Assignment 6
Assignment 6
A B C D
2- The ABC Cooling and Heating Company manufactures several different types of air
conditioners. Five departments are involved in the processing required for the products. A
summary of the processing sequences required for the five major products and the weekly
production volumes for the products are shown in the tables below along with the
department area. Based on the graph-based construction method, develop a block layout.
Product Process Sequence Weekly Production
1 ABC 150
2 ABED 200
3 ACE 50
4 ACBE 200
5 ADE 250
Fall 2013
A 1500
B 1500
C 1000
D 2000
E 2000
3- Explain the steps CRAFT would take with the following problem and determine the final
layout. Only two-way exchanges are to be considered.
From-To Chart
From To A B C D E
A - 3 2 1
B - 1 3
C 1 - 4
D -
E -
Initial Layout
A A A B B B
A A A C C C
A A A C C C
D D D E E E
D D D E E E