Design Calculations of Lightning Protection Systems - Part Twenty
Design Calculations of Lightning Protection Systems - Part Twenty
In Article " Design Calculations of Lightning Protection Systems – Part Two ", I indicated the lightning
protection design process involves a number of design steps as in below Fig.1.
Also, In above Article, I indicated that the risk assessment study can be done by (4) different methods
as follows:
Methods Of Calculations
For Risk Assessment Articles
Study
Design Calculations of Lightning Protection Systems –
Part Two
Design Calculations of Lightning Protection Systems –
First: Manual Method Part Three
(Equations And Tables Design Calculations of Lightning Protection Systems –
Method) as per IEC Part Four
62305-2 Design Calculations of Lightning Protection Systems –
Part Five
Design Calculations of Lightning Protection Systems –
Part Six
Design Calculations of Lightning Protection Systems –
Part Seven
First: Manual Method
Design Calculations of Lightning Protection Systems –
(Equations And Tables
Part Eight
Method) as per NFPA 780
Design Calculations of Lightning Protection Systems –
Part Nine
Design Calculations of Lightning Protection Systems –
Part Ten
Design Calculations of Lightning Protection Systems –
Second: Software Method
Part Eleven
For Performing The Risk
Design Calculations of Lightning Protection Systems –
Assessment Study
Part Twelve
Third: Excel Sheets
Method For Performing
Design Calculations of Lightning Protection Systems –
The Risk Assessment
Part thirteen
Study
Fourth: Online
Calculators Method Used Design Calculations of Lightning Protection Systems –
for Need for Lightning Part Fourteen
Protection calculations
In Article " Design Calculations of Lightning Protection Systems – Part Sixteen ", I explained the
following points:
Types and forms of Strike Termination Subsystem,
Sizing of Air Terminals Based on IEC 62305-3 and Based on BS EN 62305-3,
Sizing of Natural Air Terminals,
Positioning / Placement of Air Termination System Components.
The Class of LPS/LPL influences on the (3) Positioning Methods.
And I explained the Methods for Positioning of Air Terminals in the following Articles:
Today, I will explain Other Steps of the Lightning Protection Design Process.
For more information, please review the following Articles:
The number of down conductors depends on the perimeter of the external edges
of the roof (perimeter of the projection on the ground surface).( but at least two down-
conductors should be used on a structure).
The down conductors must be arranged to ensure that, starting at the exposed
corners of the structure, they are distributed as uniformly as possible to the perimeter.
(Note: A down-conductor should be installed at each exposed corner of the structure,
where this is possible).
However an exposed corner does not need a down conductor if the distance
between this exposed corner to the nearest down-conductors complies with the following
conditions:
1. The distance to both adjacent down-conductors is half the distance
according to Table#1 or smaller; or
2. The distance to one adjacent down-conductor is one-quarter of the distance
according to Table#1 or smaller.
The IEC 62305-3 (EN 62305-3) standard gives typical distances between down
conductors and ring conductors for each class of lightning protection system in Table#1 in
below.
Typical Distance
Class of LPS between down
conductors
I 10 m
II 10 m
III 15 m
IV 20 m
Note:
1- General Rule:
At least two down conductors shall be provided on any kind of structure, including
steeples.
Structures exceeding 76 m (250 ft) in perimeter shall have a down conductor for
every 30 m (100 ft) of perimeter or fraction thereof.
Lower roofs or projections that are located within a zone of protection shall not
be required to be included in the perimeter measurement.
2- Special Rules:
The total number of down conductors on structures having flat or gently sloping
roofs shall be such that the average distance between all down conductors does not
exceed 30 m (100 ft).
For a flat or gently sloping roof structure, only the perimeter of the roof areas
requiring protection shall be measured.
Example#1:
For a pitched roof structure shown in Fig.3 with spacing between shown points as
follows:
Points Space
1–2 40 m (130 ft)
2-3 26 m (85 ft)
3-4 26 m (85 ft)
4-5 26 m (85 ft)
5-1 26 m (85 ft)
Solution:
Total perimeter = 40 m (130 ft) + 26 m (85 ft) + 26 m (85 ft) + 26 m (85 ft) + 26 m (85 ft)
= 144 m (470 ft)
Since, the average distance between down conductors does not exceed 30 m (100 ft).
Number of
Area of building in m2
down conductors
100 - 400 2
400 - 700 3
700 - 1000 4
1000 - 1300 5
1300 – 1600 6
1600 - 1900 7
Table#2
Example#2:
If the total perimeter of intermediate school = 625 mt, Find the Minimum
required number of down conductors by the rules of thumb method if the
intermediate school height < 30 m?
Solution:
Since intermediate school height < 30 m , then use One down conductor for
each 30m of building perimeter.
If the air termination system consists of one rod, at least one down
conductor is needed. If the air termination system consists of individual
rods, at least one down conductor is needed for each rod.
If the air termination system consists of stretched wires, at least one
down conductor is needed at each wire end.
If the air termination system consists of meshed conductors, at least
two down conductor are needed, distributed around the perimeter of the
building to be protected.
Complete design drawings shall be submitted to the engineer for approval and
showing at least the following:
PART 1 – GENERAL
1.5. Quality Assurance: The LPS shall conform to the requirements and
standards
for LPS(s) in accordance with section of the standards and specifications.
PART 2 – PRODUCTS
2.1 Standard: The system furnished under this specification shall be the
standard
product of a manufacturer regularly engaged in the production of lightning
protection equipment and shall be the manufacturer’s latest approved design.
2.3 Materials: All lightning protection materials and components shall comply
in
weight, size and composition with the specifications and standards of the
most
current editions listed in section of the standards and specifications.
PART 3 – EXECUTION
3.2 Coordination: The lightning protection contractor will work with other
trade contractors to ensure a correct, neat and inconspicuous as practical
installation. It shall be the responsibility of the lightning protection
contractor
to assure a proper common bond to the appropriate grounded utilities; such
as
the electric service ground, incoming water and gas pipe, etc.
End Of Course
Lightning-2: Lightning System Protection Design and Calculations