRANSFORMER DIMENSION
LENGTH (mm) 3250 (Approx.)
40.
BREADTH (mm) 2470 (Approx.)
HEIGHT (mm) 2210 (Approx.)
41. HV – LV ORIENTATION 180 DEGREE.
D. BUSHING DETAIL
42. STANDARD IS : 2099 & IS: 3347
43. PORCELAIN BUSHINGS HV 3
44. EPOXY BUSHING LV 4
E. PAINTING DETAIL
45. PAINTING LIGHT GREY POLYURETHANE PAINT
G. TESTS / ROUTINE TEST
46. TEST-ROUTINE TEST STANDARD AS PER IS : 1180 (Part 1) : 2014
47. RATIO TEST
48. POLARITY
L&T CONSTRUCTION Public Health and Municipal
Water and Effluent Treatment IC – Wastewater BU Engineering Department

Construction of Decentralized Sewage Treatment Plants with REV


any proven Technology including receiving sumps cum pumping
stations, Providing Sewer Network System in entire city DOCUMENT NO
PROJECT: including construction of Conventional Manholes & Precast .
0
Manholes, House Sewer Connections and Allied Works, O&M LE160315-E-WW-SW-DD-4418
for a period of 5 years complete, in Nellore Municipal
Corporation.
PREPARED CHECKED APPROVED SHEET
TITLE: Technical Datasheet for Transformer _55MLD Allipuram
PM BGV CC

49. PHASE ANGLE ERROR MEASUREMENT


50. I R VALUES
51. WINDING RESISTANCE
52. OPEN CIRCUIT TEST
53. SHORT CIRCUIT & IMPEDANCE TEST
54. SEPARATE SOURCE VOLTAGE TEST
55. INDUCED OVER VOLTAGE TEST
56. PRESSURE TEST
57. OIL LEAKAGE TEST
58. TYPE TEST CERTIFICATE OF 2.5MVA IS 1180 DONE AT CPRI.
F. STANDARD FITTINGS & ACCESSORIES
RATING & TERMINALMARKING PLATE – 1 No.
EARTHING TERMINALS – 2 Nos.
LIFTING LUGS – 4 Nos.
DRAIN VALVE WITH BLANKING PLATE - 1 No.
FILTER VALVE WITH BLANKING PLATE –1No.
CONSERVATOR -1 No.
CONSERVATOR OIL FILLING HOLE
WITH CAP – 2 Nos.
OIL LEVEL INDICATOR WITH MIN.
MARKING – 1 No.
DEHYDRATING BREATHER – 1 No.
CONSERVATOR DRAIN PLUG – 2 Nos.
STANDARD FITTINGS& AIR RELEASE DEVICE – 1 No.
59.
ACCESSORIES THERMOMETER POCKET – 1 No.
PRESSURE RELIEF VALVE – 1 No.
ROLLER UNI DIRECTIONAL – 4 Nos.
RADIATORS (DETACHABLE TYPE) – 6 Nos.
CABLE BOX (HV) – 1 No.
BUSDUCT (LV) – 1 No.
SEPARATE NEUTRAL TERMINAL – 1No.
ON CIRCUIT TAP CHANGER – 1 No.
O.T.I WITH ALARM & TRIP CONTACTS – 1 No.
BUCHHOLZ RELAY WITH ALARM & TRIP
CONTACTS – 1 |No.
RADIATOR VALVES – 12 Nos.
MARSHALLING BOX – 1 No.
L&T CONSTRUCTION Public Health and Municipal
Water and Effluent Treatment IC – Wastewater BU Engineering Department

Construction of Decentralized Sewage Treatment Plants with REV


any proven Technology including receiving sumps cum pumping
stations, Providing Sewer Network System in entire city DOCUMENT NO
PROJECT: including construction of Conventional Manholes & Precast .
0
Manholes, House Sewer Connections and Allied Works, O&M LE160315-E-WW-SW-DD-4418
for a period of 5 years complete, in Nellore Municipal
Corporation.
PREPARED CHECKED APPROVED SHEET
TITLE: Technical Datasheet for Transformer _55MLD Allipuram
PM BGV CC

DRAIN VALVE WITH BLANKING PLATE


(OLTC) – 1 No.
FILTER VALVE WITH BLANKING PLATE
(OLTC) –1No.
CURRENT TRANSFORMER (2150/5A) – 1No.
OLTC SURGE RELAY – 1 No.
RTCC - 1 No.
AVR - 1 No.
W.T.I WITH ALARM & TRIP CONTACTS – 1No.
W.T.I POCKET – 1No.
INSPECTION COVER – 1No.

M.O.G. WITH LOLA CONTACTS – 1No.

G. ENCLOSURE
1600 KVA-11000-433V
60. ET-GA-A4-01
(OLTC)GENERAL ASSEMBLY
GENERAL ASSEMBLY OF H.V
61. CABLE BOX WITH ET-GA-A4-02
DISCONNECTING CHAMBER
GENERAL ASSEMBLY L.V BUS
62. ET-GA-A4-03
DUCT
GENERAL ASSEMBLY
63. ET-GA-A4-04
MARSHALLING BOX
WIRING DIAGRAM OF
64. ET-GA-A4-05
MARSHALLING BOX
65. GENERAL ASSEMBLY OF RTCC ET-GA-A4-06
INTER CONNECTION DIAGRAM
66. AND TERMINAL ARRGT WITH ET-GA-A4-07
RTCC & OLTC
67. RATING AND DIAGRAM PLATE ET-GA-A4-08
68. PLINTH ARRANGEMENT ET-GA-A4-09
69. UNDER BASE ARRANGEMENT ET-GA-A4-10
70. OLTC SCHEMATIC DIAGRAM 2074250
ON LOAD GEARS GENERAL
71. 1001330
ARRANGEMENT
72. QAP NO. ETPL/EPEPL/16-17